  (i). Proposal No. : FP/UP/TRANS/29629/2017              (ii). Name of Project for which Forest Land is required : Protected Forest Land Proposed to be diverted for 11 KV Transmission line on NH-76(Allhabad-Banda) Road from km.349 to 332(RHS) in Chitrakoot District              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Construction of 11 KV Transmission line on NH-76(Allhabad-Banda) Road from km.349 to 332(RHS) in Chitrakoot Distric for power supply to Mau Drinking water Scheme in Chitrakoot District              (iv). File no. : 8B/UP/04/38/2018              (v). State : Uttar Pradesh              (vi). Category of the Project : Transmission Line              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 25.5
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/UP/TRANS/29629/201707/11/201720/12/2017  19/12/2017  11/12/2017  08/11/2017   28/12/2017  20/12/2017  19/12/2017  08/12/2017   28/12/2017   29/01/2018 Forest Division Chitrakoot (Karvi) :29/01/2018Chitrakoot Circle Banda:
  10/03/2018 (Forest Division Chitrakoot (Karvi))

Uttar Pradesh:
16/03/2018
Uttar Pradesh:
23/03/2018
Lucknow:
03/04/2018
05/10/2018
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Lucknow) on:16/05/2018  
Replied by State Government(Uttar Pradesh) on:15/06/2018  
Query raised by Regional Office (Lucknow) on:29/06/2018  
Replied by State Government(Uttar Pradesh) on:28/08/2018  
Query raised by Regional Office (Lucknow) on:31/08/2018  
Replied by State Government(Uttar Pradesh) on:28/09/2018  
Query raised by State Government (Uttar Pradesh) on:17/05/2018  
Replied by Nodal Officer (Uttar Pradesh) on:31/05/2018  
Query raised by State Government (Uttar Pradesh) on:03/07/2018  
Replied by Nodal Officer (Uttar Pradesh) on:03/07/2018  
Query raised by State Government (Uttar Pradesh) on:18/09/2018  
Replied by Nodal Officer (Uttar Pradesh) on:18/09/2018  
Query raised by Nodal Officer (Uttar Pradesh) on:20/03/2018  
Replied by Circle(Chitrakoot Circle Banda) on:23/03/2018  
Query raised by Nodal Officer (Uttar Pradesh) on:18/05/2018  
Replied by Circle(Chitrakoot Circle Banda) on:24/05/2018  
Query raised by Circle (Chitrakoot Circle Banda) on:23/03/2018  
Replied by DFO (Forest Division Chitrakoot (Karvi)) on:23/03/2018  
Query raised by Circle (Chitrakoot Circle Banda) on:21/05/2018  
Replied by DFO (Forest Division Chitrakoot (Karvi)) on:22/05/2018  
Query raised by DFO (Forest Division Chitrakoot (Karvi)) on:02/02/2018  
Replied by UA on :09/03/2018  
NOTE:- Stage-I Approval accorded by : Regional Office .