TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/UP/TRANS/42524/2019              (ii). Name of Project for which Forest Land is required : 765 kV Ghatampur-Hapur S/C Transmission Line              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Proposal for Diversion of Reserve & Protected Forest Land in Kanpur Nagar, Kanpur Dehat, Auraiya, Etawah, Mainpuri, Kannauj, Etah, Kasganj, Aligarh, Bulandshahar & Hapur Districts for construction of 765 kV Ghatampur- Hapur Transmission line.              (iv). File no. : 8B/UP/04/169/2020              (v). State : Uttar Pradesh              (vi). Category of the Project : Transmission Line              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 16.5761
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onCompliance Report Submitted by State onStage-II Approval on
FP/UP/TRANS/42524/201922/12/201926/12/2019   11/03/2020   12/03/2020   30/05/2020 Social Forestry Division Kanpur Nagar :01/06/2020
Forest Division Kanpur Dehat :01/06/2020
Auraiya :01/06/2020
Social Forestry Division Etawah :01/06/2020
Kannauj :01/06/2020
Social Forestry Division Mainpuri :01/06/2020
Social Forestry Division Etah :01/06/2020
Forest Division Kashiram Nagar :01/06/2020
Social Forestry Division Aligarh :01/06/2020
Social Forestry Division Bulandshahar :01/06/2020
Forest Division Hapur :01/06/2020
Meerut Circle Meerut:
  19/09/2020 (Social Forestry Division Bulandshahar)

Meerut Circle Meerut:
  19/09/2020 (Forest Division Hapur)

Aligarh Circle Aligarh:
  21/09/2020 (Forest Division Kashiram Nagar)

Kanpur Circle Kanpur:
  16/07/2020 (Social Forestry Division Kanpur Nagar)

Kanpur Circle Kanpur:
  20/07/2020 (Kannauj)

Aligarh Circle Aligarh:
  21/07/2020 (Social Forestry Division Aligarh)

Kanpur Circle Kanpur:
  23/07/2020 (Forest Division Kanpur Dehat)

Kanpur Circle Kanpur:
  07/08/2020 (Auraiya)

Aligarh Circle Aligarh:
  07/08/2020 (Social Forestry Division Etah)

Kanpur Circle Kanpur:
  06/06/2020 (Social Forestry Division Etawah)

Agra Circle Agra:
  14/10/2020 (Social Forestry Division Mainpuri)

Uttar Pradesh:
06/11/2020
Uttar Pradesh:
11/11/2020
Lucknow:
24/11/2020
24/12/2020
By :Regional Office
Uttar Pradesh
21/04/2025
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by Nodal Officer (Uttar Pradesh) on:09/11/2020  
Replied by Circle(Agra Circle Agra) on:09/11/2020  
Query raised by Nodal Officer (Uttar Pradesh) on:09/11/2020  
Replied by Circle(Kanpur Circle Kanpur) on:10/11/2020  
Query raised by Circle (Agra Circle Agra) on:14/10/2020  
Replied by DFO (Social Forestry Division Mainpuri) on:15/10/2020  
Query raised by Circle (Agra Circle Agra) on:20/10/2020  
Replied by DFO (Social Forestry Division Mainpuri) on:23/10/2020  
Query raised by Circle (Agra Circle Agra) on:26/10/2020  
Replied by DFO (Social Forestry Division Mainpuri) on:27/10/2020  
Query raised by Circle (Kanpur Circle Kanpur) on:05/11/2020  
Replied by DFO (Auraiya) on:05/11/2020  
Query raised by Circle (Kanpur Circle Kanpur) on:09/11/2020  
Replied by DFO (Forest Division Kanpur Dehat) on:09/11/2020  
Query raised by DFO (Forest Division Hapur) on:25/06/2020  
Replied by UA on :14/07/2020  
Query raised by DFO (Social Forestry Division Bulandshahar) on:25/06/2020  
Replied by UA on :14/07/2020  
Query raised by DFO (Social Forestry Division Bulandshahar) on:04/08/2020  
Replied by UA on :07/08/2020  
Query raised by DFO (Forest Division Hapur) on:04/08/2020  
Replied by UA on :07/08/2020  
Query raised by DFO (Social Forestry Division Mainpuri) on:10/08/2020  
Replied by UA on :28/08/2020  
Query raised by DFO (Forest Division Kashiram Nagar) on:15/09/2020  
Replied by UA on :16/09/2020  
Query raised by DFO (Forest Division Kanpur Dehat) on:09/11/2020  
Replied by UA on :09/11/2020  
D. Essential Details Sought History (Stage-II)
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & User Agency
Query raised by Regional Office (Lucknow) on:06/05/2025  
Query raised by State Government (Uttar Pradesh) on:17/06/2025  
Query raised by Nodal Officer on:21/06/2025  
NOTE:- Proposal is pending at User Agency due to EDS raised by RO for Stage-II .