TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/UP/TRANS/31506/2018              (ii). Name of Project for which Forest Land is required : 765kV D/C Orai - Aligarh Transmission line Part-4 of PkgTE09 under WR - NR IRSS Scheme              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : 765kV D/C Orai-Aligarh transmission line part-IV associated with Inter - Regional system strengthening scheme for Western Region (WR)- Northern region(NR. 765/400kV GIS Sub-station at village Mohsanpur, Tehsil- Khair, District- Aligarh (UP)              (iv). File no. : 8B/UP/04/22/2018/FC              (v). State : Uttar Pradesh              (vi). Category of the Project : Transmission Line              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 1.6677
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/UP/TRANS/31506/201825/01/201829/01/2018   29/01/2018   30/01/2018   02/02/2018

Social Forestry Division Hathras :02/02/2018


Social Forestry Division Aligarh :02/02/2018

Aligarh Circle Aligarh:
  19/02/2018 (Social Forestry Division Aligarh)

Aligarh Circle Aligarh:
  20/02/2018 (Social Forestry Division Hathras)

Uttar Pradesh:
22/02/2018
Uttar Pradesh:
27/02/2018
Lucknow:
27/02/2018
19/11/2018
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Lucknow) on:23/03/2018  
Replied by State Government(Uttar Pradesh) on:01/11/2018  
Query raised by State Government (Uttar Pradesh) on:26/03/2018  
Replied by Nodal Officer (Uttar Pradesh) on:01/11/2018  
Query raised by Nodal Officer (Uttar Pradesh) on:05/04/2018  
Replied by Circle(Aligarh Circle Aligarh) on:24/10/2018  
Query raised by Nodal Officer (Uttar Pradesh) on:26/10/2018  
Replied by Circle(Aligarh Circle Aligarh) on:29/10/2018  
Query raised by Circle (Aligarh Circle Aligarh) on:21/02/2018  
Replied by DFO (Social Forestry Division Aligarh) on:21/02/2018  
Query raised by Circle (Aligarh Circle Aligarh) on:10/04/2018  
Replied by DFO (Social Forestry Division Hathras) on:12/10/2018  
Query raised by DFO (Social Forestry Division Aligarh) on:05/02/2018  
Replied by UA on :08/02/2018  
Query raised by DFO (Social Forestry Division Hathras) on:11/04/2018  
Replied by UA on :03/09/2018  
Query raised by DFO (Social Forestry Division Hathras) on:04/09/2018  
Replied by UA on :14/09/2018  