TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/UP/ROAD/118819/2021              (ii). Name of Project for which Forest Land is required : Proposed forest land to be diverted for Widening & Strengthening of RS Road (Sidhahawa) to Jogendra Road Via Khajura Road from Km. No. 0.000 to Km. No. 20.150 Under Road Connectivity Project on Left Wing Extremism Area (RCPLWEA) in Tehsil-Robertsganj, District-Sonbhadra by PMGSY Division, PWD Sonbhadra              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Proposed forest land to be diverted for Widening & Strengthening of RS Road (Sidhahawa) to Jogendra Road Via Khajura Road from Km. No. 0.000 to Km. No. 20.150 Under Road Connectivity Project on Left Wing Extremism Area (RCPLWEA) in Tehsil-Robertsganj, District-Sonbhadra by PMGSY Division, PWD Sonbh              (iv). File no. : 8B/UP/06/33/2022/FC              (v). State : Uttar Pradesh              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 14.5603
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onCompliance Report Submitted by State onStage-II Approval on
FP/UP/ROAD/118819/202111/01/202109/07/2021  21/06/2021  07/06/2021  15/01/2021   12/07/2021  22/06/2021  16/06/2021  28/05/2021   23/06/2021   08/07/2021 Forest Division Renukoot :14/07/2021Mirzapur Circle Mirzapur:
  22/12/2021 (Forest Division Renukoot)

Uttar Pradesh:
04/01/2022
Uttar Pradesh:
14/01/2022
Lucknow:
25/02/2022
04/11/2022
By :Regional Office
Uttar Pradesh
13/08/2024
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Lucknow) on:31/03/2022  
Replied by State Government(Uttar Pradesh) on:21/09/2022  
Query raised by Regional Office (Lucknow) on:18/10/2022  
Replied by State Government(Uttar Pradesh) on:20/10/2022  
Query raised by State Government (Uttar Pradesh) on:05/04/2022  
Replied by Nodal Officer (Uttar Pradesh) on:21/09/2022  
Query raised by State Government (Uttar Pradesh) on:18/10/2022  
Replied by Nodal Officer (Uttar Pradesh) on:20/10/2022  
Query raised by Nodal Officer (Uttar Pradesh) on:05/01/2022  
Replied by Circle(Mirzapur Circle Mirzapur) on:13/01/2022  
Query raised by Nodal Officer (Uttar Pradesh) on:14/01/2022  
Replied by Circle(Mirzapur Circle Mirzapur) on:14/01/2022  
Query raised by Nodal Officer (Uttar Pradesh) on:06/04/2022  
Replied by Circle(Mirzapur Circle Mirzapur) on:11/08/2022  
Query raised by Nodal Officer (Uttar Pradesh) on:16/08/2022  
Replied by Circle(Mirzapur Circle Mirzapur) on:21/09/2022  
Query raised by Nodal Officer (Uttar Pradesh) on:18/10/2022  
Replied by Circle(Mirzapur Circle Mirzapur) on:19/10/2022  
Query raised by Circle (Mirzapur Circle Mirzapur) on:23/12/2021  
Replied by DFO (Forest Division Renukoot) on:28/12/2021  
Query raised by Circle (Mirzapur Circle Mirzapur) on:06/01/2022  
Replied by DFO (Forest Division Renukoot) on:11/01/2022  
Query raised by Circle (Mirzapur Circle Mirzapur) on:14/01/2022  
Replied by DFO (Forest Division Renukoot) on:14/01/2022  
Query raised by Circle (Mirzapur Circle Mirzapur) on:06/04/2022  
Replied by DFO (Forest Division Renukoot) on:29/07/2022  
Query raised by Circle (Mirzapur Circle Mirzapur) on:20/08/2022  
Replied by DFO (Forest Division Renukoot) on:21/09/2022  
Query raised by Circle (Mirzapur Circle Mirzapur) on:19/10/2022  
Replied by DFO (Forest Division Renukoot) on:19/10/2022  
Query raised by DFO (Forest Division Renukoot) on:17/07/2021  
Replied by UA on :02/09/2021  
Query raised by DFO (Forest Division Renukoot) on:16/09/2021  
Replied by UA on :18/12/2021  
Query raised by DFO (Forest Division Renukoot) on:11/01/2022  
Replied by UA on :11/01/2022  
Query raised by DFO (Forest Division Renukoot) on:19/04/2022  
Replied by UA on :21/07/2022  
Query raised by DFO (Forest Division Renukoot) on:22/08/2022  
Replied by UA on :17/09/2022  
D. Essential Details Sought History (Stage-II)
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & User Agency
Query raised by Regional Office (Lucknow) on:10/09/2024  
Query raised by State Government (Uttar Pradesh) on:19/09/2024  
Query raised by Nodal Officer on:23/09/2024  
NOTE:- Proposal is pending at User Agency due to EDS raised by RO for Stage-II .