TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/UP/ROAD/23699/2017              (ii). Name of Project for which Forest Land is required : Froest Land proposed to be Diverted for 4-Laning of SH-33 Road from Lalpur Badi Zayarat to Ujhani bypass from Ch 102.115 Km to Ch 114.20 Km on Pilibhit-Bareilly-Mathura-Bharatpur Road in Budaun District              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Froest Land proposed for 4-Laning of SH-33 Road from Lalpur Badi Zayarat to Ujhani bypass from Ch 102.115 Km to Ch 114.20 Km on Pilibhit-Bareilly-Mathura-Bharatpur Road in Budaun District              (iv). File no. : 8B/UP/06/57/2017/FC              (v). State : Uttar Pradesh              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 13.29
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/UP/ROAD/23699/201720/01/201731/01/2017  27/01/2017   31/01/2017  30/01/2017   31/01/2017   28/02/2017 Social Forestry Division Budaun :02/03/2017Bareilly Circle Bareilly:
  04/04/2017 (Social Forestry Division Budaun)

Uttar Pradesh:
13/04/2017
Uttar Pradesh:
22/05/2017
Lucknow:
24/08/2017
20/02/2018
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Lucknow) on:31/08/2017  
Replied by State Government(Uttar Pradesh) on:18/01/2018  
Query raised by State Government (Uttar Pradesh) on:06/09/2017  
Replied by Nodal Officer (Uttar Pradesh) on:26/12/2017  
Query raised by Nodal Officer (Uttar Pradesh) on:21/04/2017  
Replied by Circle(Bareilly Circle Bareilly) on:12/05/2017  
Query raised by Nodal Officer (Uttar Pradesh) on:18/05/2017  
Replied by Circle(Bareilly Circle Bareilly) on:20/05/2017  
Query raised by Nodal Officer (Uttar Pradesh) on:08/09/2017  
Replied by Circle(Bareilly Circle Bareilly) on:10/11/2017  
Query raised by Nodal Officer (Uttar Pradesh) on:30/11/2017  
Replied by Circle(Bareilly Circle Bareilly) on:14/12/2017  
Query raised by Circle (Bareilly Circle Bareilly) on:26/04/2017  
Replied by DFO (Social Forestry Division Budaun) on:12/05/2017  
Query raised by Circle (Bareilly Circle Bareilly) on:19/05/2017  
Replied by DFO (Social Forestry Division Budaun) on:20/05/2017  
Query raised by Circle (Bareilly Circle Bareilly) on:21/09/2017  
Replied by DFO (Social Forestry Division Budaun) on:09/11/2017  
Query raised by Circle (Bareilly Circle Bareilly) on:05/12/2017  
Replied by DFO (Social Forestry Division Budaun) on:06/12/2017  
Query raised by DFO (Social Forestry Division Budaun) on:08/05/2017  
Replied by UA on :08/05/2017  
Query raised by DFO (Social Forestry Division Budaun) on:08/05/2017  
Replied by UA on :12/05/2017  
Query raised by DFO (Social Forestry Division Budaun) on:08/11/2017  
Replied by UA on :09/11/2017  
NOTE:- Stage-I Approval accorded by : Regional Office .