Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Social Forestry Division Rampur)
|
EDS
|
User Agency (athakle@indianoil.in)
|
22/07/2017
|
plz. jionts inspection with R.O.Bilspur.
|
|
2
|
User Agency (athakle@indianoil.in)
|
REPLY
|
DFO (Social Forestry Division Rampur)
|
08/08/2017
|
The correction have been made as per the instruction received
|
|
3
|
Nodal Officer
|
EDS
|
CF (Moradabad Circle Moradabad)
|
22/08/2017
|
EDS letter attached.
|
|
4
|
CF (Moradabad Circle Moradabad)
|
EDS
|
DFO (Social Forestry Division Rampur)
|
23/08/2017
|
Remove query raised by nodal officers.
|
|
5
|
DFO (Social Forestry Division Rampur)
|
EDS
|
User Agency (athakle@indianoil.in)
|
29/08/2017
|
plz.upload correct area of diverted land.
|
|
6
|
User Agency (athakle@indianoil.in)
|
REPLY
|
DFO (Social Forestry Division Rampur)
|
30/08/2017
|
The correction have been made as per the instruction received
|
|
7
|
DFO (Social Forestry Division Rampur)
|
REPLY
|
CF (Moradabad Circle Moradabad)
|
30/08/2017
|
EDS has been removed.
|
|
8
|
CF (Moradabad Circle Moradabad)
|
EDS
|
DFO (Social Forestry Division Rampur)
|
31/08/2017
|
part-2 incarrct
|
|
9
|
DFO (Social Forestry Division Rampur)
|
REPLY
|
CF (Moradabad Circle Moradabad)
|
05/09/2017
|
CCF/Nodal lko EDS letter 488 dated 18.08.2017 EDS point wise hasbeen removed.
|
|
10
|
CF (Moradabad Circle Moradabad)
|
EDS
|
DFO (Social Forestry Division Rampur)
|
05/09/2017
|
part-1& part-2 incrrect.justification incrrect
|
|
11
|
DFO (Social Forestry Division Rampur)
|
EDS
|
User Agency (athakle@indianoil.in)
|
07/09/2017
|
plz.eds of CF Mbd remoed early
|
|
12
|
User Agency (athakle@indianoil.in)
|
REPLY
|
DFO (Social Forestry Division Rampur)
|
13/09/2017
|
The correction have been made as per the instruction received
|
|
13
|
DFO (Social Forestry Division Rampur)
|
EDS
|
User Agency (athakle@indianoil.in)
|
14/09/2017
|
plz Addition report s.no.1 is incorrect.
|
|
14
|
User Agency (athakle@indianoil.in)
|
REPLY
|
DFO (Social Forestry Division Rampur)
|
14/09/2017
|
The correction have been made as per the instruction received
|
|
15
|
DFO (Social Forestry Division Rampur)
|
REPLY
|
CF (Moradabad Circle Moradabad)
|
18/09/2017
|
EDS has Been removed.
|
|
16
|
CF (Moradabad Circle Moradabad)
|
REPLY
|
Nodal Officer
|
20/09/2017
|
Objection has been remove
|
|