TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/UP/TRANS/44753/2020              (ii). Name of Project for which Forest Land is required : LEASE RENEWAL OF 400 KV LILO OBRA TRANSMISSION LINE, PASSING THROUGH THE FOREST DIVISION:OBRA , DISTRICT:SONBHADRA              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : LEASE RENEWAL OF 400 KV LILO OBRA TRANSMISSION LINE Passing through Forest Division Obra,District:Sonbhadra              (iv). State : Uttar Pradesh              (v). Category of the Project : Transmission Line              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 7.5118
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/UP/TRANS/44753/202022/07/202018/12/2020  14/08/2020  31/07/2020   30/12/2020  31/10/2020  06/08/2020   31/12/2020   07/01/2021 Forest Division Obra :19/01/2021Mirzapur Circle Mirzapur:
  25/10/2021 (Forest Division Obra)

Uttar Pradesh:
26/12/2022
Uttar Pradesh:
30/12/2022
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by State Government (Uttar Pradesh) on:27/01/2023  
Replied by Nodal Officer (Uttar Pradesh) on:03/04/2023  
Query raised by State Government (Uttar Pradesh) on:25/05/2023  
Replied by Nodal Officer (Uttar Pradesh) on:17/07/2023  
Query raised by Nodal Officer (Uttar Pradesh) on:31/01/2023  
Replied by Circle(Mirzapur Circle Mirzapur) on:29/03/2023  
Query raised by Nodal Officer (Uttar Pradesh) on:26/05/2023  
Replied by Circle(Mirzapur Circle Mirzapur) on:17/07/2023  
Query raised by Circle (Mirzapur Circle Mirzapur) on:28/10/2021  
Replied by DFO (Forest Division Obra) on:24/01/2022  
Query raised by Circle (Mirzapur Circle Mirzapur) on:27/01/2022  
Replied by DFO (Forest Division Obra) on:13/05/2022  
Query raised by Circle (Mirzapur Circle Mirzapur) on:23/05/2022  
Replied by DFO (Forest Division Obra) on:08/08/2022  
Query raised by Circle (Mirzapur Circle Mirzapur) on:11/08/2022  
Replied by DFO (Forest Division Obra) on:20/12/2022  
Query raised by Circle (Mirzapur Circle Mirzapur) on:02/02/2023  
Replied by DFO (Forest Division Obra) on:23/03/2023  
Query raised by Circle (Mirzapur Circle Mirzapur) on:29/05/2023  
Replied by DFO (Forest Division Obra) on:10/07/2023  
Query raised by DFO (Forest Division Obra) on:01/07/2021  
Replied by UA on :09/09/2021  
Query raised by DFO (Forest Division Obra) on:16/11/2021  
Replied by UA on :30/11/2021  
Query raised by DFO (Forest Division Obra) on:16/06/2022  
Replied by UA on :28/06/2022  
Query raised by DFO (Forest Division Obra) on:14/07/2022  
Replied by UA on :06/08/2022  
Query raised by DFO (Forest Division Obra) on:20/08/2022  
Replied by UA on :21/09/2022  
Query raised by DFO (Forest Division Obra) on:29/09/2022  
Replied by UA on :19/11/2022  
Query raised by DFO (Forest Division Obra) on:01/12/2022  
Replied by UA on :16/12/2022  
Query raised by DFO (Forest Division Obra) on:17/02/2023  
Replied by UA on :03/03/2023  
Query raised by DFO (Forest Division Obra) on:30/05/2023  
Replied by UA on :30/06/2023  
NOTE:- Proposal is pending at State Government .