TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/UP/ROAD/17826/2016              (ii). Name of Project for which Forest Land is required : Widening & strengthening of U.P. State Highway-46, Pukharayan-Ghatampur- Bindiki Road.by U.P. State Highways Authority, Lucknow (U.P.)              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Project envisages the use of Protected Forest Land for diversion (under FCA-1980) for non-forestry purpose for 4-lane Widening & strengthening of U.P. State Highway-46, Pukharayan-Ghatampur- Bindiki Section from Km. Chainage 0+000 to 82+220 in Distt. Kanpur Dehat, Kanpur Nagar & Fatehpur.              (iv). File no. : 8B/UP/06/44/2017              (v). State : Uttar Pradesh              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 75.5235
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onCompliance Report Submitted by State onStage-II Approval on
FP/UP/ROAD/17826/201624/05/201609/06/2016  25/05/2016   01/07/2016  26/05/2016   30/05/2016   06/06/2016 Forest Division Kanpur Dehat:  04/07/2016
Social Forestry Division Kanpur Nagar:  04/07/2016
Social Forestry Division Fatehpur:  04/07/2016
Allhabad Circle Allhabad:
  16/10/2016 (Social Forestry Division Fatehpur)

Kanpur Circle Kanpur:
  02/09/2016 (Social Forestry Division Kanpur Nagar)

Kanpur Circle Kanpur:
  21/09/2016 (Forest Division Kanpur Dehat)

Uttar Pradesh:
02/11/2016
Uttar Pradesh:
04/05/2017
Lucknow:
19/07/2017
20/04/2018
By :Regional Office
Uttar Pradesh
29/11/2022
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Lucknow) on:14/08/2017  
Replied by State Government(Uttar Pradesh) on:04/04/2018  
Query raised by State Government (Uttar Pradesh) on:17/08/2017  
Replied by Nodal Officer (Uttar Pradesh) on:16/01/2018  
Query raised by Nodal Officer (Uttar Pradesh) on:17/11/2016  
Replied by Circle(Kanpur Circle Kanpur) on:19/04/2017  
Query raised by Nodal Officer (Uttar Pradesh) on:17/11/2016  
Replied by Circle(Allhabad Circle Allhabad) on:19/04/2017  
Query raised by Nodal Officer (Uttar Pradesh) on:24/04/2017  
Replied by Circle(Kanpur Circle Kanpur) on:03/05/2017  
Query raised by Nodal Officer (Uttar Pradesh) on:24/04/2017  
Replied by Circle(Allhabad Circle Allhabad) on:04/05/2017  
Query raised by Nodal Officer (Uttar Pradesh) on:18/08/2017  
Replied by Circle(Allhabad Circle Allhabad) on:15/12/2017  
Query raised by Nodal Officer (Uttar Pradesh) on:18/08/2017  
Replied by Circle(Kanpur Circle Kanpur) on:08/01/2018  
Query raised by Circle (Allhabad Circle Allhabad) on:21/11/2016  
Replied by DFO (Social Forestry Division Fatehpur) on:30/03/2017  
Query raised by Circle (Allhabad Circle Allhabad) on:30/03/2017  
Replied by DFO (Social Forestry Division Fatehpur) on:31/03/2017  
Query raised by Circle (Kanpur Circle Kanpur) on:10/04/2017  
Replied by DFO (Social Forestry Division Kanpur Nagar) on:19/04/2017  
Query raised by Circle (Kanpur Circle Kanpur) on:10/04/2017  
Replied by DFO (Forest Division Kanpur Dehat) on:19/04/2017  
Query raised by Circle (Allhabad Circle Allhabad) on:22/08/2017  
Replied by DFO (Social Forestry Division Fatehpur) on:15/12/2017  
Query raised by Circle (Kanpur Circle Kanpur) on:20/12/2017  
Replied by DFO (Social Forestry Division Kanpur Nagar) on:28/12/2017  
Query raised by Circle (Kanpur Circle Kanpur) on:20/12/2017  
Replied by DFO (Forest Division Kanpur Dehat) on:29/12/2017  
Query raised by Circle (Kanpur Circle Kanpur) on:01/01/2018  
Replied by DFO (Social Forestry Division Kanpur Nagar) on:02/01/2018  
Query raised by Circle (Kanpur Circle Kanpur) on:01/01/2018  
Replied by DFO (Forest Division Kanpur Dehat) on:02/01/2018  
Query raised by DFO (Social Forestry Division Fatehpur) on:12/07/2016  
Replied by UA on :19/09/2016  
Query raised by DFO (Social Forestry Division Fatehpur) on:01/12/2016  
Replied by UA on :20/01/2017  
Query raised by DFO (Social Forestry Division Fatehpur) on:07/02/2017  
Replied by UA on :25/03/2017  
Query raised by DFO (Social Forestry Division Fatehpur) on:06/09/2017  
Replied by UA on :09/10/2017  
Query raised by DFO (Social Forestry Division Fatehpur) on:16/10/2017  
Replied by UA on :28/10/2017  
D. Essential Details Sought History (Stage-II)
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & User Agency
Query raised by Regional Office (Lucknow) on:31/12/2022  
Query raised by State Government (Uttar Pradesh) on:02/01/2023  
Query raised by Nodal Officer on:03/01/2023  
NOTE:- Proposal is pending at User Agency due to EDS raised by RO for Stage-II .