TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/UP/ROAD/17575/2016              (ii). Name of Project for which Forest Land is required : Construction of Four Lane: Jalaun to Orai (Bilrayan - Panwari Road SH21 From Km 352.00 to 370.450, Bypass No. 1 & 2 and Remaining Part of NH 25) District-Jalaun, Uttar Pradesh              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : 4 Lane Widening of Road              (iv). File no. : 8B/UP/06/37/2016              (v). State : Uttar Pradesh              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 35.71435
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/UP/ROAD/17575/201625/01/201623/02/2016  18/02/2016  17/02/2016  25/01/2016   24/02/2016  19/02/2016  18/02/2016  13/02/2016   19/02/2016   22/02/2016 Forest Division Orai :24/02/2016Bundelkhand Circle Jhansi:
  16/03/2016 (Forest Division Orai)

Uttar Pradesh:
30/03/2016
Uttar Pradesh:
21/04/2016
Lucknow:
21/04/2016
28/07/2016
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Lucknow) on:13/05/2016  
Replied by State Government(Uttar Pradesh) on:15/06/2016  
Query raised by Regional Office (Lucknow) on:08/07/2016  
Replied by State Government(Uttar Pradesh) on:15/07/2016  
Query raised by State Government (Uttar Pradesh) on:19/05/2016  
Replied by Nodal Officer (Uttar Pradesh) on:10/06/2016  
Query raised by State Government (Uttar Pradesh) on:12/07/2016  
Replied by Nodal Officer (Uttar Pradesh) on:15/07/2016  
Query raised by Nodal Officer (Uttar Pradesh) on:01/04/2016  
Replied by Circle(Bundelkhand Circle Jhansi) on:20/04/2016  
Query raised by Nodal Officer (Uttar Pradesh) on:20/05/2016  
Replied by Circle(Bundelkhand Circle Jhansi) on:09/06/2016  
Query raised by Nodal Officer (Uttar Pradesh) on:09/06/2016  
Replied by Circle(Bundelkhand Circle Jhansi) on:09/06/2016  
Query raised by Nodal Officer (Uttar Pradesh) on:10/06/2016  
Replied by Circle(Bundelkhand Circle Jhansi) on:10/06/2016  
Query raised by Nodal Officer (Uttar Pradesh) on:14/07/2016  
Replied by Circle(Bundelkhand Circle Jhansi) on:15/07/2016  
Query raised by Circle (Bundelkhand Circle Jhansi) on:17/03/2016  
Replied by DFO (Forest Division Orai) on:17/03/2016  
Query raised by Circle (Bundelkhand Circle Jhansi) on:11/04/2016  
Replied by DFO (Forest Division Orai) on:11/04/2016  
Query raised by Circle (Bundelkhand Circle Jhansi) on:03/06/2016  
Replied by DFO (Forest Division Orai) on:09/06/2016  
Query raised by Circle (Bundelkhand Circle Jhansi) on:09/06/2016  
Replied by DFO (Forest Division Orai) on:09/06/2016  
Query raised by Circle (Bundelkhand Circle Jhansi) on:10/06/2016  
Replied by DFO (Forest Division Orai) on:10/06/2016  
Query raised by Circle (Bundelkhand Circle Jhansi) on:14/07/2016  
Replied by DFO (Forest Division Orai) on:15/07/2016  
Query raised by DFO (Forest Division Orai) on:04/06/2016  
Replied by UA on :08/06/2016  
Query raised by DFO (Forest Division Orai) on:14/07/2016  
Replied by UA on :15/07/2016  
NOTE:- Stage-I Approval accorded by : Regional Office .