Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Kaimur Wild Life Division Mirzapur)
|
EDS
|
User Agency (pmgsypwdsonbhadra@gmail.com)
|
03/08/2021
|
Hard copy not submitted at Kaimur division
|
|
2
|
DFO (Forest Division Sonbhadra)
|
EDS
|
User Agency (pmgsypwdsonbhadra@gmail.com)
|
14/08/2021
|
Please Remove EDS
|
|
3
|
User Agency (pmgsypwdsonbhadra@gmail.com)
|
REPLY
|
DFO (Kaimur Wild Life Division Mirzapur)
|
02/09/2021
|
The correction have been made as per the instruction received
|
|
4
|
User Agency (pmgsypwdsonbhadra@gmail.com)
|
REPLY
|
DFO (Forest Division Sonbhadra)
|
02/09/2021
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Forest Division Sonbhadra)
|
EDS
|
User Agency (pmgsypwdsonbhadra@gmail.com)
|
06/09/2021
|
Please Remove EDS
|
|
6
|
User Agency (pmgsypwdsonbhadra@gmail.com)
|
REPLY
|
DFO (Forest Division Sonbhadra)
|
09/11/2021
|
The correction have been made as per the instruction received
|
|
7
|
DFO (Forest Division Sonbhadra)
|
EDS
|
User Agency (pmgsypwdsonbhadra@gmail.com)
|
27/11/2021
|
Please Remove EDS
|
|
8
|
User Agency (pmgsypwdsonbhadra@gmail.com)
|
REPLY
|
DFO (Forest Division Sonbhadra)
|
04/12/2021
|
The correction have been made as per the instruction received
|
|
9
|
DFO (Forest Division Sonbhadra)
|
EDS
|
User Agency (pmgsypwdsonbhadra@gmail.com)
|
06/12/2021
|
Please Remove EDS
|
|
10
|
User Agency (pmgsypwdsonbhadra@gmail.com)
|
REPLY
|
DFO (Forest Division Sonbhadra)
|
25/07/2022
|
The correction have been made as per the instruction received
|
|
11
|
DFO (Forest Division Sonbhadra)
|
EDS
|
User Agency (pmgsypwdsonbhadra@gmail.com)
|
27/07/2022
|
Please Remove EDS
|
|
12
|
User Agency (pmgsypwdsonbhadra@gmail.com)
|
REPLY
|
DFO (Forest Division Sonbhadra)
|
27/07/2022
|
The correction have been made as per the instruction received
|
|
13
|
DFO (Forest Division Sonbhadra)
|
EDS
|
User Agency (pmgsypwdsonbhadra@gmail.com)
|
28/07/2022
|
Please Remove EDS
|
|
14
|
User Agency (pmgsypwdsonbhadra@gmail.com)
|
REPLY
|
DFO (Forest Division Sonbhadra)
|
28/07/2022
|
The correction have been made as per the instruction received
|
|
15
|
CF (Wild life Circle Western Region Kanpur)
|
EDS
|
DFO (Kaimur Wild Life Division Mirzapur)
|
18/08/2022
|
Correct district profile data
|
|
16
|
DFO (Kaimur Wild Life Division Mirzapur)
|
REPLY
|
CF (Wild life Circle Western Region Kanpur)
|
18/08/2022
|
District profile data has been corrected
|
|
17
|
Nodal Officer
|
EDS
|
CF (Mirzapur Circle Mirzapur)
|
06/09/2022
|
EDS letter attached.
|
|
18
|
Nodal Officer
|
EDS
|
CF (Wild life Circle Western Region Kanpur)
|
06/09/2022
|
EDS letter attached.
|
|
19
|
CF (Mirzapur Circle Mirzapur)
|
EDS
|
DFO (Forest Division Sonbhadra)
|
08/09/2022
|
EDS
|
|
20
|
DFO (Forest Division Sonbhadra)
|
EDS
|
User Agency (pmgsypwdsonbhadra@gmail.com)
|
12/09/2022
|
Please Remove EDS
|
|
21
|
User Agency (pmgsypwdsonbhadra@gmail.com)
|
REPLY
|
DFO (Forest Division Sonbhadra)
|
12/09/2022
|
The correction have been made as per the instruction received
|
|
22
|
DFO (Forest Division Sonbhadra)
|
EDS
|
User Agency (pmgsypwdsonbhadra@gmail.com)
|
13/09/2022
|
Please Remove EDS
|
|
23
|
User Agency (pmgsypwdsonbhadra@gmail.com)
|
REPLY
|
DFO (Forest Division Sonbhadra)
|
13/09/2022
|
The correction have been made as per the instruction received
|
|
24
|
DFO (Forest Division Sonbhadra)
|
REPLY
|
CF (Mirzapur Circle Mirzapur)
|
19/09/2022
|
The correction have been made as per the instruction received
|
|
25
|
CF (Mirzapur Circle Mirzapur)
|
REPLY
|
Nodal Officer
|
21/09/2022
|
Eds letter hasbeen remove
|
|
26
|
CF (Wild life Circle Western Region Kanpur)
|
REPLY
|
Nodal Officer
|
21/09/2022
|
eds has been complete
|
|
27
|
Regional Office
|
EDS
|
State secretary
|
23/11/2022
|
EDS
|
|
28
|
State secretary
|
EDS
|
Nodal Officer
|
24/11/2022
|
eds
|
|
29
|
Nodal Officer
|
EDS
|
CF (Mirzapur Circle Mirzapur)
|
24/11/2022
|
EDS letter attached.
|
|
30
|
Nodal Officer
|
EDS
|
CF (Wild life Circle Western Region Kanpur)
|
24/11/2022
|
EDS letter attached.
|
|
31
|
CF (Mirzapur Circle Mirzapur)
|
EDS
|
DFO (Forest Division Sonbhadra)
|
01/12/2022
|
Eds letter attached
|
|
32
|
DFO (Forest Division Sonbhadra)
|
EDS
|
User Agency (pmgsypwdsonbhadra@gmail.com)
|
01/12/2022
|
After resolving the objections raised by the Chief Conservator of Forests/Nodal Officer, try to provide the revised proposal.
|
|
33
|
User Agency (pmgsypwdsonbhadra@gmail.com)
|
REPLY
|
DFO (Forest Division Sonbhadra)
|
28/12/2022
|
The correction have been made as per the instruction received
|
|
34
|
DFO (Forest Division Sonbhadra)
|
EDS
|
User Agency (pmgsypwdsonbhadra@gmail.com)
|
06/01/2023
|
Please Remove EDS
|
|
35
|
User Agency (pmgsypwdsonbhadra@gmail.com)
|
REPLY
|
DFO (Forest Division Sonbhadra)
|
14/03/2023
|
The correction have been made as per the instruction received
|
|
36
|
DFO (Forest Division Sonbhadra)
|
EDS
|
User Agency (pmgsypwdsonbhadra@gmail.com)
|
14/03/2023
|
Please Remove EDS
|
|
37
|
User Agency (pmgsypwdsonbhadra@gmail.com)
|
REPLY
|
DFO (Forest Division Sonbhadra)
|
14/03/2023
|
The correction have been made as per the instruction received
|
|
38
|
DFO (Forest Division Sonbhadra)
|
REPLY
|
CF (Mirzapur Circle Mirzapur)
|
14/03/2023
|
EDS Removed as per instruction Received
|
|
39
|
CF (Mirzapur Circle Mirzapur)
|
REPLY
|
Nodal Officer
|
24/03/2023
|
Eds letter hasbeen remove
|
|
40
|
CF (Wild life Circle Western Region Kanpur)
|
REPLY
|
Nodal Officer
|
24/03/2023
|
eds has been complete
|
|
41
|
Nodal Officer
|
REPLY
|
State secretary
|
28/03/2023
|
EDS Removed.
|
|
42
|
State secretary
|
REPLY
|
Regional Office
|
28/03/2023
|
EDS Removed.
|
|
43
|
Regional Office
|
EDS
|
State secretary
|
25/04/2023
|
EDS
|
|
44
|
State secretary
|
EDS
|
Nodal Officer
|
27/04/2023
|
eds
|
|
45
|
Nodal Officer
|
REPLY
|
State secretary
|
27/04/2023
|
EDS Removed.
|
|
46
|
State secretary
|
REPLY
|
Regional Office
|
27/04/2023
|
EDS Removed.
|
|