TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/UP/WATER/155091/2022              (ii). Name of Project for which Forest Land is required : Diversion of 8.161809 Hectare of Forest Land for laying of Drinking Water Distribution Pipelines (Total KM. 96.30) under Jakhlaun Birdha, Dhorra, Balabehat, Kadesara Kalan and Mau Group of Villages Water Supply Scheme, District- Lalitpur (U.P.)              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Due to lack of ground water in Bundelkhand area, the main objective of this Drinking Water PipelineProject is to provide safe and drinking water to People of rural areas of District Lalitpur. In this project the large number of people will be benefitted.              (iv). File no. : 8B/UP/08/75/2023/FC              (v). State : Uttar Pradesh              (vi). Category of the Project : Drinking Water              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 8.161809
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onCompliance Report Submitted by State onStage-II Approval on
FP/UP/WATER/155091/202206/05/202226/05/2022  15/05/2022  10/05/2022   20/06/2022  19/05/2022  15/05/2022   27/06/2022   29/06/2022 Social Forestry Division Lalitpur :30/06/2022Bundelkhand Circle Jhansi:
  08/01/2023 (Social Forestry Division Lalitpur)

Uttar Pradesh:
10/01/2023
Uttar Pradesh:
21/03/2023
Lucknow:
28/03/2023
13/09/2023
By :Regional Office
Uttar Pradesh
11/03/2025
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Lucknow) on:19/04/2023  
Replied by State Government(Uttar Pradesh) on:10/05/2023  
Query raised by Regional Office (Lucknow) on:09/06/2023  
Replied by State Government(Uttar Pradesh) on:21/06/2023  
Query raised by State Government (Uttar Pradesh) on:20/04/2023  
Replied by Nodal Officer (Uttar Pradesh) on:10/05/2023  
Query raised by State Government (Uttar Pradesh) on:12/06/2023  
Replied by Nodal Officer (Uttar Pradesh) on:21/06/2023  
Query raised by Nodal Officer (Uttar Pradesh) on:16/01/2023  
Replied by Circle(Bundelkhand Circle Jhansi) on:06/02/2023  
Query raised by Nodal Officer (Uttar Pradesh) on:16/02/2023  
Replied by Circle(Bundelkhand Circle Jhansi) on:20/03/2023  
Query raised by Nodal Officer (Uttar Pradesh) on:20/03/2023  
Replied by Circle(Bundelkhand Circle Jhansi) on:21/03/2023  
Query raised by Nodal Officer (Uttar Pradesh) on:21/04/2023  
Replied by Circle(Bundelkhand Circle Jhansi) on:09/05/2023  
Query raised by Nodal Officer (Uttar Pradesh) on:12/06/2023  
Replied by Circle(Bundelkhand Circle Jhansi) on:16/06/2023  
Query raised by Circle (Bundelkhand Circle Jhansi) on:18/01/2023  
Replied by DFO (Social Forestry Division Lalitpur) on:02/02/2023  
Query raised by Circle (Bundelkhand Circle Jhansi) on:17/02/2023  
Query raised by Circle (Bundelkhand Circle Jhansi) on:20/03/2023  
Query raised by Circle (Bundelkhand Circle Jhansi) on:03/05/2023  
Query raised by Circle (Bundelkhand Circle Jhansi) on:04/05/2023  
Query raised by Circle (Bundelkhand Circle Jhansi) on:13/06/2023  
Query raised by Circle (Bundelkhand Circle Jhansi) on:15/06/2023  
Query raised by DFO (Social Forestry Division Lalitpur) on:02/07/2022  
Replied by UA on :06/07/2022  
Query raised by DFO (Social Forestry Division Lalitpur) on:08/07/2022  
Replied by UA on :09/07/2022  
Query raised by DFO (Social Forestry Division Lalitpur) on:13/07/2022  
Replied by UA on :16/07/2022  
Query raised by DFO (Social Forestry Division Lalitpur) on:18/07/2022  
Replied by UA on :18/07/2022  
Query raised by DFO (Social Forestry Division Lalitpur) on:29/07/2022  
Replied by UA on :09/08/2022  
Query raised by DFO (Social Forestry Division Lalitpur) on:10/08/2022  
Replied by UA on :02/11/2022  
Query raised by DFO (Social Forestry Division Lalitpur) on:03/11/2022  
Replied by UA on :07/11/2022  
Query raised by DFO (Social Forestry Division Lalitpur) on:14/11/2022  
Replied by UA on :03/12/2022  
Query raised by DFO (Social Forestry Division Lalitpur) on:05/12/2022  
Replied by UA on :06/12/2022  
Query raised by DFO (Social Forestry Division Lalitpur) on:06/12/2022  
Replied by UA on :09/12/2022  
Query raised by DFO (Social Forestry Division Lalitpur) on:09/12/2022  
Replied by UA on :15/12/2022  
Query raised by DFO (Social Forestry Division Lalitpur) on:17/12/2022  
Replied by UA on :30/12/2022  
Query raised by DFO (Social Forestry Division Lalitpur) on:20/01/2023  
Replied by UA on :24/01/2023  
Query raised by DFO (Social Forestry Division Lalitpur) on:20/02/2023  
Replied by UA on :21/02/2023  
D. Essential Details Sought History (Stage-II)
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & User Agency
Query raised by Regional Office (Lucknow) on:21/04/2025  
Query raised by State Government (Uttar Pradesh) on:17/06/2025  
Query raised by Nodal Officer on:17/06/2025  
NOTE:- Proposal is pending at User Agency due to EDS raised by RO for Stage-II .