| Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
|
1
|
DFO (Social Forestry Division Barabanki)
|
EDS
|
User Agency (iocl.divlko@gmail.com)
|
15/06/2019
|
complete proposals forworted
|
|
|
2
|
User Agency (iocl.divlko@gmail.com)
|
REPLY
|
DFO (Social Forestry Division Barabanki)
|
17/06/2019
|
The correction have been made as per the instruction received
|
|
|
3
|
Nodal Officer
|
EDS
|
CF (Saryu Circle Faizabad)
|
25/06/2019
|
EDS letter Attached.
|
|
|
4
|
CF (Saryu Circle Faizabad)
|
EDS
|
DFO (Social Forestry Division Barabanki)
|
27/06/2019
|
EDS Has not been Completed
|
|
|
5
|
DFO (Social Forestry Division Barabanki)
|
REPLY
|
CF (Saryu Circle Faizabad)
|
01/07/2019
|
EDS letter resolves
|
|
|
6
|
CF (Saryu Circle Faizabad)
|
REPLY
|
Nodal Officer
|
01/07/2019
|
EDS Completed
|
|