| Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
|
1
|
Nodal Officer
|
EDS
|
CF (Gorakhpur Circle Gorakhpur)
|
11/01/2018
|
EDS Letter Attached.
|
|
|
2
|
CF (Gorakhpur Circle Gorakhpur)
|
EDS
|
DFO (Forest Division Gorakhpur)
|
12/01/2018
|
Remove quary
|
|
|
3
|
DFO (Forest Division Gorakhpur)
|
EDS
|
User Agency (nhgkp123@gmail.com)
|
15/01/2018
|
do the required corrections
|
|
|
4
|
User Agency (nhgkp123@gmail.com)
|
REPLY
|
DFO (Forest Division Gorakhpur)
|
15/01/2018
|
The correction have been made as per the instruction received
|
|
|
5
|
DFO (Forest Division Gorakhpur)
|
EDS
|
User Agency (nhgkp123@gmail.com)
|
16/01/2018
|
Remove quary
|
|
|
6
|
User Agency (nhgkp123@gmail.com)
|
REPLY
|
DFO (Forest Division Gorakhpur)
|
16/01/2018
|
The correction have been made as per the instruction received
|
|
|
7
|
DFO (Forest Division Gorakhpur)
|
REPLY
|
CF (Gorakhpur Circle Gorakhpur)
|
17/01/2018
|
Plz Sir Project Reback
|
|
|
8
|
CF (Gorakhpur Circle Gorakhpur)
|
EDS
|
DFO (Forest Division Gorakhpur)
|
17/01/2018
|
Remove quary
|
|
|
9
|
DFO (Forest Division Gorakhpur)
|
REPLY
|
CF (Gorakhpur Circle Gorakhpur)
|
24/01/2018
|
EDS Removed.
|
|
|
10
|
CF (Gorakhpur Circle Gorakhpur)
|
REPLY
|
Nodal Officer
|
24/01/2018
|
EDS Removed.
|
|