  (i). Proposal No. : FP/UP/ROAD/13049/2015              (ii). Name of Project for which Forest Land is required : STRENTHENING OF BARABANKI DEVA FATEHPUR ROAD WITH CONSTRUCTION OF BOX CULVERT in between km 2.100 to 2.300 on Bhehda nala              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : strenthening of Barabanki Deva Fatehpur road with construction of box culvert and its approach road in between km 2.100 to 2.300 on Bhehda nala in District Barabanki              (iv). File no. : 8B/UP/06/31/2015/FC              (v). State : Uttar Pradesh              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.285
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/UP/ROAD/13049/201503/06/201506/06/2015  04/06/2015   06/06/2015  04/06/2015   07/06/2015   11/06/2015 Social Forestry Division Barabanki :12/06/2015Saryu Circle Faizabad:
  18/06/2015 (Social Forestry Division Barabanki)

Uttar Pradesh:
30/06/2015
Uttar Pradesh:
12/08/2015
Lucknow:
12/08/2015
08/12/2015
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Lucknow) on:01/09/2015  
Replied by State Government(Uttar Pradesh) on:12/01/2016  
Query raised by State Government (Uttar Pradesh) on:02/11/2015  
Replied by Nodal Officer (Uttar Pradesh) on:12/01/2016  
Query raised by Nodal Officer (Uttar Pradesh) on:14/07/2015  
Replied by Circle(Saryu Circle Faizabad) on:12/08/2015  
Query raised by Nodal Officer (Uttar Pradesh) on:04/11/2015  
Replied by Circle(Saryu Circle Faizabad) on:07/01/2016  
Query raised by Nodal Officer (Uttar Pradesh) on:07/01/2016  
Replied by Circle(Saryu Circle Faizabad) on:08/01/2016  
Query raised by Nodal Officer (Uttar Pradesh) on:11/01/2016  
Replied by Circle(Saryu Circle Faizabad) on:12/01/2016  
Query raised by Circle (Saryu Circle Faizabad) on:05/08/2015  
Replied by DFO (Social Forestry Division Barabanki) on:11/08/2015  
Query raised by Circle (Saryu Circle Faizabad) on:28/12/2015  
Replied by DFO (Social Forestry Division Barabanki) on:07/01/2016  
Query raised by DFO (Social Forestry Division Barabanki) on:11/08/2015  
Replied by UA on :11/08/2015  
Query raised by DFO (Social Forestry Division Barabanki) on:29/12/2015  
Replied by UA on :29/12/2015  
NOTE:- Stage-I Approval accorded by : Regional Office .