TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/UP/Others/35215/2018              (ii). Name of Project for which Forest Land is required : OFC LAYING BY BSNL AGRA FROM KM. CH. 44.700 TO 91.200 ON RHS OF A.B.K. ROAD (SH-62) IN TAH.- BAH & DISTT.-AGRA              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : OFC LAYING BY BSNL UNDER NOFN PROJECT (TO PROVIDE CONNECTIVITY TO GRAM PANCHAYATS OF THE COUNTRY) IN 46500 MTR. LENGTH FROM KM. CH. 44.700 TO 91.200 ON RHS OF AGRA-BAH-KACHORAGHAT ROAD (SH-62) BETWEEN VILL.- ARNOTA TO KACHORAGHAT IN TAH.- BAH & DISTT.-AGRA.              (iv). File no. : 01              (v). State : Uttar Pradesh              (vi). Category of the Project : Others              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 1.395
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentStage-I Approval onStage-II Approval on
FP/UP/Others/35215/201813/08/201826/12/2022  22/09/2022  11/02/2022  14/01/2022  24/08/2018   31/12/2022  23/09/2022  13/09/2022  08/02/2022  04/01/2022   29/09/2022   23/12/2022 Social Forestry Division Agra :06/01/2023Agra Circle Agra:
  06/04/2023 (Social Forestry Division Agra)

Uttar Pradesh:
28/04/2023
Uttar Pradesh:
28/07/2023
29/07/2023
By :State Government
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by Nodal Officer (Uttar Pradesh) on:02/05/2023  
Replied by Circle(Agra Circle Agra) on:26/06/2023  
Query raised by Nodal Officer (Uttar Pradesh) on:27/06/2023  
Replied by Circle(Agra Circle Agra) on:27/06/2023  
Query raised by Circle (Agra Circle Agra) on:07/04/2023  
Replied by DFO (Social Forestry Division Agra) on:18/04/2023  
Query raised by Circle (Agra Circle Agra) on:03/05/2023  
Replied by DFO (Social Forestry Division Agra) on:14/06/2023  
Query raised by DFO (Social Forestry Division Agra) on:07/01/2023  
Replied by UA on :18/03/2023  
Query raised by DFO (Social Forestry Division Agra) on:29/03/2023  
Replied by UA on :01/04/2023  
Query raised by DFO (Social Forestry Division Agra) on:13/05/2023  
Replied by UA on :17/05/2023  
Query raised by DFO (Social Forestry Division Agra) on:26/05/2023  
Replied by UA on :31/05/2023  
Query raised by DFO (Social Forestry Division Agra) on:02/06/2023  
Replied by UA on :14/06/2023  
NOTE:- Stage-I Approval accorded by : State Government .