TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/UP/Others/27358/2017              (ii). Name of Project for which Forest Land is required : City Gas Distribution (CGD) Network Porject in Saharanpur Geographical Area              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Laying BPCL's 200/150 mm dia Steel/MDPE Natural Gas Pipeline alongwith OFC to set up City Gas Distribution Network - Diversion of 6.3430 ha of Forest Land i.e.road side strip land on NH-73 (Km24.511 to Km57), SH-57, SH-59 declared as Protected Forest              (iv). File no. : 8B/UP/09/47/2018/FC              (v). State : Uttar Pradesh              (vi). Category of the Project : Others              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 6.343
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/UP/Others/27358/201725/07/201721/09/2017  08/09/2017  05/09/2017  01/09/2017  24/08/2017  21/08/2017  14/08/2017  28/07/2017   22/09/2017  11/09/2017  06/09/2017  01/09/2017  01/09/2017  21/08/2017  19/08/2017  10/08/2017   13/09/2017   19/09/2017

Social Forestry Division Saharanpur :22/09/2017


Forest Division Shiwalik, Saharanpur :22/09/2017

Saharanpur Circle Saharanpur:
  28/02/2018 (Forest Division Shiwalik, Saharanpur)

Saharanpur Circle Saharanpur:
  28/02/2018 (Social Forestry Division Saharanpur)

Uttar Pradesh:
08/03/2018
Uttar Pradesh:
02/04/2018
Lucknow:
19/04/2018
09/07/2018
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Lucknow) on:11/05/2018  
Replied by State Government(Uttar Pradesh) on:07/06/2018  
Query raised by State Government (Uttar Pradesh) on:23/05/2018  
Replied by Nodal Officer (Uttar Pradesh) on:01/06/2018  
Query raised by Nodal Officer (Uttar Pradesh) on:21/03/2018  
Replied by Circle(Saharanpur Circle Saharanpur) on:27/03/2018  
Query raised by Nodal Officer (Uttar Pradesh) on:24/05/2018  
Replied by Circle(Saharanpur Circle Saharanpur) on:30/05/2018  
Query raised by Circle (Saharanpur Circle Saharanpur) on:28/02/2018  
Replied by DFO (Forest Division Shiwalik, Saharanpur) on:08/03/2018  
Query raised by Circle (Saharanpur Circle Saharanpur) on:21/03/2018  
Replied by DFO (Social Forestry Division Saharanpur) on:26/03/2018  
Query raised by Circle (Saharanpur Circle Saharanpur) on:21/03/2018  
Replied by DFO (Forest Division Shiwalik, Saharanpur) on:26/03/2018  
Query raised by Circle (Saharanpur Circle Saharanpur) on:26/03/2018  
Query raised by Circle (Saharanpur Circle Saharanpur) on:26/03/2018  
Query raised by Circle (Saharanpur Circle Saharanpur) on:24/05/2018  
Replied by DFO (Forest Division Shiwalik, Saharanpur) on:30/05/2018  
Query raised by Circle (Saharanpur Circle Saharanpur) on:24/05/2018  
Replied by DFO (Social Forestry Division Saharanpur) on:30/05/2018  
Query raised by DFO (Social Forestry Division Saharanpur) on:05/10/2017  
Replied by UA on :29/12/2017  
Query raised by DFO (Social Forestry Division Saharanpur) on:29/12/2017  
Replied by UA on :01/01/2018  
Query raised by DFO (Forest Division Shiwalik, Saharanpur) on:09/01/2018  
Replied by UA on :02/02/2018  
Query raised by DFO (Social Forestry Division Saharanpur) on:13/02/2018  
Replied by UA on :19/02/2018  
Query raised by DFO (Forest Division Shiwalik, Saharanpur) on:22/03/2018  
Replied by UA on :26/03/2018  
Query raised by DFO (Forest Division Shiwalik, Saharanpur) on:26/03/2018  
Replied by UA on :26/03/2018  
NOTE:- Stage-I Approval accorded by : Regional Office .