TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/UP/Others/25152/2017              (ii). Name of Project for which Forest Land is required : M/s C&DS unit -18 UP Jal Nigam Moradabad by Proposed Amroha city water drainage from Faizeaam inter college Amroha to Baan river Along Amroha -Kanth Road (M.D.R. No. 150) km. chanaige 21.840 to 26.540 Tehsil &distric Amroha.              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Construction of drainage and protected forest land is required to be diverted (under FCA Act 1980 for Non forestry purpose) Along Faizeaam inter college Amroha to Baan river Along Amroha -Kanth Road (M.D.R. No. 150) km. chanaige 21.840 to 26.540 Tehsil &distric Amroha              (iv). File no. : 8B/UP/09/42/2017/FC              (v). State : Uttar Pradesh              (vi). Category of the Project : Others              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 1.692
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onCompliance Report Submitted by State onStage-II Approval on
FP/UP/Others/25152/201727/03/201728/03/2017   30/03/2017   30/03/2017   03/04/2017 J P Nagar :06/04/2017Amroha Circle:
  04/05/2017 (J P Nagar)

Uttar Pradesh:
24/05/2017
Uttar Pradesh:
07/07/2017
Lucknow:
07/07/2017
15/06/2018
By :Regional Office
Uttar Pradesh
24/01/2020
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Lucknow) on:24/07/2017  
Replied by State Government(Uttar Pradesh) on:15/01/2018  
Query raised by Regional Office (Lucknow) on:07/03/2018  
Replied by State Government(Uttar Pradesh) on:01/05/2018  
Query raised by State Government (Uttar Pradesh) on:28/07/2017  
Replied by Nodal Officer (Uttar Pradesh) on:15/01/2018  
Query raised by State Government (Uttar Pradesh) on:09/03/2018  
Replied by Nodal Officer (Uttar Pradesh) on:01/05/2018  
Query raised by Nodal Officer (Uttar Pradesh) on:01/06/2017  
Replied by Circle(Amroha Circle) on:23/06/2017  
Query raised by Nodal Officer (Uttar Pradesh) on:02/08/2017  
Replied by Circle(Amroha Circle) on:22/11/2017  
Query raised by Nodal Officer (Uttar Pradesh) on:04/12/2017  
Replied by Circle(Amroha Circle) on:09/01/2018  
Query raised by Nodal Officer (Uttar Pradesh) on:09/03/2018  
Replied by Circle(Amroha Circle) on:19/03/2018  
Query raised by Nodal Officer (Uttar Pradesh) on:11/04/2018  
Replied by Circle(Amroha Circle) on:18/04/2018  
Query raised by Circle (Amroha Circle) on:04/05/2017  
Replied by DFO (J P Nagar) on:08/05/2017  
Query raised by Circle (Amroha Circle) on:15/05/2017  
Replied by DFO (J P Nagar) on:22/05/2017  
Query raised by Circle (Amroha Circle) on:02/06/2017  
Replied by DFO (J P Nagar) on:21/06/2017  
Query raised by Circle (Amroha Circle) on:03/08/2017  
Replied by DFO (J P Nagar) on:21/06/2017  
Query raised by Circle (Amroha Circle) on:31/10/2017  
Replied by DFO (J P Nagar) on:28/10/2017  
Query raised by Circle (Amroha Circle) on:04/12/2017  
Replied by DFO (J P Nagar) on:20/11/2017  
Query raised by Circle (Amroha Circle) on:09/01/2018  
Replied by DFO (J P Nagar) on:09/01/2018  
Query raised by Circle (Amroha Circle) on:13/03/2018  
Replied by DFO (J P Nagar) on:09/01/2018  
Query raised by Circle (Amroha Circle) on:13/04/2018  
Replied by DFO (J P Nagar) on:09/01/2018  
Query raised by DFO (J P Nagar) on:09/06/2017  
Replied by UA on :20/06/2017  
Query raised by DFO (J P Nagar) on:16/08/2017  
Replied by UA on :19/09/2017  
Query raised by DFO (J P Nagar) on:26/12/2017  
Replied by UA on :26/12/2017  
Query raised by DFO (J P Nagar) on:30/12/2017  
Replied by UA on :30/12/2017  
D. Essential Details Sought History (Stage-II)
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & User Agency
Query raised by Regional Office (Lucknow) on:08/03/2021  
Replied by State Government(Uttar Pradesh) on:27/07/2022  
Query raised by Regional Office (Lucknow) on:10/08/2022  
Query raised by State Government (Uttar Pradesh) on:12/03/2021  
Replied by Nodal Officer (Uttar Pradesh) on:27/07/2022  
Query raised by State Government (Uttar Pradesh) on:18/08/2022  
Query raised by Nodal Officer on:12/03/2021  
Replied by UA on :27/07/2022  
Query raised by Nodal Officer on:22/08/2022  
Replied by UA on :  
NOTE:- Proposal is pending at User Agency due to EDS raised by RO for Stage-II .