TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/UP/ROAD/10018/2015              (ii). Name of Project for which Forest Land is required : Construction of Safipur-Miyaganj Road (Nani Kuthariya) to Siddnath Nai basti Link road              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Construction of Safipur-Miyaganj Road (Nani Kuthariya) to Siddnath Nai basti Link road,Construction Division-1,PWD Unnao.              (iv). File no. : 2316/14-2-2015-800(71)/2015              (v). State : Uttar Pradesh              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.3304
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentStage-I Approval onStage-II Approval on
FP/UP/ROAD/10018/201522/02/201522/02/2015   27/02/2015   28/02/2015   10/03/2015 Social Forestry Division Unnao :14/03/2015Lucknow Circle Lucknow:
  20/03/2015 (Social Forestry Division Unnao)

Uttar Pradesh:
10/04/2015
Uttar Pradesh:
25/05/2015
15/10/2015
By :State Government
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by State Government (Uttar Pradesh) on:13/07/2015  
Replied by Nodal Officer (Uttar Pradesh) on:30/09/2015  
Query raised by Nodal Officer (Uttar Pradesh) on:08/04/2015  
Replied by Circle(Lucknow Circle Lucknow) on:07/05/2015  
Query raised by Nodal Officer (Uttar Pradesh) on:07/05/2015  
Replied by Circle(Lucknow Circle Lucknow) on:08/05/2015  
Query raised by Nodal Officer (Uttar Pradesh) on:08/05/2015  
Replied by Circle(Lucknow Circle Lucknow) on:11/05/2015  
Query raised by Nodal Officer (Uttar Pradesh) on:11/05/2015  
Replied by Circle(Lucknow Circle Lucknow) on:15/05/2015  
Query raised by Nodal Officer (Uttar Pradesh) on:20/05/2015  
Replied by Circle(Lucknow Circle Lucknow) on:21/05/2015  
Query raised by Nodal Officer (Uttar Pradesh) on:22/05/2015  
Replied by Circle(Lucknow Circle Lucknow) on:22/05/2015  
Query raised by Nodal Officer (Uttar Pradesh) on:13/07/2015  
Replied by Circle(Lucknow Circle Lucknow) on:25/09/2015  
Query raised by Circle (Lucknow Circle Lucknow) on:08/05/2015  
Replied by DFO (Social Forestry Division Unnao) on:08/05/2015  
Query raised by Circle (Lucknow Circle Lucknow) on:09/05/2015  
Replied by DFO (Social Forestry Division Unnao) on:10/05/2015  
Query raised by Circle (Lucknow Circle Lucknow) on:13/05/2015  
Replied by DFO (Social Forestry Division Unnao) on:15/05/2015  
Query raised by Circle (Lucknow Circle Lucknow) on:20/05/2015  
Replied by DFO (Social Forestry Division Unnao) on:21/05/2015  
Query raised by Circle (Lucknow Circle Lucknow) on:22/05/2015  
Replied by DFO (Social Forestry Division Unnao) on:22/05/2015  
Query raised by Circle (Lucknow Circle Lucknow) on:14/07/2015  
Replied by DFO (Social Forestry Division Unnao) on:14/09/2015  
NOTE:- Stage-I Approval accorded by : State Government .
Close(X)