Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Social Forestry Division Pilibhit)
|
EDS
|
User Agency (piumorthshahjahanpur@gmail.com)
|
08/12/2020
|
EDS RAIS BY DFO
|
|
2
|
User Agency (piumorthshahjahanpur@gmail.com)
|
REPLY
|
DFO (Social Forestry Division Pilibhit)
|
18/12/2020
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Social Forestry Division Pilibhit)
|
EDS
|
User Agency (piumorthshahjahanpur@gmail.com)
|
25/09/2021
|
Proposal is incomplete
|
|
4
|
User Agency (piumorthshahjahanpur@gmail.com)
|
REPLY
|
DFO (Social Forestry Division Pilibhit)
|
29/09/2021
|
The correction have been made as per the instruction received
|
|
5
|
CF (Bareilly Circle Bareilly)
|
EDS
|
DFO (Social Forestry Division Pilibhit)
|
22/10/2021
|
EDS
|
|
6
|
DFO (Social Forestry Division Pilibhit)
|
EDS
|
User Agency (piumorthshahjahanpur@gmail.com)
|
22/10/2021
|
EDS Letter dated 21 10 2021
|
|
7
|
User Agency (piumorthshahjahanpur@gmail.com)
|
REPLY
|
DFO (Social Forestry Division Pilibhit)
|
22/10/2021
|
The correction have been made as per the instruction received
|
|
8
|
DFO (Social Forestry Division Pilibhit)
|
REPLY
|
CF (Bareilly Circle Bareilly)
|
26/10/2021
|
EDS Reply letter n0 1415 dated 26 Oct 2021
|
|
9
|
CF (Bareilly Circle Bareilly)
|
EDS
|
DFO (Social Forestry Division Pilibhit)
|
02/11/2021
|
HARD COPY NOT RECEIVED
|
|
10
|
DFO (Social Forestry Division Pilibhit)
|
REPLY
|
CF (Bareilly Circle Bareilly)
|
02/11/2021
|
Hard copies of Proposal is already submitted to CF Pilibhit office
|
|
11
|
CF (Bareilly Circle Bareilly)
|
EDS
|
DFO (Social Forestry Division Pilibhit)
|
08/12/2021
|
HARD COPY NOT RECEIVED
|
|
12
|
DFO (Social Forestry Division Pilibhit)
|
REPLY
|
CF (Bareilly Circle Bareilly)
|
09/12/2021
|
Hard copies of Proposal is already submitted to CF Pilibhit office after signature by CF will be submit to CF Bareilly office for further necessary action.
|
|
13
|
CF (Bareilly Circle Bareilly)
|
EDS
|
DFO (Social Forestry Division Pilibhit)
|
05/01/2022
|
HARD COPY NOT RECEIVED TILL DATE
|
|
14
|
DFO (Social Forestry Division Pilibhit)
|
REPLY
|
CF (Bareilly Circle Bareilly)
|
05/01/2022
|
Hard copies of Proposal is already submitted to CF Pilibhit office for further necessary action.
|
|
15
|
CF (Bareilly Circle Bareilly)
|
EDS
|
DFO (Social Forestry Division Pilibhit)
|
11/01/2022
|
NPV REVISED EDS
|
|
16
|
DFO (Social Forestry Division Pilibhit)
|
REPLY
|
CF (Bareilly Circle Bareilly)
|
14/01/2022
|
Revised NPV Bill Uploaded and enclosed in the hard copies
|
|
17
|
CF (Bareilly Circle Bareilly)
|
EDS
|
DFO (Social Forestry Division Pilibhit)
|
28/01/2022
|
HARD COPY NOT RECEIVED TILL DATE
|
|
18
|
DFO (Social Forestry Division Pilibhit)
|
REPLY
|
CF (Bareilly Circle Bareilly)
|
01/02/2022
|
EDS is completed
|
|
19
|
Regional Office
|
EDS
|
State secretary
|
31/03/2022
|
EDS
|
|
20
|
State secretary
|
EDS
|
Nodal Officer
|
06/04/2022
|
EDS
|
|
21
|
Nodal Officer
|
EDS
|
CF (Bareilly Circle Bareilly)
|
06/04/2022
|
EDS
|
|
22
|
CF (Bareilly Circle Bareilly)
|
EDS
|
DFO (Social Forestry Division Pilibhit)
|
11/04/2022
|
EDS
|
|
23
|
DFO (Social Forestry Division Pilibhit)
|
REPLY
|
CF (Bareilly Circle Bareilly)
|
19/04/2022
|
EDS Reply by DFO Pilibhit letter dated 19 April 2022
|
|
24
|
CF (Bareilly Circle Bareilly)
|
REPLY
|
Nodal Officer
|
22/04/2022
|
EDS REMOVED
|
|
25
|
Nodal Officer
|
REPLY
|
State secretary
|
26/04/2022
|
EDS replied.
|
|
26
|
State secretary
|
REPLY
|
Regional Office
|
28/04/2022
|
EDS Complied
|
|