| Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
|
1
|
DFO (Social Forestry Division Bijnor)
|
EDS
|
User Agency (vijaykkori@hpcl.in)
|
24/10/2018
|
Plz. Upload FRA Certificate.
|
|
|
2
|
User Agency (vijaykkori@hpcl.in)
|
REPLY
|
DFO (Social Forestry Division Bijnor)
|
14/01/2019
|
The correction have been made as per the instruction received
|
|
|
3
|
CF (Moradabad Circle Moradabad)
|
EDS
|
DFO (Social Forestry Division Bijnor)
|
23/01/2019
|
EDS letter attached.
|
|
|
4
|
DFO (Social Forestry Division Bijnor)
|
EDS
|
User Agency (vijaykkori@hpcl.in)
|
01/02/2019
|
Plz.Points no.1 part II and III is incorrect.
|
|
|
5
|
User Agency (vijaykkori@hpcl.in)
|
REPLY
|
DFO (Social Forestry Division Bijnor)
|
01/02/2019
|
The correction have been made as per the instruction received
|
|
|
6
|
DFO (Social Forestry Division Bijnor)
|
REPLY
|
CF (Moradabad Circle Moradabad)
|
02/02/2019
|
EDS of letter No,1969/14-1 dated 23-01-2019
|
|
|
7
|
CF (Moradabad Circle Moradabad)
|
EDS
|
DFO (Social Forestry Division Bijnor)
|
05/02/2019
|
Part -2 Bindu-15 incorrect.
|
|
|
8
|
DFO (Social Forestry Division Bijnor)
|
EDS
|
User Agency (vijaykkori@hpcl.in)
|
05/02/2019
|
Justification Area in Correct plz.correct area 0.078764 ha
|
|
|
9
|
User Agency (vijaykkori@hpcl.in)
|
REPLY
|
DFO (Social Forestry Division Bijnor)
|
06/02/2019
|
The correction have been made as per the instruction received
|
|
|
10
|
DFO (Social Forestry Division Bijnor)
|
EDS
|
User Agency (vijaykkori@hpcl.in)
|
11/02/2019
|
plz.upload labour .
|
|
|
11
|
User Agency (vijaykkori@hpcl.in)
|
REPLY
|
DFO (Social Forestry Division Bijnor)
|
18/02/2019
|
The correction have been made as per the instruction received
|
|
|
12
|
DFO (Social Forestry Division Bijnor)
|
REPLY
|
CF (Moradabad Circle Moradabad)
|
18/02/2019
|
EDS has been removed
|
|
|
13
|
Nodal Officer
|
EDS
|
CF (Moradabad Circle Moradabad)
|
22/02/2019
|
EDS letter is attached as PDF.
|
|
|
14
|
CF (Moradabad Circle Moradabad)
|
EDS
|
DFO (Social Forestry Division Bijnor)
|
25/02/2019
|
Remove query raised by nodal officer
|
|
|
15
|
DFO (Social Forestry Division Bijnor)
|
EDS
|
User Agency (vijaykkori@hpcl.in)
|
12/03/2019
|
plz.remove eds of Nodal officer date 22.02.2019
|
|
|
16
|
User Agency (vijaykkori@hpcl.in)
|
REPLY
|
DFO (Social Forestry Division Bijnor)
|
12/03/2019
|
The correction have been made as per the instruction received
|
|
|
17
|
DFO (Social Forestry Division Bijnor)
|
REPLY
|
CF (Moradabad Circle Moradabad)
|
12/03/2019
|
EDS has been removed as per direction of Nodal Officer Lucknow.
|
|
|
18
|
CF (Moradabad Circle Moradabad)
|
REPLY
|
Nodal Officer
|
18/03/2019
|
objection has been remove
|
|