Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Social Forestry Division Sitapur)
|
EDS
|
User Agency (nhdivisionkanpur2012@gmail.com)
|
07/06/2022
|
remove quary as pur latter
|
|
2
|
User Agency (nhdivisionkanpur2012@gmail.com)
|
REPLY
|
DFO (Social Forestry Division Sitapur)
|
27/07/2022
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Social Forestry Division Sitapur)
|
EDS
|
User Agency (nhdivisionkanpur2012@gmail.com)
|
28/07/2022
|
remove quary as pur latter
|
|
4
|
User Agency (nhdivisionkanpur2012@gmail.com)
|
REPLY
|
DFO (Social Forestry Division Sitapur)
|
02/08/2022
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Social Forestry Division Sitapur)
|
EDS
|
User Agency (nhdivisionkanpur2012@gmail.com)
|
04/08/2022
|
remove quary as pur latter no 5882 date 04-06-2022
|
|
6
|
User Agency (nhdivisionkanpur2012@gmail.com)
|
REPLY
|
DFO (Social Forestry Division Sitapur)
|
04/08/2022
|
The correction have been made as per the instruction received
|
|
7
|
DFO (Social Forestry Division Hardoi)
|
EDS
|
User Agency (nhdivisionkanpur2012@gmail.com)
|
07/08/2022
|
Plz Provide Tree and other report
|
|
8
|
User Agency (nhdivisionkanpur2012@gmail.com)
|
REPLY
|
DFO (Social Forestry Division Hardoi)
|
08/08/2022
|
The correction have been made as per the instruction received
|
|
9
|
DFO (Social Forestry Division Sitapur)
|
EDS
|
User Agency (nhdivisionkanpur2012@gmail.com)
|
22/08/2022
|
remove quary as pur latter
|
|
10
|
User Agency (nhdivisionkanpur2012@gmail.com)
|
REPLY
|
DFO (Social Forestry Division Sitapur)
|
23/08/2022
|
The correction have been made as per the instruction received
|
|
11
|
DFO (Social Forestry Division Hardoi)
|
EDS
|
User Agency (nhdivisionkanpur2012@gmail.com)
|
24/08/2022
|
Plz Provide CA Land Estimate & Digital Map
|
|
12
|
User Agency (nhdivisionkanpur2012@gmail.com)
|
REPLY
|
DFO (Social Forestry Division Hardoi)
|
24/08/2022
|
The correction have been made as per the instruction received
|
|
13
|
DFO (Social Forestry Division Hardoi)
|
EDS
|
User Agency (nhdivisionkanpur2012@gmail.com)
|
28/09/2022
|
The Correction of Project Totle Km
|
|
14
|
User Agency (nhdivisionkanpur2012@gmail.com)
|
REPLY
|
DFO (Social Forestry Division Hardoi)
|
28/09/2022
|
The correction have been made as per the instruction received
|
|
15
|
DFO (Social Forestry Division Sitapur)
|
EDS
|
User Agency (nhdivisionkanpur2012@gmail.com)
|
13/10/2022
|
remove quary as pur latter no 3004 date 13-10-2022
|
|
16
|
User Agency (nhdivisionkanpur2012@gmail.com)
|
REPLY
|
DFO (Social Forestry Division Sitapur)
|
14/10/2022
|
The correction have been made as per the instruction received
|
|
17
|
CF (Lucknow Circle Lucknow)
|
EDS
|
DFO (Social Forestry Division Sitapur)
|
02/11/2022
|
Hard Copy not received till date
|
|
18
|
CF (Lucknow Circle Lucknow)
|
EDS
|
DFO (Social Forestry Division Hardoi)
|
02/11/2022
|
Hard Copy not received till date
|
|
19
|
DFO (Social Forestry Division Hardoi)
|
REPLY
|
CF (Lucknow Circle Lucknow)
|
14/11/2022
|
Objection Remove
|
|
20
|
DFO (Social Forestry Division Sitapur)
|
REPLY
|
CF (Lucknow Circle Lucknow)
|
15/11/2022
|
quary remove
|
|
21
|
CF (Lucknow Circle Lucknow)
|
EDS
|
DFO (Social Forestry Division Sitapur)
|
18/11/2022
|
Please Remove EDS
|
|
22
|
DFO (Social Forestry Division Sitapur)
|
REPLY
|
CF (Lucknow Circle Lucknow)
|
08/12/2022
|
quary remove
|
|
23
|
Nodal Officer
|
EDS
|
CF (Lucknow Circle Lucknow)
|
22/12/2022
|
EDS letter Attached.
|
|
24
|
CF (Lucknow Circle Lucknow)
|
EDS
|
DFO (Social Forestry Division Sitapur)
|
23/12/2022
|
Please Remove EDS
|
|
25
|
CF (Lucknow Circle Lucknow)
|
EDS
|
DFO (Social Forestry Division Hardoi)
|
23/12/2022
|
Please Remove EDS
|
|
26
|
DFO (Social Forestry Division Hardoi)
|
EDS
|
User Agency (nhdivisionkanpur2012@gmail.com)
|
09/01/2023
|
Plz provide information regarding following Points
|
|
27
|
User Agency (nhdivisionkanpur2012@gmail.com)
|
REPLY
|
DFO (Social Forestry Division Hardoi)
|
14/03/2023
|
The correction have been made as per the instruction received
|
|
28
|
DFO (Social Forestry Division Sitapur)
|
EDS
|
User Agency (nhdivisionkanpur2012@gmail.com)
|
03/04/2023
|
dls anlisis
|
|
29
|
User Agency (nhdivisionkanpur2012@gmail.com)
|
REPLY
|
DFO (Social Forestry Division Sitapur)
|
10/04/2023
|
The correction have been made as per the instruction received
|
|
30
|
DFO (Social Forestry Division Sitapur)
|
REPLY
|
CF (Lucknow Circle Lucknow)
|
16/05/2023
|
hadoi-pratapnagar road
|
|
31
|
DFO (Social Forestry Division Hardoi)
|
REPLY
|
CF (Lucknow Circle Lucknow)
|
22/05/2023
|
Objection Remove By Letter No-4269/14-1 Date-02-03-2023
|
|
32
|
CF (Lucknow Circle Lucknow)
|
EDS
|
DFO (Social Forestry Division Sitapur)
|
29/05/2023
|
Please Complete Remove EDS
|
|
33
|
DFO (Social Forestry Division Sitapur)
|
EDS
|
User Agency (nhdivisionkanpur2012@gmail.com)
|
13/06/2023
|
quary shoughtout
|
|
34
|
User Agency (nhdivisionkanpur2012@gmail.com)
|
REPLY
|
DFO (Social Forestry Division Sitapur)
|
13/06/2023
|
The correction have been made as per the instruction received
|
|
35
|
DFO (Social Forestry Division Sitapur)
|
REPLY
|
CF (Lucknow Circle Lucknow)
|
13/06/2023
|
quary removed
|
|
36
|
CF (Lucknow Circle Lucknow)
|
EDS
|
DFO (Social Forestry Division Sitapur)
|
22/06/2023
|
Please Send Combine Hardoi and sitapur resolved report
|
|
37
|
DFO (Social Forestry Division Sitapur)
|
REPLY
|
CF (Lucknow Circle Lucknow)
|
30/06/2023
|
query reaised
|
|
38
|
CF (Lucknow Circle Lucknow)
|
EDS
|
DFO (Social Forestry Division Sitapur)
|
04/07/2023
|
Please Upload All Documnet Of This Proposal
|
|
39
|
CF (Lucknow Circle Lucknow)
|
EDS
|
DFO (Social Forestry Division Hardoi)
|
04/07/2023
|
Please Upload All Documnet Of This Proposal
|
|
40
|
DFO (Social Forestry Division Sitapur)
|
REPLY
|
CF (Lucknow Circle Lucknow)
|
10/07/2023
|
queiry reaised
|
|
41
|
DFO (Social Forestry Division Hardoi)
|
REPLY
|
CF (Lucknow Circle Lucknow)
|
14/07/2023
|
Objection Remove by Letter No. 4269/14-1 Dt. 02-03-2023
|
|
42
|
CF (Lucknow Circle Lucknow)
|
REPLY
|
Nodal Officer
|
17/07/2023
|
EDS Completed
|
|
43
|
Nodal Officer
|
EDS
|
CF (Lucknow Circle Lucknow)
|
25/07/2023
|
EDS attached.
|
|
44
|
CF (Lucknow Circle Lucknow)
|
EDS
|
DFO (Social Forestry Division Sitapur)
|
25/07/2023
|
REmove EDS
|
|
45
|
CF (Lucknow Circle Lucknow)
|
EDS
|
DFO (Social Forestry Division Hardoi)
|
25/07/2023
|
REmove EDS
|
|
46
|
DFO (Social Forestry Division Sitapur)
|
EDS
|
User Agency (nhdivisionkanpur2012@gmail.com)
|
26/07/2023
|
hardoi-sitapur road chaurikaran 330d
|
|
47
|
User Agency (nhdivisionkanpur2012@gmail.com)
|
REPLY
|
DFO (Social Forestry Division Sitapur)
|
12/08/2023
|
The correction have been made as per the instruction received
|
|
48
|
DFO (Social Forestry Division Hardoi)
|
EDS
|
User Agency (nhdivisionkanpur2012@gmail.com)
|
16/08/2023
|
Plz Provide CA kml file & SOI toposheet
|
|
49
|
User Agency (nhdivisionkanpur2012@gmail.com)
|
REPLY
|
DFO (Social Forestry Division Hardoi)
|
17/08/2023
|
The correction have been made as per the instruction received
|
|
50
|
DFO (Social Forestry Division Sitapur)
|
REPLY
|
CF (Lucknow Circle Lucknow)
|
28/08/2023
|
eds remooed
|
|
51
|
DFO (Social Forestry Division Hardoi)
|
REPLY
|
CF (Lucknow Circle Lucknow)
|
28/08/2023
|
Objection Reaove
|
|
52
|
CF (Lucknow Circle Lucknow)
|
EDS
|
DFO (Social Forestry Division Sitapur)
|
28/08/2023
|
Please remove eds
|
|
53
|
CF (Lucknow Circle Lucknow)
|
EDS
|
DFO (Social Forestry Division Hardoi)
|
28/08/2023
|
Please remove eds
|
|
54
|
DFO (Social Forestry Division Sitapur)
|
REPLY
|
CF (Lucknow Circle Lucknow)
|
28/08/2023
|
qyery nisatrit kar di gai hai
|
|
55
|
DFO (Social Forestry Division Hardoi)
|
REPLY
|
CF (Lucknow Circle Lucknow)
|
28/08/2023
|
Objection Remove
|
|
56
|
CF (Lucknow Circle Lucknow)
|
EDS
|
DFO (Social Forestry Division Sitapur)
|
29/08/2023
|
Please complete EDS
|
|
57
|
CF (Lucknow Circle Lucknow)
|
EDS
|
DFO (Social Forestry Division Hardoi)
|
29/08/2023
|
Please complete EDS
|
|
58
|
DFO (Social Forestry Division Sitapur)
|
REPLY
|
CF (Lucknow Circle Lucknow)
|
29/08/2023
|
LEETER
|
|
59
|
DFO (Social Forestry Division Hardoi)
|
EDS
|
User Agency (nhdivisionkanpur2012@gmail.com)
|
29/08/2023
|
Plz Provide EDs
|
|
60
|
User Agency (nhdivisionkanpur2012@gmail.com)
|
REPLY
|
DFO (Social Forestry Division Hardoi)
|
29/08/2023
|
The correction have been made as per the instruction received
|
|
61
|
DFO (Social Forestry Division Hardoi)
|
REPLY
|
CF (Lucknow Circle Lucknow)
|
29/08/2023
|
query removed
|
|
62
|
CF (Lucknow Circle Lucknow)
|
REPLY
|
Nodal Officer
|
30/08/2023
|
EDS Completed
|
|
63
|
Nodal Officer
|
EDS
|
CF (Lucknow Circle Lucknow)
|
04/09/2023
|
EDS letter Attached.
|
|
64
|
CF (Lucknow Circle Lucknow)
|
EDS
|
DFO (Social Forestry Division Sitapur)
|
04/09/2023
|
Please Remove EDS
|
|
65
|
CF (Lucknow Circle Lucknow)
|
EDS
|
DFO (Social Forestry Division Hardoi)
|
04/09/2023
|
Please Remove EDS
|
|
66
|
DFO (Social Forestry Division Sitapur)
|
REPLY
|
CF (Lucknow Circle Lucknow)
|
11/09/2023
|
quiry send by letter 1558/14-1 date 11.09.2023
|
|
67
|
DFO (Social Forestry Division Hardoi)
|
REPLY
|
CF (Lucknow Circle Lucknow)
|
11/09/2023
|
quiry send
|
|
68
|
CF (Lucknow Circle Lucknow)
|
REPLY
|
Nodal Officer
|
12/09/2023
|
EDS Removed
|
|
69
|
Regional Office
|
EDS
|
State secretary
|
09/11/2023
|
EDS
|
|
70
|
State secretary
|
EDS
|
Nodal Officer
|
14/11/2023
|
eds
|
|
71
|
Nodal Officer
|
EDS
|
CF (Lucknow Circle Lucknow)
|
14/11/2023
|
EDS
|
|
72
|
CF (Lucknow Circle Lucknow)
|
EDS
|
DFO (Social Forestry Division Sitapur)
|
14/11/2023
|
Please Remove EDS
|
|
73
|
CF (Lucknow Circle Lucknow)
|
EDS
|
DFO (Social Forestry Division Hardoi)
|
14/11/2023
|
Please Remove EDS
|
|
74
|
DFO (Social Forestry Division Sitapur)
|
EDS
|
User Agency (nhdivisionkanpur2012@gmail.com)
|
14/11/2023
|
Edd
|
|
75
|
User Agency (nhdivisionkanpur2012@gmail.com)
|
REPLY
|
DFO (Social Forestry Division Sitapur)
|
15/12/2023
|
The correction have been made as per the instruction received
|
|
76
|
DFO (Social Forestry Division Hardoi)
|
EDS
|
User Agency (nhdivisionkanpur2012@gmail.com)
|
16/12/2023
|
Plz Provide CA Cordinates Degeri Minutes & Second Digit
|
|
77
|
User Agency (nhdivisionkanpur2012@gmail.com)
|
REPLY
|
DFO (Social Forestry Division Hardoi)
|
20/12/2023
|
The correction have been made as per the instruction received
|
|
78
|
DFO (Social Forestry Division Hardoi)
|
REPLY
|
CF (Lucknow Circle Lucknow)
|
20/12/2023
|
EDS COMPLETED
|
|
79
|
DFO (Social Forestry Division Sitapur)
|
EDS
|
User Agency (nhdivisionkanpur2012@gmail.com)
|
21/12/2023
|
query shatout
|
|
80
|
User Agency (nhdivisionkanpur2012@gmail.com)
|
REPLY
|
DFO (Social Forestry Division Sitapur)
|
22/12/2023
|
The correction have been made as per the instruction received
|
|
81
|
DFO (Social Forestry Division Sitapur)
|
REPLY
|
CF (Lucknow Circle Lucknow)
|
23/12/2023
|
hardoi-pratapnagar road query removed
|
|
82
|
CF (Lucknow Circle Lucknow)
|
REPLY
|
Nodal Officer
|
28/12/2023
|
EDS Removed
|
|
83
|
Nodal Officer
|
REPLY
|
State secretary
|
07/01/2024
|
EDS removed.
|
|
84
|
State secretary
|
REPLY
|
Regional Office
|
07/01/2024
|
EDS removed.
|
|
85
|
Regional Office
|
EDS
|
State secretary
|
05/02/2024
|
EDS
|
|
86
|
State secretary
|
EDS
|
Nodal Officer
|
05/02/2024
|
eds
|
|
87
|
Nodal Officer
|
EDS
|
CF (Lucknow Circle Lucknow)
|
06/02/2024
|
EDS
|
|
88
|
CF (Lucknow Circle Lucknow)
|
EDS
|
DFO (Social Forestry Division Sitapur)
|
06/02/2024
|
Remove EDS
|
|
89
|
CF (Lucknow Circle Lucknow)
|
EDS
|
DFO (Social Forestry Division Hardoi)
|
06/02/2024
|
Remove EDS
|
|
90
|
DFO (Social Forestry Division Sitapur)
|
EDS
|
User Agency (nhdivisionkanpur2012@gmail.com)
|
06/02/2024
|
eds shaught out
|
|
91
|
User Agency (nhdivisionkanpur2012@gmail.com)
|
REPLY
|
DFO (Social Forestry Division Sitapur)
|
06/02/2024
|
The correction have been made as per the instruction received
|
|
92
|
DFO (Social Forestry Division Sitapur)
|
REPLY
|
CF (Lucknow Circle Lucknow)
|
06/02/2024
|
prastav 330 ki akhya
|
|
93
|
DFO (Social Forestry Division Hardoi)
|
REPLY
|
CF (Lucknow Circle Lucknow)
|
06/02/2024
|
prastav 330 d
|
|
94
|
CF (Lucknow Circle Lucknow)
|
REPLY
|
Nodal Officer
|
07/02/2024
|
EDS Removed
|
|
95
|
Nodal Officer
|
REPLY
|
State secretary
|
07/02/2024
|
EDS Removed.
|
|
96
|
State secretary
|
REPLY
|
Regional Office
|
07/02/2024
|
EDS Removed.
|
|
97
|
Regional Office
|
EDS
|
State secretary
|
04/03/2024
|
EDS
|
|
98
|
State secretary
|
EDS
|
Nodal Officer
|
04/03/2024
|
eds
|
|
99
|
Nodal Officer
|
EDS
|
CF (Lucknow Circle Lucknow)
|
04/03/2024
|
EDS letter Attached.
|
|
100
|
CF (Lucknow Circle Lucknow)
|
EDS
|
DFO (Social Forestry Division Sitapur)
|
05/03/2024
|
Please remove EDS
|
|
101
|
CF (Lucknow Circle Lucknow)
|
EDS
|
DFO (Social Forestry Division Hardoi)
|
05/03/2024
|
Please remove EDS
|
|
102
|
DFO (Social Forestry Division Sitapur)
|
EDS
|
User Agency (nhdivisionkanpur2012@gmail.com)
|
07/03/2024
|
Please kml ,dgps,soiltroposheet
|
|
103
|
User Agency (nhdivisionkanpur2012@gmail.com)
|
REPLY
|
DFO (Social Forestry Division Sitapur)
|
07/03/2024
|
The correction have been made as per the instruction received
|
|
104
|
DFO (Social Forestry Division Sitapur)
|
REPLY
|
CF (Lucknow Circle Lucknow)
|
12/03/2024
|
query remooved
|
|
105
|
DFO (Social Forestry Division Hardoi)
|
REPLY
|
CF (Lucknow Circle Lucknow)
|
12/03/2024
|
query removed
|
|
106
|
CF (Lucknow Circle Lucknow)
|
EDS
|
DFO (Social Forestry Division Sitapur)
|
15/03/2024
|
Please correct, remove EDS
|
|
107
|
CF (Lucknow Circle Lucknow)
|
EDS
|
DFO (Social Forestry Division Hardoi)
|
15/03/2024
|
Please correct, remove EDS
|
|
108
|
DFO (Social Forestry Division Sitapur)
|
REPLY
|
CF (Lucknow Circle Lucknow)
|
21/03/2024
|
prastav akhya
|
|
109
|
DFO (Social Forestry Division Hardoi)
|
REPLY
|
CF (Lucknow Circle Lucknow)
|
21/03/2024
|
query remove
|
|
110
|
CF (Lucknow Circle Lucknow)
|
REPLY
|
Nodal Officer
|
21/03/2024
|
EDS Removed
|
|
111
|
Nodal Officer
|
REPLY
|
State secretary
|
22/03/2024
|
EDS Removed.
|
|
112
|
State secretary
|
REPLY
|
Regional Office
|
22/03/2024
|
EDS Removed.
|
|