Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Forest Division Nazibabad)
|
EDS
|
User Agency (piu_meerut@yahoo.co.in)
|
01/04/2023
|
PlZ Removed EDS.
|
|
2
|
DFO (Social Forestry Division Bijnor)
|
EDS
|
User Agency (piu_meerut@yahoo.co.in)
|
01/04/2023
|
Plz. EDS removed.
|
|
3
|
User Agency (piu_meerut@yahoo.co.in)
|
REPLY
|
DFO (Forest Division Nazibabad)
|
22/05/2024
|
The correction have been made as per the instruction received
|
|
4
|
User Agency (piu_meerut@yahoo.co.in)
|
REPLY
|
DFO (Social Forestry Division Bijnor)
|
22/05/2024
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Social Forestry Division Bijnor)
|
EDS
|
User Agency (piu_meerut@yahoo.co.in)
|
10/06/2024
|
DFO Nodal Officer of this project after completion of part-11 this office
|
|
6
|
DFO (Forest Division Nazibabad)
|
EDS
|
User Agency (piu_meerut@yahoo.co.in)
|
10/06/2024
|
The information sought by the Forest Department was found to be incorrect as per the checklist.
|
|
7
|
User Agency (piu_meerut@yahoo.co.in)
|
REPLY
|
DFO (Social Forestry Division Bijnor)
|
14/06/2024
|
The correction have been made as per the instruction received
|
|
8
|
User Agency (piu_meerut@yahoo.co.in)
|
REPLY
|
DFO (Forest Division Nazibabad)
|
14/06/2024
|
The correction have been made as per the instruction received
|
|
9
|
DFO (Social Forestry Division Bijnor)
|
EDS
|
User Agency (piu_meerut@yahoo.co.in)
|
31/07/2024
|
Plz Joint Inspection of project Range officer Najibabad.
|
|
10
|
User Agency (piu_meerut@yahoo.co.in)
|
REPLY
|
DFO (Social Forestry Division Bijnor)
|
14/08/2024
|
The correction have been made as per the instruction received
|
|
11
|
CF (Moradabad Circle Moradabad)
|
EDS
|
DFO (Social Forestry Division Bijnor)
|
04/09/2024
|
EDS letter is attached.
|
|
12
|
CF (Moradabad Circle Moradabad)
|
EDS
|
DFO (Forest Division Nazibabad)
|
04/09/2024
|
EDS letter is attached.
|
|
13
|
DFO (Social Forestry Division Bijnor)
|
REPLY
|
CF (Moradabad Circle Moradabad)
|
15/09/2024
|
EDS has been removed as per order.
|
|
14
|
DFO (Forest Division Nazibabad)
|
REPLY
|
CF (Moradabad Circle Moradabad)
|
18/09/2024
|
the query has been resolved .the project is not available for online changes . kindly revert back sothat necessary changes can be made
|
|
15
|
CF (Moradabad Circle Moradabad)
|
EDS
|
DFO (Forest Division Nazibabad)
|
18/09/2024
|
CA scheme details and other docoments in correct.
|
|
16
|
DFO (Forest Division Nazibabad)
|
EDS
|
User Agency (piu_meerut@yahoo.co.in)
|
20/09/2024
|
1.THE updated undertaking for 5.27 ha is to be uploaded
2. the gazette notification for section 20 under indian forest act is to be uploaded for forest land to be diverted .
|
|
17
|
User Agency (piu_meerut@yahoo.co.in)
|
REPLY
|
DFO (Forest Division Nazibabad)
|
24/09/2024
|
The correction have been made as per the instruction received
|
|
18
|
DFO (Forest Division Nazibabad)
|
EDS
|
User Agency (piu_meerut@yahoo.co.in)
|
26/09/2024
|
THE updated undertaking for 5.27 ha is to be countersigned by DFO BIJNOR too.
|
|
19
|
User Agency (piu_meerut@yahoo.co.in)
|
REPLY
|
DFO (Forest Division Nazibabad)
|
27/09/2024
|
The correction have been made as per the instruction received
|
|
20
|
DFO (Forest Division Nazibabad)
|
REPLY
|
CF (Moradabad Circle Moradabad)
|
02/10/2024
|
the query resolved and reverted
|
|
21
|
Nodal Officer
|
EDS
|
CF (Moradabad Circle Moradabad)
|
08/10/2024
|
eds reply uploaded.
|
|
22
|
CF (Moradabad Circle Moradabad)
|
EDS
|
DFO (Social Forestry Division Bijnor)
|
09/10/2024
|
Remove query raised by ccf/Nodal officer UP.
|
|
23
|
CF (Moradabad Circle Moradabad)
|
EDS
|
DFO (Forest Division Nazibabad)
|
09/10/2024
|
Remove query raised by ccf/Nodal officer UP.
|
|
24
|
DFO (Forest Division Nazibabad)
|
EDS
|
User Agency (piu_meerut@yahoo.co.in)
|
10/10/2024
|
Remove query raised by ccf/Nodal officer UP.
|
|
25
|
User Agency (piu_meerut@yahoo.co.in)
|
REPLY
|
DFO (Forest Division Nazibabad)
|
18/10/2024
|
The correction have been made as per the instruction received
|
|
26
|
DFO (Forest Division Nazibabad)
|
REPLY
|
CF (Moradabad Circle Moradabad)
|
25/10/2024
|
CORRECTIONS HAVE BEEN MADE AS PER INSTRUCTIONS RECIVED FROM NODAL OFFICE.
|
|
27
|
DFO (Social Forestry Division Bijnor)
|
REPLY
|
CF (Moradabad Circle Moradabad)
|
04/11/2024
|
Eds has been replied
|
|
28
|
CF (Moradabad Circle Moradabad)
|
EDS
|
DFO (Social Forestry Division Bijnor)
|
04/11/2024
|
The objection raised by CCF/Nodal Officer lucknow have not been resolved completely.
|
|
29
|
DFO (Social Forestry Division Bijnor)
|
REPLY
|
CF (Moradabad Circle Moradabad)
|
05/11/2024
|
EDS has been removed.
|
|
30
|
CF (Moradabad Circle Moradabad)
|
EDS
|
DFO (Social Forestry Division Bijnor)
|
05/11/2024
|
NPV ditels incorrect,
|
|
31
|
DFO (Social Forestry Division Bijnor)
|
REPLY
|
CF (Moradabad Circle Moradabad)
|
06/11/2024
|
EDS has been removed.
|
|
32
|
CF (Moradabad Circle Moradabad)
|
REPLY
|
Nodal Officer
|
08/11/2024
|
Objection has been removed.
|
|
33
|
Nodal Officer
|
EDS
|
CF (Moradabad Circle Moradabad)
|
09/11/2024
|
eds
|
|
34
|
CF (Moradabad Circle Moradabad)
|
EDS
|
DFO (Social Forestry Division Bijnor)
|
09/11/2024
|
Remove query raised by ccf/Nodal officer UP.
|
|
35
|
CF (Moradabad Circle Moradabad)
|
EDS
|
DFO (Forest Division Nazibabad)
|
09/11/2024
|
Remove query raised by ccf/Nodal officer UP.
|
|
36
|
DFO (Social Forestry Division Bijnor)
|
REPLY
|
CF (Moradabad Circle Moradabad)
|
12/11/2024
|
EDS Of Nodal Officer as per eds has been remooved.
|
|
37
|
DFO (Forest Division Nazibabad)
|
EDS
|
User Agency (piu_meerut@yahoo.co.in)
|
13/11/2024
|
CCF/Nodal officer lucknow EDS letter no. 1262/1C date 09/11/2024 online part 1 CA plantation in project NFL KML is not uploaded please upload e NFL KML in part 1
|
|
38
|
User Agency (piu_meerut@yahoo.co.in)
|
REPLY
|
DFO (Forest Division Nazibabad)
|
20/11/2024
|
The correction have been made as per the instruction received
|
|
39
|
DFO (Forest Division Nazibabad)
|
REPLY
|
CF (Moradabad Circle Moradabad)
|
26/11/2024
|
EDS raised by Nodal Officer on the proposal has been removed
|
|
40
|
CF (Moradabad Circle Moradabad)
|
EDS
|
DFO (Forest Division Nazibabad)
|
26/11/2024
|
The EDS imposed by the ccf/nodal officer.UP. has not been completely resolved . Re-check and resolve the EDS.
|
|
41
|
DFO (Forest Division Nazibabad)
|
REPLY
|
CF (Moradabad Circle Moradabad)
|
27/11/2024
|
EDS raised by Nodal Officer on the proposal has been removed
|
|
42
|
CF (Moradabad Circle Moradabad)
|
EDS
|
DFO (Forest Division Nazibabad)
|
27/11/2024
|
EDS incomplite
|
|
43
|
DFO (Forest Division Nazibabad)
|
REPLY
|
CF (Moradabad Circle Moradabad)
|
27/11/2024
|
EDS raised by Nodal Officer on the proposal has been removed
|
|
44
|
CF (Moradabad Circle Moradabad)
|
REPLY
|
Nodal Officer
|
28/11/2024
|
Objection has been removed.
|
|
45
|
State secretary
|
EDS
|
Nodal Officer
|
10/12/2024
|
eds
|
|
46
|
Nodal Officer
|
REPLY
|
State secretary
|
16/12/2024
|
eds reply uploaded.
|
|
47
|
State secretary
|
EDS
|
Nodal Officer
|
17/12/2024
|
eds
|
|
48
|
Nodal Officer
|
REPLY
|
State secretary
|
18/12/2024
|
eds reply letter uploaded.
|
|
49
|
State secretary
|
EDS
|
Nodal Officer
|
19/12/2024
|
eds
|
|
50
|
Nodal Officer
|
EDS
|
CF (Moradabad Circle Moradabad)
|
20/12/2024
|
eds letter
|
|
51
|
CF (Moradabad Circle Moradabad)
|
EDS
|
DFO (Social Forestry Division Bijnor)
|
23/12/2024
|
eds letter
|
|
52
|
CF (Moradabad Circle Moradabad)
|
EDS
|
DFO (Forest Division Nazibabad)
|
23/12/2024
|
eds letter
|
|
53
|
DFO (Forest Division Nazibabad)
|
EDS
|
User Agency (piu_meerut@yahoo.co.in)
|
27/12/2024
|
eds letter
|
|
54
|
User Agency (piu_meerut@yahoo.co.in)
|
REPLY
|
DFO (Forest Division Nazibabad)
|
03/01/2025
|
The correction have been made as per the instruction received
|
|
55
|
DFO (Forest Division Nazibabad)
|
EDS
|
User Agency (piu_meerut@yahoo.co.in)
|
07/01/2025
|
eds letter
|
|
56
|
DFO (Social Forestry Division Bijnor)
|
REPLY
|
CF (Moradabad Circle Moradabad)
|
08/01/2025
|
EDS has been removed
|
|
57
|
User Agency (piu_meerut@yahoo.co.in)
|
REPLY
|
DFO (Forest Division Nazibabad)
|
10/01/2025
|
The correction have been made as per the instruction received
|
|
58
|
DFO (Forest Division Nazibabad)
|
REPLY
|
CF (Moradabad Circle Moradabad)
|
10/01/2025
|
PSC Committee has recommended the proposal on dt.09.01.2025 accordingly User Agency vide letter no.17296 dt. 10.01.2025 has submitted the compliance of EDS raised by State Government
|
|
59
|
CF (Moradabad Circle Moradabad)
|
EDS
|
DFO (Forest Division Nazibabad)
|
10/01/2025
|
EDS letter is not uploaded please upload.
|
|
60
|
DFO (Forest Division Nazibabad)
|
REPLY
|
CF (Moradabad Circle Moradabad)
|
10/01/2025
|
PSC Committee has recommended the proposal on dt.09.01.2025 accordingly User Agency vide letter no.17296 dt. 10.01.2025 has submitted the compliance of EDS raised by State Government
|
|
61
|
CF (Moradabad Circle Moradabad)
|
EDS
|
DFO (Forest Division Nazibabad)
|
10/01/2025
|
EDS letter is not uploaded please upload.
|
|
62
|
DFO (Forest Division Nazibabad)
|
REPLY
|
CF (Moradabad Circle Moradabad)
|
10/01/2025
|
PSC Committee has recommended the proposal on dt.09.01.2025 accordingly User Agency vide letter no.17296 dt. 10.01.2025 has submitted the compliance of EDS raised by State Government
|
|
63
|
CF (Moradabad Circle Moradabad)
|
REPLY
|
Nodal Officer
|
10/01/2025
|
Objection has been removed.
|
|
64
|
Nodal Officer
|
REPLY
|
State secretary
|
13/01/2025
|
eds reply
|
|
65
|
Regional Office
|
EDS
|
State secretary
|
20/02/2025
|
EDS
|
|
66
|
State secretary
|
EDS
|
Nodal Officer
|
21/02/2025
|
eds
|
|
67
|
Nodal Officer
|
EDS
|
CF (Moradabad Circle Moradabad)
|
21/02/2025
|
eds GOI
|
|
68
|
CF (Moradabad Circle Moradabad)
|
EDS
|
DFO (Social Forestry Division Bijnor)
|
21/02/2025
|
Remove query raised by ccf/Nodal officer UP.
|
|
69
|
CF (Moradabad Circle Moradabad)
|
EDS
|
DFO (Forest Division Nazibabad)
|
21/02/2025
|
Remove query raised by ccf/Nodal officer UP.
|
|
70
|
DFO (Forest Division Nazibabad)
|
EDS
|
User Agency (piu_meerut@yahoo.co.in)
|
22/02/2025
|
Remove query raised by ccf/Nodal officer UP.
|
|
71
|
User Agency (piu_meerut@yahoo.co.in)
|
REPLY
|
DFO (Forest Division Nazibabad)
|
27/03/2025
|
The correction have been made as per the instruction received
|
|
72
|
DFO (Forest Division Nazibabad)
|
REPLY
|
CF (Moradabad Circle Moradabad)
|
23/04/2025
|
eds reply
|
|
73
|
DFO (Social Forestry Division Bijnor)
|
REPLY
|
CF (Moradabad Circle Moradabad)
|
29/04/2025
|
EDS has been removed
|
|
74
|
CF (Moradabad Circle Moradabad)
|
REPLY
|
Nodal Officer
|
29/04/2025
|
Objection has been removed.
|
|
75
|
Nodal Officer
|
EDS
|
CF (Moradabad Circle Moradabad)
|
30/04/2025
|
pointwise eds letter has been not uploaded.
|
|
76
|
CF (Moradabad Circle Moradabad)
|
EDS
|
DFO (Forest Division Nazibabad)
|
30/04/2025
|
Remove query raised by ccf/Nodal officer UP.
|
|
77
|
DFO (Forest Division Nazibabad)
|
REPLY
|
CF (Moradabad Circle Moradabad)
|
28/05/2025
|
Point wise reply of the EDS raised by IRO, Lucknow on dt.20.02.2025
|
|
78
|
CF (Moradabad Circle Moradabad)
|
REPLY
|
Nodal Officer
|
30/05/2025
|
Objection has been removed.
|
|
79
|
Nodal Officer
|
REPLY
|
State secretary
|
30/05/2025
|
eds reply
|
|
80
|
State secretary
|
REPLY
|
Regional Office
|
30/05/2025
|
eds reply
|
|