Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
CF (Bundelkhand Circle Jhansi)
|
EDS
|
DFO (Forest Division Orai)
|
17/03/2016
|
orai
|
|
2
|
DFO (Forest Division Orai)
|
REPLY
|
CF (Bundelkhand Circle Jhansi)
|
17/03/2016
|
forword to cir jhansi
|
|
3
|
Nodal Officer
|
EDS
|
CF (Bundelkhand Circle Jhansi)
|
01/04/2016
|
EDS raised vide letter dated 01.04.2016 in attached file and following observation in online part-2
1. KML file for CA area has not been uploaded.
2. Scaned copy of the Geo Referenced Map has not been uploaded.
3. SOI toposheet indicating boundary of forest land proposed for CA has not been uploaded.
4. FRA certificate has not been uploaded.
DO the needful.
|
|
4
|
CF (Bundelkhand Circle Jhansi)
|
EDS
|
DFO (Forest Division Orai)
|
11/04/2016
|
Plan not to be match
|
|
5
|
DFO (Forest Division Orai)
|
REPLY
|
CF (Bundelkhand Circle Jhansi)
|
11/04/2016
|
plant to be correct
|
|
6
|
CF (Bundelkhand Circle Jhansi)
|
REPLY
|
Nodal Officer
|
20/04/2016
|
Area to match.
|
|
7
|
Regional Office
|
EDS
|
State secretary
|
13/05/2016
|
EDS
|
|
8
|
State secretary
|
EDS
|
Nodal Officer
|
19/05/2016
|
pl resubmit the proposal after removing the objections
|
|
9
|
Nodal Officer
|
EDS
|
CF (Bundelkhand Circle Jhansi)
|
20/05/2016
|
pl resubmit the proposal after removing the objections
|
|
10
|
CF (Bundelkhand Circle Jhansi)
|
EDS
|
DFO (Forest Division Orai)
|
03/06/2016
|
orai
|
|
11
|
DFO (Forest Division Orai)
|
EDS
|
User Agency (forestpdpwdorai@gmail.com)
|
04/06/2016
|
orai
|
|
12
|
User Agency (forestpdpwdorai@gmail.com)
|
REPLY
|
DFO (Forest Division Orai)
|
08/06/2016
|
The correction have been made as per the instruction received
|
|
13
|
DFO (Forest Division Orai)
|
REPLY
|
CF (Bundelkhand Circle Jhansi)
|
09/06/2016
|
corret
|
|
14
|
CF (Bundelkhand Circle Jhansi)
|
REPLY
|
Nodal Officer
|
09/06/2016
|
is to be correct
|
|
15
|
Nodal Officer
|
EDS
|
CF (Bundelkhand Circle Jhansi)
|
09/06/2016
|
pl resubmit the proposal after removing the objections
|
|
16
|
CF (Bundelkhand Circle Jhansi)
|
EDS
|
DFO (Forest Division Orai)
|
09/06/2016
|
worng
|
|
17
|
DFO (Forest Division Orai)
|
REPLY
|
CF (Bundelkhand Circle Jhansi)
|
09/06/2016
|
correct
|
|
18
|
CF (Bundelkhand Circle Jhansi)
|
REPLY
|
Nodal Officer
|
09/06/2016
|
correct
|
|
19
|
Nodal Officer
|
EDS
|
CF (Bundelkhand Circle Jhansi)
|
10/06/2016
|
District profile details is not correct.
|
|
20
|
CF (Bundelkhand Circle Jhansi)
|
EDS
|
DFO (Forest Division Orai)
|
10/06/2016
|
District profile details is not correct
|
|
21
|
DFO (Forest Division Orai)
|
REPLY
|
CF (Bundelkhand Circle Jhansi)
|
10/06/2016
|
to be correct
|
|
22
|
CF (Bundelkhand Circle Jhansi)
|
REPLY
|
Nodal Officer
|
10/06/2016
|
to be correct
|
|
23
|
Nodal Officer
|
REPLY
|
State secretary
|
10/06/2016
|
EDS have been removed.
|
|
24
|
State secretary
|
REPLY
|
Regional Office
|
15/06/2016
|
EDS Complied
|
|
25
|
Regional Office
|
EDS
|
State secretary
|
08/07/2016
|
EDS but proposal is placed for July REC
|
|
26
|
State secretary
|
EDS
|
Nodal Officer
|
12/07/2016
|
please provide required information
|
|
27
|
Nodal Officer
|
EDS
|
CF (Bundelkhand Circle Jhansi)
|
14/07/2016
|
EDS attached letter dt. 14 June 2016. Do the needful.
|
|
28
|
CF (Bundelkhand Circle Jhansi)
|
EDS
|
DFO (Forest Division Orai)
|
14/07/2016
|
correct it
|
|
29
|
DFO (Forest Division Orai)
|
EDS
|
User Agency (forestpdpwdorai@gmail.com)
|
14/07/2016
|
correct it
|
|
30
|
User Agency (forestpdpwdorai@gmail.com)
|
REPLY
|
DFO (Forest Division Orai)
|
15/07/2016
|
The correction have been made as per the instruction received
|
|
31
|
DFO (Forest Division Orai)
|
REPLY
|
CF (Bundelkhand Circle Jhansi)
|
15/07/2016
|
to be correct
|
|
32
|
CF (Bundelkhand Circle Jhansi)
|
REPLY
|
Nodal Officer
|
15/07/2016
|
correct all document
|
|
33
|
Nodal Officer
|
REPLY
|
State secretary
|
15/07/2016
|
EDS Removed.
|
|
34
|
State secretary
|
REPLY
|
Regional Office
|
15/07/2016
|
EDS removed.
|
|