TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/UP/THE/36097/2018              (ii). Name of Project for which Forest Land is required : Regularization of 555.759 ha of diverted forest land for the construction of Rihand Super Thermal Power Project under Renukoot Forest Division in Sonebhadra district of Uttar Pradesh              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Rihand Super Thermal Power Project is a coal based power plants of NTPC Limited. The power plant is located at Rihand Nagar Bijpur under Renukoot Forest division in Sonbhadra district of Uttar Pradesh. Rihand Super Thermal Power Station has an installed capacity of 3000 MW. The First unit was commis              (iv). File no. : 8-412/1989-FC (VOL-III)              (v). State : Uttar Pradesh              (vi). Category of the Project : Thermal              (vii). Shape of forest land proposed to be diverted : Non Linear              (viii). Area of forest land proposed for diversion(in ha.): 555.759
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentMoEFCC,New DelhiRegional Office(SIR) uploaded onStage-I Approval onStage-II Approval on
FP/UP/THE/36097/201803/11/201827/04/2022  18/02/2022  26/03/2021  12/03/2020  14/11/2018   19/05/2022  05/04/2022  04/01/2022  12/03/2021  03/03/2020   31/05/2022   12/10/2022 Forest Division Renukoot :17/11/2022Mirzapur Circle Mirzapur:
  01/12/2022 (Forest Division Renukoot)

Uttar Pradesh:
21/12/2022
Uttar Pradesh:
13/10/2023
12/06/2024
  
C. Essential Details Sought History
Communication between MoEFCC,New Delhi & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by MoEFCC,New Delhi on 02/08/2024  
Query raised by State Government (Uttar Pradesh) on:21/11/2023  
Replied by Nodal Officer (Uttar Pradesh) on:22/11/2023  
Query raised by State Government (Uttar Pradesh) on:01/02/2024  
Replied by Nodal Officer (Uttar Pradesh) on:14/02/2024  
Query raised by State Government (Uttar Pradesh) on:28/08/2024  
Query raised by Nodal Officer (Uttar Pradesh) on:02/01/2023  
Replied by Circle(Mirzapur Circle Mirzapur) on:20/03/2023  
Query raised by Nodal Officer (Uttar Pradesh) on:03/04/2023  
Replied by Circle(Mirzapur Circle Mirzapur) on:06/07/2023  
Query raised by Nodal Officer (Uttar Pradesh) on:25/07/2023  
Replied by Circle(Mirzapur Circle Mirzapur) on:26/07/2023  
Query raised by Nodal Officer (Uttar Pradesh) on:31/07/2023  
Replied by Circle(Mirzapur Circle Mirzapur) on:10/10/2023  
Query raised by Nodal Officer (Uttar Pradesh) on:12/10/2023  
Replied by Circle(Mirzapur Circle Mirzapur) on:12/10/2023  
Query raised by Nodal Officer (Uttar Pradesh) on:02/02/2024  
Replied by Circle(Mirzapur Circle Mirzapur) on:14/02/2024  
Query raised by Nodal Officer (Uttar Pradesh) on:29/08/2024  
Replied by Circle() on:  
Query raised by Circle (Mirzapur Circle Mirzapur) on:01/12/2022  
Replied by DFO (Forest Division Renukoot) on:20/12/2022  
Query raised by Circle (Mirzapur Circle Mirzapur) on:03/01/2023  
Replied by DFO (Forest Division Renukoot) on:02/03/2023  
Query raised by Circle (Mirzapur Circle Mirzapur) on:06/03/2023  
Replied by DFO (Forest Division Renukoot) on:16/03/2023  
Query raised by Circle (Mirzapur Circle Mirzapur) on:05/04/2023  
Replied by DFO (Forest Division Renukoot) on:23/06/2023  
Query raised by Circle (Mirzapur Circle Mirzapur) on:26/07/2023  
Replied by DFO (Forest Division Renukoot) on:26/07/2023  
Query raised by Circle (Mirzapur Circle Mirzapur) on:01/08/2023  
Replied by DFO (Forest Division Renukoot) on:01/08/2023  
Query raised by Circle (Mirzapur Circle Mirzapur) on:04/08/2023  
Replied by DFO (Forest Division Renukoot) on:14/08/2023  
Query raised by Circle (Mirzapur Circle Mirzapur) on:17/08/2023  
Replied by DFO (Forest Division Renukoot) on:12/09/2023  
Query raised by Circle (Mirzapur Circle Mirzapur) on:22/09/2023  
Replied by DFO (Forest Division Renukoot) on:04/10/2023  
Query raised by Circle (Mirzapur Circle Mirzapur) on:12/10/2023  
Replied by DFO (Forest Division Renukoot) on:12/10/2023  
Query raised by Circle (Mirzapur Circle Mirzapur) on:12/10/2023  
Replied by DFO (Forest Division Renukoot) on:12/10/2023  
Query raised by Circle (Mirzapur Circle Mirzapur) on:05/02/2024  
Replied by DFO (Forest Division Renukoot) on:09/02/2024  
Query raised by Circle (Mirzapur Circle Mirzapur) on:29/08/2024  
Replied by DFO (Forest Division Renukoot) on:12/11/2024  
Query raised by Circle (Mirzapur Circle Mirzapur) on:19/11/2024  
Replied by DFO (Forest Division Renukoot) on:17/01/2025  
Query raised by Circle (Mirzapur Circle Mirzapur) on:04/02/2025  
Replied by DFO () on:  
Query raised by DFO (Forest Division Renukoot) on:05/01/2023  
Replied by UA on :28/02/2023  
Query raised by DFO (Forest Division Renukoot) on:06/04/2023  
Replied by UA on :23/06/2023  
Query raised by DFO (Forest Division Renukoot) on:23/08/2023  
Replied by UA on :12/09/2023  
Query raised by DFO (Forest Division Renukoot) on:18/09/2024  
Replied by UA on :12/11/2024  
Query raised by DFO (Forest Division Renukoot) on:22/11/2024  
Replied by UA on :04/01/2025  
NOTE:- Proposal is pending at DFO due to EDS raised by Head Office .