TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/UP/ROAD/10971/2015              (ii). Name of Project for which Forest Land is required : Widening of two lane to four lane of NH-92 (New NH-719) km 60.000 to km 69.850              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Proposal for seeking approval of diversion for non-forestry use of 4.1438 hec. protected forest and 3.5847 hec. reserved forest total 7.7285 hec.land and cutting of 964 obstruct trees for four lane widening of NH-92 (New NH-719) from km 60.000 to km 69.850 in district Etawah              (iv). File no. : 8B/UP/06/12/2015              (v). State : Uttar Pradesh              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 7.7285
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/UP/ROAD/10971/201517/03/201520/03/2015  19/03/2015  18/03/2015  18/03/2015  17/03/2015  17/03/2015   23/03/2015  20/03/2015  18/03/2015  18/03/2015  17/03/2015  17/03/2015   23/03/2015   27/03/2015 Social Forestry Division Etawah :01/04/2015Kanpur Circle Kanpur:
  04/04/2015 (Social Forestry Division Etawah)

Uttar Pradesh:
10/04/2015
Uttar Pradesh:
10/04/2015
Lucknow:
30/04/2015
15/06/2015
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Lucknow) on:13/05/2015  
Replied by State Government(Uttar Pradesh) on:09/11/2015  
Query raised by State Government (Uttar Pradesh) on:18/05/2015  
Replied by Nodal Officer (Uttar Pradesh) on:20/05/2015  
Query raised by State Government (Uttar Pradesh) on:04/11/2015  
Replied by Nodal Officer (Uttar Pradesh) on:06/11/2015  
Query raised by Nodal Officer (Uttar Pradesh) on:18/05/2015  
Replied by Circle(Kanpur Circle Kanpur) on:19/05/2015  
Query raised by Circle (Kanpur Circle Kanpur) on:08/04/2015  
Replied by DFO (Social Forestry Division Etawah) on:10/04/2015  
Query raised by Circle (Kanpur Circle Kanpur) on:18/05/2015  
Replied by DFO (Social Forestry Division Etawah) on:19/05/2015  
Query raised by DFO (Social Forestry Division Etawah) on:18/05/2015  
Replied by UA on :18/05/2015  
NOTE:- Stage-I Approval accorded by : Regional Office .