TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/UP/ROAD/19199/2016              (ii). Name of Project for which Forest Land is required : Establishment of Toll Plaza on NH-96 (New NH-NO.330) at km 12.600 to 12.950 (Faizabad-Sultanpur) in Faizabad District ,under Project- Strengthening with Provision of Paved Shoulders from km 0.000 to 46.470 of NH-96 (New NH No.330) in the state of Uttar Pradesh under EPC Mode.              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Establishment of Toll Plaza on NH-96 (New NH-NO.330) at km 12.600 to 12.950 (Faizabad-Sultanpur) in Faizabad District ,under Project- Strengthening with Provision of Paved Shoulders from km 0.000 to 46.470 of NH-96 (New NH No.330) in the state of Uttar Pradesh under EPC Mode.              (iv). File no. : 8B/UP/06/18/2017/FC              (v). State : Uttar Pradesh              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.84
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/UP/ROAD/19199/201605/05/201608/06/2016  03/06/2016  18/05/2016  06/05/2016   10/06/2016  03/06/2016  02/06/2016  10/05/2016   11/05/2016   18/05/2016 Forest Division Faizabad :13/06/2016Saryu Circle Faizabad:
  21/01/2017 (Forest Division Faizabad)

Uttar Pradesh:
25/01/2017
Uttar Pradesh:
23/02/2017
Lucknow:
23/02/2017
24/11/2017
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Lucknow) on:08/03/2017  
Replied by State Government(Uttar Pradesh) on:30/08/2017  
Query raised by Regional Office (Lucknow) on:19/09/2017  
Replied by State Government(Uttar Pradesh) on:10/10/2017  
Query raised by Regional Office (Lucknow) on:26/10/2017  
Replied by State Government(Uttar Pradesh) on:02/11/2017  
Query raised by State Government (Uttar Pradesh) on:10/03/2017  
Replied by Nodal Officer (Uttar Pradesh) on:30/08/2017  
Query raised by State Government (Uttar Pradesh) on:19/09/2017  
Replied by Nodal Officer (Uttar Pradesh) on:10/10/2017  
Query raised by State Government (Uttar Pradesh) on:26/10/2017  
Replied by Nodal Officer (Uttar Pradesh) on:02/11/2017  
Query raised by Nodal Officer (Uttar Pradesh) on:01/02/2017  
Replied by Circle(Saryu Circle Faizabad) on:23/02/2017  
Query raised by Nodal Officer (Uttar Pradesh) on:16/03/2017  
Replied by Circle(Saryu Circle Faizabad) on:11/08/2017  
Query raised by Nodal Officer (Uttar Pradesh) on:18/08/2017  
Replied by Circle(Saryu Circle Faizabad) on:24/08/2017  
Query raised by Nodal Officer (Uttar Pradesh) on:22/09/2017  
Replied by Circle(Saryu Circle Faizabad) on:28/09/2017  
Query raised by Nodal Officer (Uttar Pradesh) on:27/10/2017  
Replied by Circle(Saryu Circle Faizabad) on:31/10/2017  
Query raised by Circle (Saryu Circle Faizabad) on:06/02/2017  
Replied by DFO (Forest Division Faizabad) on:15/02/2017  
Query raised by Circle (Saryu Circle Faizabad) on:21/02/2017  
Replied by DFO (Forest Division Faizabad) on:21/02/2017  
Query raised by Circle (Saryu Circle Faizabad) on:21/02/2017  
Replied by DFO (Forest Division Faizabad) on:23/02/2017  
Query raised by Circle (Saryu Circle Faizabad) on:23/02/2017  
Replied by DFO (Forest Division Faizabad) on:23/02/2017  
Query raised by Circle (Saryu Circle Faizabad) on:11/07/2017  
Replied by DFO (Forest Division Faizabad) on:11/08/2017  
Query raised by Circle (Saryu Circle Faizabad) on:23/08/2017  
Replied by DFO (Forest Division Faizabad) on:24/08/2017  
Query raised by Circle (Saryu Circle Faizabad) on:22/09/2017  
Replied by DFO (Forest Division Faizabad) on:27/09/2017  
Query raised by Circle (Saryu Circle Faizabad) on:31/10/2017  
Replied by DFO (Forest Division Faizabad) on:31/10/2017  
Query raised by DFO (Forest Division Faizabad) on:07/09/2016  
Replied by UA on :18/01/2017  
Query raised by DFO (Forest Division Faizabad) on:11/07/2017  
Replied by UA on :12/07/2017  
Query raised by DFO (Forest Division Faizabad) on:15/07/2017  
Replied by UA on :31/07/2017  
Query raised by DFO (Forest Division Faizabad) on:23/08/2017  
Replied by UA on :23/08/2017  
Query raised by DFO (Forest Division Faizabad) on:23/08/2017  
Replied by UA on :23/08/2017  
Query raised by DFO (Forest Division Faizabad) on:22/09/2017  
Replied by UA on :22/09/2017  
Query raised by DFO (Forest Division Faizabad) on:27/09/2017  
Replied by UA on :27/09/2017  
Query raised by DFO (Forest Division Faizabad) on:31/10/2017  
Replied by UA on :31/10/2017  
NOTE:- Stage-I Approval accorded by : Regional Office .