TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/UP/Others/34755/2018              (ii). Name of Project for which Forest Land is required : Construction of Entry and Exit for New HPCL Retail Outlet and protected land is required to be diverted(UnderFCA Act 1980 for non forestry purpose) Along Bijnor- Haridwar Road km. 21 (RHS) khasra No.647 & Gata No.181 Tehsil Bijnor District Bijnor(U.P.)              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Construction of Entry and Exit for New HPCL Retail Outlet and protected land is required to be diverted(UnderFCA Act 1980 for non forestry purpose) Along Bijnor- Haridwar Road km. 21 (RHS) khasra No.647 and Gata No.181 Tehsil Bijnor District Bijnor (U.P.)              (iv). File no. : P-28/14-2-2019-800(47)/2019              (v). State : Uttar Pradesh              (vi). Category of the Project : Others              (vii). Shape of forest land proposed to be diverted : Non Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.078764
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentStage-I Approval onStage-II Approval on
FP/UP/Others/34755/201801/08/201818/09/2018  02/08/2018   26/09/2018  16/09/2018   27/09/2018   03/10/2018 Social Forestry Division Bijnor :03/10/2018Moradabad Circle Moradabad:
  14/01/2019 (Social Forestry Division Bijnor)

Uttar Pradesh:
20/02/2019
Uttar Pradesh:
25/03/2019
28/06/2019
By :State Government
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by Nodal Officer (Uttar Pradesh) on:22/02/2019  
Replied by Circle(Moradabad Circle Moradabad) on:18/03/2019  
Query raised by Circle (Moradabad Circle Moradabad) on:23/01/2019  
Replied by DFO (Social Forestry Division Bijnor) on:02/02/2019  
Query raised by Circle (Moradabad Circle Moradabad) on:05/02/2019  
Replied by DFO (Social Forestry Division Bijnor) on:18/02/2019  
Query raised by Circle (Moradabad Circle Moradabad) on:25/02/2019  
Replied by DFO (Social Forestry Division Bijnor) on:12/03/2019  
Query raised by DFO (Social Forestry Division Bijnor) on:24/10/2018  
Replied by UA on :14/01/2019  
Query raised by DFO (Social Forestry Division Bijnor) on:01/02/2019  
Replied by UA on :01/02/2019  
Query raised by DFO (Social Forestry Division Bijnor) on:05/02/2019  
Replied by UA on :06/02/2019  
Query raised by DFO (Social Forestry Division Bijnor) on:11/02/2019  
Replied by UA on :18/02/2019  
Query raised by DFO (Social Forestry Division Bijnor) on:12/03/2019  
Replied by UA on :12/03/2019  
NOTE:- Stage-I Approval accorded by : State Government .