TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/UP/ROAD/49626/2020              (ii). Name of Project for which Forest Land is required : Rehabilitation and Upgradation to 2-lane with paved shoulders configuration of Radhaita to Pilibhit Section of NH-731K ( Km 137.250 to Km 183.380) (Package-IV) in the State of Uttar Pradesh under Green National Highways Corridor Project (GNHCP) with the loan assistance of world Bank on EPC mode              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : In order to widening and up gradation will be performed on adjoining to the existing two laning road only .the road side plantation along the project road which is declared as PF Land will be impacted due to the proposed widening work. No other alternative exist for proposed widening              (iv). File no. : 8B/UP/06/29/2022/FC              (v). State : Uttar Pradesh              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 44.376
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onCompliance Report Submitted by State onStage-II Approval on
FP/UP/ROAD/49626/202012/09/2020aa14/09/2020   09/10/2020 Social Forestry Division Pilibhit :10/10/2020Bareilly Circle Bareilly:
  15/10/2021 (Social Forestry Division Pilibhit)

Uttar Pradesh:
01/02/2022
Uttar Pradesh:
03/02/2022
Lucknow:
22/02/2022
13/06/2022
By :Regional Office
Uttar Pradesh
23/08/2022
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Lucknow) on:31/03/2022  
Replied by State Government(Uttar Pradesh) on:28/04/2022  
Query raised by State Government (Uttar Pradesh) on:06/04/2022  
Replied by Nodal Officer (Uttar Pradesh) on:26/04/2022  
Query raised by Nodal Officer (Uttar Pradesh) on:06/04/2022  
Replied by Circle(Bareilly Circle Bareilly) on:22/04/2022  
Query raised by Circle (Bareilly Circle Bareilly) on:22/10/2021  
Replied by DFO (Social Forestry Division Pilibhit) on:26/10/2021  
Query raised by Circle (Bareilly Circle Bareilly) on:02/11/2021  
Replied by DFO (Social Forestry Division Pilibhit) on:02/11/2021  
Query raised by Circle (Bareilly Circle Bareilly) on:08/12/2021  
Replied by DFO (Social Forestry Division Pilibhit) on:09/12/2021  
Query raised by Circle (Bareilly Circle Bareilly) on:05/01/2022  
Replied by DFO (Social Forestry Division Pilibhit) on:05/01/2022  
Query raised by Circle (Bareilly Circle Bareilly) on:11/01/2022  
Replied by DFO (Social Forestry Division Pilibhit) on:14/01/2022  
Query raised by Circle (Bareilly Circle Bareilly) on:28/01/2022  
Replied by DFO (Social Forestry Division Pilibhit) on:01/02/2022  
Query raised by Circle (Bareilly Circle Bareilly) on:11/04/2022  
Replied by DFO (Social Forestry Division Pilibhit) on:19/04/2022  
Query raised by DFO (Social Forestry Division Pilibhit) on:08/12/2020  
Replied by UA on :18/12/2020  
Query raised by DFO (Social Forestry Division Pilibhit) on:25/09/2021  
Replied by UA on :29/09/2021  
Query raised by DFO (Social Forestry Division Pilibhit) on:22/10/2021  
Replied by UA on :22/10/2021  
D. Essential Details Sought History (Stage-II)
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & User Agency
Query raised by Regional Office (Lucknow) on:31/08/2022  
Replied by State Government(Uttar Pradesh) on:18/05/2023  
Query raised by Regional Office (Lucknow) on:23/06/2023  
Replied by State Government(Uttar Pradesh) on:20/10/2023  
Query raised by Regional Office (Lucknow) on:05/12/2023  
Replied by State Government(Uttar Pradesh) on:28/03/2024  
Query raised by Regional Office (Lucknow) on:18/06/2024  
Query raised by State Government (Uttar Pradesh) on:02/09/2022  
Replied by Nodal Officer (Uttar Pradesh) on:18/05/2023  
Query raised by State Government (Uttar Pradesh) on:26/06/2023  
Replied by Nodal Officer (Uttar Pradesh) on:20/10/2023  
Query raised by State Government (Uttar Pradesh) on:12/12/2023  
Replied by Nodal Officer (Uttar Pradesh) on:28/03/2024  
Query raised by State Government (Uttar Pradesh) on:19/06/2024  
Query raised by Nodal Officer on:06/09/2022  
Replied by UA on :17/05/2023  
Query raised by Nodal Officer on:28/06/2023  
Replied by UA on :19/09/2023  
Query raised by Nodal Officer on:21/09/2023  
Replied by UA on :19/10/2023  
Query raised by Nodal Officer on:14/12/2023  
Replied by UA on :28/03/2024  
Query raised by Nodal Officer on:20/06/2024  
Replied by UA on :  
NOTE:- Proposal is pending at User Agency due to EDS raised by RO for Stage-II .