| Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
|
1
|
DFO (Forest Division Renukoot)
|
EDS
|
User Agency (vivek.kumar@adityabirla.com)
|
19/02/2021
|
Eds letter attached.
|
|
|
2
|
User Agency (vivek.kumar@adityabirla.com)
|
REPLY
|
DFO (Forest Division Renukoot)
|
20/03/2021
|
The correction have been made as per the instruction received
|
|
|
3
|
CF (Mirzapur Circle Mirzapur)
|
EDS
|
DFO (Forest Division Renukoot)
|
16/09/2021
|
N0 hard sennd
|
|
|
4
|
DFO (Forest Division Renukoot)
|
REPLY
|
CF (Mirzapur Circle Mirzapur)
|
21/09/2021
|
Hardcopy Send
|
|
|
5
|
Regional Office
|
EDS
|
State secretary
|
11/04/2022
|
EDS
|
|
|
6
|
State secretary
|
EDS
|
Nodal Officer
|
11/04/2022
|
EDS
|
|
|
7
|
Nodal Officer
|
EDS
|
CF (Mirzapur Circle Mirzapur)
|
11/04/2022
|
EDS letter Attached.
|
|
|
8
|
CF (Mirzapur Circle Mirzapur)
|
EDS
|
DFO (Forest Division Renukoot)
|
19/04/2022
|
Eds letter attached
|
|
|
9
|
DFO (Forest Division Renukoot)
|
EDS
|
User Agency (vivek.kumar@adityabirla.com)
|
22/04/2022
|
Eds letter attached
|
|
|
10
|
User Agency (vivek.kumar@adityabirla.com)
|
REPLY
|
DFO (Forest Division Renukoot)
|
08/08/2022
|
The correction have been made as per the instruction received
|
|
|
11
|
DFO (Forest Division Renukoot)
|
EDS
|
User Agency (vivek.kumar@adityabirla.com)
|
10/08/2022
|
hardcopy not submitted.
|
|
|
12
|
User Agency (vivek.kumar@adityabirla.com)
|
REPLY
|
DFO (Forest Division Renukoot)
|
11/08/2022
|
The correction have been made as per the instruction received
|
|
|
13
|
DFO (Forest Division Renukoot)
|
EDS
|
User Agency (vivek.kumar@adityabirla.com)
|
16/08/2022
|
Report/Hardcopy required.
|
|
|
14
|
User Agency (vivek.kumar@adityabirla.com)
|
REPLY
|
DFO (Forest Division Renukoot)
|
19/12/2022
|
The correction have been made as per the instruction received
|
|
|
15
|
DFO (Forest Division Renukoot)
|
EDS
|
User Agency (vivek.kumar@adityabirla.com)
|
20/12/2022
|
As per EDS Letter Point-1,3 online Compliance not completed.
|
|
|
16
|
User Agency (vivek.kumar@adityabirla.com)
|
REPLY
|
DFO (Forest Division Renukoot)
|
21/12/2022
|
The correction have been made as per the instruction received
|
|
|
17
|
DFO (Forest Division Renukoot)
|
REPLY
|
CF (Mirzapur Circle Mirzapur)
|
24/12/2022
|
The correction have been made as per the instruction received.
|
|
|
18
|
CF (Mirzapur Circle Mirzapur)
|
EDS
|
DFO (Forest Division Renukoot)
|
24/12/2022
|
no hard copy recive.
|
|
|
19
|
DFO (Forest Division Renukoot)
|
REPLY
|
CF (Mirzapur Circle Mirzapur)
|
24/12/2022
|
The correction have been made as per the instruction received.
|
|
|
20
|
CF (Mirzapur Circle Mirzapur)
|
REPLY
|
Nodal Officer
|
09/01/2023
|
Eds letter hasbeen remove
|
|
|
21
|
Nodal Officer
|
EDS
|
CF (Mirzapur Circle Mirzapur)
|
11/01/2023
|
EDS letter attached.
|
|
|
22
|
CF (Mirzapur Circle Mirzapur)
|
EDS
|
DFO (Forest Division Renukoot)
|
11/01/2023
|
Eds letterattached
|
|
|
23
|
DFO (Forest Division Renukoot)
|
EDS
|
User Agency (vivek.kumar@adityabirla.com)
|
16/01/2023
|
Eds letter attached.
|
|
|
24
|
User Agency (vivek.kumar@adityabirla.com)
|
REPLY
|
DFO (Forest Division Renukoot)
|
07/02/2023
|
The correction have been made as per the instruction received
|
|
|
25
|
DFO (Forest Division Renukoot)
|
REPLY
|
CF (Mirzapur Circle Mirzapur)
|
13/02/2023
|
The correction have been made as per the instruction received.
|
|
|
26
|
CF (Mirzapur Circle Mirzapur)
|
REPLY
|
Nodal Officer
|
15/02/2023
|
Eds letter hasbeen remove
|
|
|
27
|
Nodal Officer
|
REPLY
|
State secretary
|
16/02/2023
|
EDS Removed.
|
|
|
28
|
State secretary
|
REPLY
|
Regional Office
|
16/02/2023
|
EDS Removed.
|
|
|
29
|
Regional Office
|
EDS
|
State secretary
|
31/03/2023
|
EDS
|
|
|
30
|
State secretary
|
EDS
|
Nodal Officer
|
31/03/2023
|
eds
|
|
|
31
|
Nodal Officer
|
EDS
|
CF (Mirzapur Circle Mirzapur)
|
03/04/2023
|
EDS letter attached.
|
|
|
32
|
CF (Mirzapur Circle Mirzapur)
|
EDS
|
DFO (Forest Division Renukoot)
|
03/04/2023
|
Eds letter attached
|
|
|
33
|
DFO (Forest Division Renukoot)
|
EDS
|
User Agency (vivek.kumar@adityabirla.com)
|
03/04/2023
|
Eds letter attached
|
|
|
34
|
User Agency (vivek.kumar@adityabirla.com)
|
REPLY
|
DFO (Forest Division Renukoot)
|
19/04/2023
|
The correction have been made as per the instruction received
|
|
|
35
|
DFO (Forest Division Renukoot)
|
EDS
|
User Agency (vivek.kumar@adityabirla.com)
|
25/04/2023
|
hardcopy not submitted.
|
|
|
36
|
User Agency (vivek.kumar@adityabirla.com)
|
REPLY
|
DFO (Forest Division Renukoot)
|
06/07/2023
|
The correction have been made as per the instruction received
|
|
|
37
|
DFO (Forest Division Renukoot)
|
EDS
|
User Agency (vivek.kumar@adityabirla.com)
|
07/07/2023
|
information Required as per Letter Attached
|
|
|
38
|
User Agency (vivek.kumar@adityabirla.com)
|
REPLY
|
DFO (Forest Division Renukoot)
|
27/07/2023
|
The correction have been made as per the instruction received
|
|
|
39
|
DFO (Forest Division Renukoot)
|
REPLY
|
CF (Mirzapur Circle Mirzapur)
|
27/07/2023
|
EDS Letter as per Attached intuition
|
|
|
40
|
CF (Mirzapur Circle Mirzapur)
|
REPLY
|
Nodal Officer
|
31/07/2023
|
Eds letter hasbeen remove
|
|
|
41
|
Nodal Officer
|
REPLY
|
State secretary
|
01/08/2023
|
EDS Removed.
|
|
|
42
|
State secretary
|
REPLY
|
Regional Office
|
01/08/2023
|
EDS Removed.
|
|
|
43
|
Regional Office
|
EDS
|
State secretary
|
30/01/2025
|
EDS
|
|
|
44
|
State secretary
|
EDS
|
Nodal Officer
|
24/02/2025
|
eds
|
|
|
45
|
Nodal Officer
|
EDS
|
CF (Mirzapur Circle Mirzapur)
|
24/02/2025
|
eds letter attached.
|
|
|
46
|
CF (Mirzapur Circle Mirzapur)
|
EDS
|
DFO (Forest Division Renukoot)
|
24/02/2025
|
EDS Letter Attached.
|
|
|
47
|
DFO (Forest Division Renukoot)
|
EDS
|
User Agency (vivek.kumar@adityabirla.com)
|
28/04/2025
|
EDS Letter attached as per Instarction
|
|
|
48
|
User Agency (vivek.kumar@adityabirla.com)
|
REPLY
|
DFO (Forest Division Renukoot)
|
20/05/2025
|
The correction have been made as per the instruction received
|
|
|
49
|
DFO (Forest Division Renukoot)
|
EDS
|
User Agency (vijaykant.dubey@adityabirla.com)
|
24/05/2025
|
??????? ??0?0 Geo-referenced map and Toposheet not Received in the Office
|
|
|
50
|
User Agency (vijaykant.dubey@adityabirla.com)
|
REPLY
|
DFO (Forest Division Renukoot)
|
09/09/2025
|
The correction have been made as per the instruction received
|
|
|
51
|
DFO (Forest Division Renukoot)
|
REPLY
|
CF (Mirzapur Circle Mirzapur)
|
18/12/2025
|
EDS Lette Attached
|
|
|
52
|
CF (Mirzapur Circle Mirzapur)
|
REPLY
|
Nodal Officer
|
22/12/2025
|
EDS letter Attached.
|
|
|
53
|
Nodal Officer
|
EDS
|
CF (Mirzapur Circle Mirzapur)
|
22/12/2025
|
pointwise reply of eds raised by GoI has not been uploaded.
|
|
|
54
|
CF (Mirzapur Circle Mirzapur)
|
EDS
|
DFO (Forest Division Renukoot)
|
26/12/2025
|
The point-wise response to the EDS raised by the Government of India has not been uploaded. Ensure that the point-wise report is uploaded.
|
|
|
55
|
DFO (Forest Division Renukoot)
|
REPLY
|
CF (Mirzapur Circle Mirzapur)
|
02/01/2026
|
EDS Lt no 2221
|
|
|
56
|
CF (Mirzapur Circle Mirzapur)
|
REPLY
|
Nodal Officer
|
06/01/2026
|
EDS Letter Attached.
|
|
|
57
|
Nodal Officer
|
REPLY
|
State secretary
|
07/01/2026
|
EDS Removed.
|
|
|
58
|
State secretary
|
REPLY
|
Regional Office
|
07/01/2026
|
EDS Removed.
|
|