Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Forest Division Bahraich)
|
EDS
|
User Agency (cewbuppwd@gmail.com)
|
27/01/2022
|
Plese Remove Objection
|
|
2
|
User Agency (cewbuppwd@gmail.com)
|
REPLY
|
DFO (Forest Division Bahraich)
|
23/03/2022
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Forest Division Gonda)
|
EDS
|
User Agency (cewbuppwd@gmail.com)
|
29/04/2022
|
?????? ?????? ????? ????? ???? ???????? ??? ???????? ?? ??? ????? ?? ??????? ???? ?? ??????? ???????? ?? ???? ??? ????????
|
|
4
|
User Agency (cewbuppwd@gmail.com)
|
REPLY
|
DFO (Forest Division Gonda)
|
03/06/2022
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Forest Division Bahraich)
|
EDS
|
User Agency (cewbuppwd@gmail.com)
|
16/06/2022
|
Please Remove Objection
|
|
6
|
User Agency (cewbuppwd@gmail.com)
|
REPLY
|
DFO (Forest Division Bahraich)
|
21/09/2022
|
The correction have been made as per the instruction received
|
|
7
|
DFO (Forest Division Bahraich)
|
EDS
|
User Agency (cewbuppwd@gmail.com)
|
24/09/2022
|
Please Remove objection
|
|
8
|
User Agency (cewbuppwd@gmail.com)
|
REPLY
|
DFO (Forest Division Bahraich)
|
22/12/2022
|
The correction have been made as per the instruction received
|
|
9
|
CF (Devipatan Circle Gonda)
|
EDS
|
DFO (Forest Division Gonda)
|
13/01/2023
|
correct the proposal
|
|
10
|
CF (Devipatan Circle Gonda)
|
EDS
|
DFO (Forest Division Bahraich)
|
13/01/2023
|
correct the proposal
|
|
11
|
CF (Devipatan Circle Gonda)
|
EDS
|
DFO (Forest Division Shrawasti)
|
13/01/2023
|
correct the proposal
|
|
12
|
DFO (Forest Division Gonda)
|
REPLY
|
CF (Devipatan Circle Gonda)
|
17/01/2023
|
EDS Latter is Submited and Work Project is Important for Public Intrested
|
|
13
|
DFO (Forest Division Shrawasti)
|
REPLY
|
CF (Devipatan Circle Gonda)
|
18/01/2023
|
correct the proposal
|
|
14
|
DFO (Forest Division Bahraich)
|
REPLY
|
CF (Devipatan Circle Gonda)
|
18/01/2023
|
correct the proposal
|
|
15
|
Nodal Officer
|
EDS
|
CF (Devipatan Circle Gonda)
|
20/01/2023
|
EDS letter attached.
|
|
16
|
CF (Devipatan Circle Gonda)
|
EDS
|
DFO (Forest Division Gonda)
|
20/01/2023
|
EDS letter attached.
|
|
17
|
CF (Devipatan Circle Gonda)
|
EDS
|
DFO (Forest Division Bahraich)
|
20/01/2023
|
EDS letter attached.
|
|
18
|
CF (Devipatan Circle Gonda)
|
EDS
|
DFO (Forest Division Shrawasti)
|
20/01/2023
|
EDS letter attached.
|
|
19
|
DFO (Forest Division Bahraich)
|
EDS
|
User Agency (cewbuppwd@gmail.com)
|
23/01/2023
|
Objection Remove
|
|
20
|
DFO (Forest Division Gonda)
|
REPLY
|
CF (Devipatan Circle Gonda)
|
02/02/2023
|
bahraich gonda Apatii
|
|
21
|
DFO (Forest Division Shrawasti)
|
EDS
|
User Agency (cewbuppwd@gmail.com)
|
21/02/2023
|
EDS letter attached.
|
|
22
|
User Agency (cewbuppwd@gmail.com)
|
REPLY
|
DFO (Forest Division Bahraich)
|
02/03/2023
|
The correction have been made as per the instruction received
|
|
23
|
User Agency (cewbuppwd@gmail.com)
|
REPLY
|
DFO (Forest Division Shrawasti)
|
02/03/2023
|
The correction have been made as per the instruction received
|
|
24
|
DFO (Forest Division Bahraich)
|
EDS
|
User Agency (cewbuppwd@gmail.com)
|
18/03/2023
|
objection Removed
|
|
25
|
User Agency (cewbuppwd@gmail.com)
|
REPLY
|
DFO (Forest Division Bahraich)
|
22/03/2023
|
The correction have been made as per the instruction received
|
|
26
|
DFO (Forest Division Shrawasti)
|
EDS
|
User Agency (cewbuppwd@gmail.com)
|
06/04/2023
|
This Praposal is not editing file so plz objection remove
|
|
27
|
User Agency (cewbuppwd@gmail.com)
|
REPLY
|
DFO (Forest Division Shrawasti)
|
06/04/2023
|
The correction have been made as per the instruction received
|
|
28
|
DFO (Forest Division Bahraich)
|
REPLY
|
CF (Devipatan Circle Gonda)
|
27/04/2023
|
EDS Removed.
|
|
29
|
DFO (Forest Division Shrawasti)
|
REPLY
|
CF (Devipatan Circle Gonda)
|
27/04/2023
|
EDS Removed.
|
|
30
|
CF (Devipatan Circle Gonda)
|
EDS
|
DFO (Forest Division Gonda)
|
27/04/2023
|
EDS
|
|
31
|
CF (Devipatan Circle Gonda)
|
EDS
|
DFO (Forest Division Bahraich)
|
27/04/2023
|
EDS
|
|
32
|
CF (Devipatan Circle Gonda)
|
EDS
|
DFO (Forest Division Shrawasti)
|
27/04/2023
|
EDS
|
|
33
|
DFO (Forest Division Gonda)
|
REPLY
|
CF (Devipatan Circle Gonda)
|
03/05/2023
|
?????? ?? ?????? ??0??0-30 ?? ????????? ?? ??????? ?? ???? ??? ???
|
|
34
|
DFO (Forest Division Shrawasti)
|
REPLY
|
CF (Devipatan Circle Gonda)
|
12/05/2023
|
correct the EDS
|
|
35
|
DFO (Forest Division Bahraich)
|
REPLY
|
CF (Devipatan Circle Gonda)
|
12/05/2023
|
EDS
|
|
36
|
CF (Devipatan Circle Gonda)
|
EDS
|
DFO (Forest Division Gonda)
|
12/05/2023
|
correct the EDS
|
|
37
|
CF (Devipatan Circle Gonda)
|
EDS
|
DFO (Forest Division Bahraich)
|
12/05/2023
|
correct the EDS
|
|
38
|
CF (Devipatan Circle Gonda)
|
EDS
|
DFO (Forest Division Shrawasti)
|
12/05/2023
|
correct the EDS
|
|
39
|
DFO (Forest Division Gonda)
|
REPLY
|
CF (Devipatan Circle Gonda)
|
12/05/2023
|
EDS
|
|
40
|
DFO (Forest Division Bahraich)
|
REPLY
|
CF (Devipatan Circle Gonda)
|
12/05/2023
|
EDS
|
|
41
|
DFO (Forest Division Shrawasti)
|
REPLY
|
CF (Devipatan Circle Gonda)
|
12/05/2023
|
EDS
|
|
42
|
CF (Devipatan Circle Gonda)
|
EDS
|
DFO (Forest Division Gonda)
|
12/05/2023
|
Correct the EDS
|
|
43
|
CF (Devipatan Circle Gonda)
|
EDS
|
DFO (Forest Division Bahraich)
|
12/05/2023
|
Correct the EDS
|
|
44
|
CF (Devipatan Circle Gonda)
|
EDS
|
DFO (Forest Division Shrawasti)
|
12/05/2023
|
Correct the EDS
|
|
45
|
DFO (Forest Division Shrawasti)
|
REPLY
|
CF (Devipatan Circle Gonda)
|
16/05/2023
|
Objection Remove
|
|
46
|
DFO (Forest Division Bahraich)
|
REPLY
|
CF (Devipatan Circle Gonda)
|
16/05/2023
|
Objection Removed
|
|
47
|
DFO (Forest Division Gonda)
|
REPLY
|
CF (Devipatan Circle Gonda)
|
18/05/2023
|
eds letter attached
|
|
48
|
CF (Devipatan Circle Gonda)
|
EDS
|
DFO (Forest Division Shrawasti)
|
18/05/2023
|
correct the proposal
|
|
49
|
DFO (Forest Division Shrawasti)
|
REPLY
|
CF (Devipatan Circle Gonda)
|
18/05/2023
|
eds letter attached
|
|
50
|
CF (Devipatan Circle Gonda)
|
REPLY
|
Nodal Officer
|
18/05/2023
|
EDS letter Attached
|
|
51
|
Nodal Officer
|
EDS
|
CF (Devipatan Circle Gonda)
|
25/05/2023
|
EDS letter attached.
|
|
52
|
CF (Devipatan Circle Gonda)
|
EDS
|
DFO (Forest Division Gonda)
|
25/05/2023
|
EDS letter attached.
|
|
53
|
CF (Devipatan Circle Gonda)
|
EDS
|
DFO (Forest Division Bahraich)
|
25/05/2023
|
EDS letter attached.
|
|
54
|
CF (Devipatan Circle Gonda)
|
EDS
|
DFO (Forest Division Shrawasti)
|
25/05/2023
|
EDS letter attached.
|
|
55
|
DFO (Forest Division Bahraich)
|
EDS
|
User Agency (cewbuppwd@gmail.com)
|
30/05/2023
|
Correct the proposal
|
|
56
|
User Agency (cewbuppwd@gmail.com)
|
REPLY
|
DFO (Forest Division Bahraich)
|
31/05/2023
|
The correction have been made as per the instruction received
|
|
57
|
DFO (Forest Division Bahraich)
|
REPLY
|
CF (Devipatan Circle Gonda)
|
01/06/2023
|
Objection Removed
|
|
58
|
DFO (Forest Division Shrawasti)
|
REPLY
|
CF (Devipatan Circle Gonda)
|
05/06/2023
|
Objection remove
|
|
59
|
DFO (Forest Division Gonda)
|
REPLY
|
CF (Devipatan Circle Gonda)
|
08/06/2023
|
Objection remove
|
|
60
|
CF (Devipatan Circle Gonda)
|
REPLY
|
Nodal Officer
|
08/06/2023
|
EDS letter Attached
|
|
61
|
Regional Office
|
EDS
|
State secretary
|
29/08/2023
|
EDS
|
|
62
|
State secretary
|
EDS
|
Nodal Officer
|
30/08/2023
|
eds
|
|
63
|
Nodal Officer
|
EDS
|
CF (Devipatan Circle Gonda)
|
30/08/2023
|
EDS letter Attached.
|
|
64
|
CF (Devipatan Circle Gonda)
|
EDS
|
DFO (Forest Division Gonda)
|
30/08/2023
|
EDS letter Attached.
|
|
65
|
CF (Devipatan Circle Gonda)
|
EDS
|
DFO (Forest Division Bahraich)
|
30/08/2023
|
EDS letter Attached.
|
|
66
|
CF (Devipatan Circle Gonda)
|
EDS
|
DFO (Forest Division Shrawasti)
|
30/08/2023
|
EDS letter Attached.
|
|
67
|
DFO (Forest Division Bahraich)
|
EDS
|
User Agency (cewbuppwd@gmail.com)
|
04/09/2023
|
objection Removed
|
|
68
|
User Agency (cewbuppwd@gmail.com)
|
REPLY
|
DFO (Forest Division Bahraich)
|
19/10/2023
|
The correction have been made as per the instruction received
|
|
69
|
DFO (Forest Division Bahraich)
|
REPLY
|
CF (Devipatan Circle Gonda)
|
31/10/2023
|
Objection Removed
|
|
70
|
DFO (Forest Division Shrawasti)
|
REPLY
|
CF (Devipatan Circle Gonda)
|
01/11/2023
|
objection remove
|
|
71
|
DFO (Forest Division Gonda)
|
REPLY
|
CF (Devipatan Circle Gonda)
|
21/11/2023
|
EDS letter Attached
|
|
72
|
CF (Devipatan Circle Gonda)
|
REPLY
|
Nodal Officer
|
22/11/2023
|
EDS Letter Attached
|
|
73
|
Nodal Officer
|
EDS
|
CF (Devipatan Circle Gonda)
|
24/11/2023
|
EDS letter Attached.
|
|
74
|
CF (Devipatan Circle Gonda)
|
EDS
|
DFO (Forest Division Gonda)
|
24/11/2023
|
EDS letter Attached
|
|
75
|
CF (Devipatan Circle Gonda)
|
EDS
|
DFO (Forest Division Bahraich)
|
24/11/2023
|
EDS letter Attached
|
|
76
|
CF (Devipatan Circle Gonda)
|
EDS
|
DFO (Forest Division Shrawasti)
|
24/11/2023
|
EDS letter Attached
|
|
77
|
DFO (Forest Division Gonda)
|
EDS
|
User Agency (cewbuppwd@gmail.com)
|
02/12/2023
|
Apatti
|
|
78
|
User Agency (cewbuppwd@gmail.com)
|
REPLY
|
DFO (Forest Division Gonda)
|
30/01/2024
|
The correction have been made as per the instruction received
|
|
79
|
DFO (Forest Division Bahraich)
|
REPLY
|
CF (Devipatan Circle Gonda)
|
16/02/2024
|
EDS Remove
|
|
80
|
DFO (Forest Division Shrawasti)
|
REPLY
|
CF (Devipatan Circle Gonda)
|
02/03/2024
|
objuction remove
|
|
81
|
DFO (Forest Division Gonda)
|
REPLY
|
CF (Devipatan Circle Gonda)
|
04/03/2024
|
EDS letter Attached
|
|
82
|
CF (Devipatan Circle Gonda)
|
EDS
|
DFO (Forest Division Gonda)
|
04/03/2024
|
correct the proposal
|
|
83
|
DFO (Forest Division Gonda)
|
REPLY
|
CF (Devipatan Circle Gonda)
|
11/03/2024
|
EDS letter Attached
|
|
84
|
CF (Devipatan Circle Gonda)
|
REPLY
|
Nodal Officer
|
12/03/2024
|
EDS Letter Attached
|
|
85
|
Nodal Officer
|
REPLY
|
State secretary
|
13/03/2024
|
EDS Removed.
|
|
86
|
State secretary
|
REPLY
|
Regional Office
|
13/03/2024
|
EDS Removed.
|
|