| Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
|
1
|
CF (Moradabad Circle Moradabad)
|
EDS
|
DFO (Social Forestry Division Rampur)
|
09/08/2018
|
part-2 bindu no-13,i-copy of CA scheme incorrect,ii-scanned copy of the Geo-reference map incorrect,iv-copy of survey of india Toposheet incorrect.bintu no-15 Date of visit DFO.incorrect&etc.
|
|
|
2
|
DFO (Social Forestry Division Rampur)
|
REPLY
|
CF (Moradabad Circle Moradabad)
|
13/08/2018
|
EDS has been removed.
|
|
|
3
|
Nodal Officer
|
EDS
|
CF (Moradabad Circle Moradabad)
|
24/08/2018
|
EDS letter is attached as pdf.
|
|
|
4
|
CF (Moradabad Circle Moradabad)
|
EDS
|
DFO (Social Forestry Division Rampur)
|
27/08/2018
|
Remove query raised by nodal officer.
|
|
|
5
|
DFO (Social Forestry Division Rampur)
|
EDS
|
User Agency (dhawansk@indianoil.in)
|
28/09/2018
|
Plz. removed CF Moradabad EDS.
|
|
|
6
|
User Agency (dhawansk@indianoil.in)
|
REPLY
|
DFO (Social Forestry Division Rampur)
|
10/10/2018
|
The correction have been made as per the instruction received
|
|
|
7
|
DFO (Social Forestry Division Rampur)
|
REPLY
|
CF (Moradabad Circle Moradabad)
|
10/10/2018
|
FRA CERTIFICATE IS UPLOADED
|
|
|
8
|
DFO (Social Forestry Division Rampur)
|
REPLY
|
CF (Moradabad Circle Moradabad)
|
10/10/2018
|
FRA CERTIFICATE IS UPLOADED
|
|
|
9
|
CF (Moradabad Circle Moradabad)
|
REPLY
|
Nodal Officer
|
10/10/2018
|
Objections has been remove by DFO Rampur
|
|