  (i). Proposal No. : FP/UP/TRANS/26973/2017              (ii). Name of Project for which Forest Land is required : laying of 132kV Underground cable along NH28C for construction of 132kV Ram sanehi ghat-burwal Tss line              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : 132kV Line is being constructed for burhwal railway for which underground cable is being laid along NH28C by UPPTCL at Ramnagar Barabanki              (iv). File no. : P-128/14-2-2017-800(124)/2017              (v). State : Uttar Pradesh              (vi). Category of the Project : Transmission Line              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.06048
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentStage-I Approval onStage-II Approval on
FP/UP/TRANS/26973/201707/07/201727/07/2017  19/07/2017  13/07/2017   28/07/2017  22/07/2017  17/07/2017   01/08/2017   13/09/2017 Social Forestry Division Barabanki :14/09/2017Saryu Circle Faizabad:
  15/09/2017 (Social Forestry Division Barabanki)

Uttar Pradesh:
28/09/2017
Uttar Pradesh:
11/10/2017
08/12/2017
By :State Government
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by Nodal Officer (Uttar Pradesh) on:04/10/2017  
Replied by Circle(Saryu Circle Faizabad) on:06/10/2017  
Query raised by Circle (Saryu Circle Faizabad) on:05/10/2017  
Replied by DFO (Social Forestry Division Barabanki) on:06/10/2017  
NOTE:- Stage-I Approval accorded by : State Government .