TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/UP/ROAD/10456/2015              (ii). Name of Project for which Forest Land is required : widening of old NH-28 Lucknow Faizabad National highway(city portion Barabanki) along with divider and levelled footpath              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : widening of old NH-28 Lucknow Faizabad National highway(city portion Barabanki) along with divider and levelled footpath in between Km 26.000 toKm 29.700.              (iv). File no. : 8B/UP/06/30/2015/FC              (v). State : Uttar Pradesh              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 1.48
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/UP/ROAD/10456/201526/02/201528/04/2015  27/04/2015  14/04/2015  22/03/2015  18/03/2015  27/02/2015   28/04/2015  27/04/2015  15/04/2015  13/04/2015  18/03/2015  16/03/2015   21/04/2015   22/04/2015 Social Forestry Division Barabanki :08/05/2015Saryu Circle Faizabad:
  10/06/2015 (Social Forestry Division Barabanki)

Uttar Pradesh:
30/06/2015
Uttar Pradesh:
12/08/2015
Lucknow:
12/08/2015
16/10/2015
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Lucknow) on:01/09/2015  
Replied by State Government(Uttar Pradesh) on:17/11/2015  
Query raised by State Government (Uttar Pradesh) on:06/11/2015  
Replied by Nodal Officer (Uttar Pradesh) on:17/11/2015  
Query raised by Nodal Officer (Uttar Pradesh) on:09/11/2015  
Replied by Circle(Saryu Circle Faizabad) on:17/11/2015  
Query raised by Circle (Saryu Circle Faizabad) on:09/11/2015  
Replied by DFO (Social Forestry Division Barabanki) on:17/11/2015  
Query raised by DFO (Social Forestry Division Barabanki) on:09/11/2015  
Replied by UA on :09/11/2015  
Query raised by DFO (Social Forestry Division Barabanki) on:09/11/2015  
Replied by UA on :16/11/2015  
Query raised by DFO (Social Forestry Division Barabanki) on:16/11/2015  
Replied by UA on :16/11/2015  
NOTE:- Stage-I Approval accorded by : Regional Office .
Close(X)