TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/UP/ROAD/11864/2015              (ii). Name of Project for which Forest Land is required : FOUR LANING WITH PAVED SHOULDER FOR VARANASI-SHAKTINAGAR ROAD (SH-05A)FROM KM 5.050 TO 10.050              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : UTTAR PRADESH STATE HIGHWAY AUTHORITY (UPSHA)HAS INITIATED FOR UPGRADATION OF VARANASI-SHAKTINAGAR ROAD FROM KM5.050 TO 10.050              (iv). File no. : 8B/UP/06/21/2015              (v). State : Uttar Pradesh              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 9
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/UP/ROAD/11864/201520/04/201520/04/2015   22/04/2015   22/04/2015   23/04/2015 Forest Division Mirzapur :28/04/2015Mirzapur Circle Mirzapur:
  12/05/2015 (Forest Division Mirzapur)

Uttar Pradesh:
14/05/2015
Uttar Pradesh:
21/05/2015
Lucknow:
04/02/2016
04/12/2015
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by State Government (Uttar Pradesh) on:04/08/2015  
Replied by Nodal Officer (Uttar Pradesh) on:04/02/2016  
Query raised by Nodal Officer (Uttar Pradesh) on:04/08/2015  
Replied by Circle(Mirzapur Circle Mirzapur) on:05/08/2015  
Query raised by Nodal Officer (Uttar Pradesh) on:11/08/2015  
Replied by Circle(Mirzapur Circle Mirzapur) on:13/08/2015  
Query raised by Nodal Officer (Uttar Pradesh) on:13/08/2015  
Replied by Circle(Mirzapur Circle Mirzapur) on:11/01/2016  
Query raised by Nodal Officer (Uttar Pradesh) on:12/01/2016  
Replied by Circle(Mirzapur Circle Mirzapur) on:02/02/2016  
Query raised by Circle (Mirzapur Circle Mirzapur) on:05/08/2015  
Replied by DFO (Forest Division Mirzapur) on:05/08/2015  
Query raised by Circle (Mirzapur Circle Mirzapur) on:11/08/2015  
Replied by DFO (Forest Division Mirzapur) on:12/08/2015  
Query raised by Circle (Mirzapur Circle Mirzapur) on:13/08/2015  
Replied by DFO (Forest Division Mirzapur) on:11/01/2016  
Query raised by Circle (Mirzapur Circle Mirzapur) on:13/01/2016  
Replied by DFO (Forest Division Mirzapur) on:02/02/2016  
NOTE:- Stage-I Approval accorded by : Regional Office .