TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/UP/Others/24318/2017              (ii). Name of Project for which Forest Land is required : Relicance 4G Project for Laying of Optical Fibre Cable (OFC) along with road on SH - 5 (Varanasi-Shaktinagar Road) from Km. 87.00 to 115.00, of total Km. 28.00 & 0.2901 Ha. in Social Forestry Division Obra, District: Obra - UP.              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Relicance 4G Project for Laying of Optical Fibre Cable (OFC) along with road on SH - 5 (Varanasi-Shaktinagar Road) from Km. 87.00 to 115.00, of total Km. 28.00 & 0.2901 Ha. in Social Forestry Division Obra, District: Obra - UP.              (iv). File no. : 2446/81-2-2020-800(161)/2017              (v). State : Uttar Pradesh              (vi). Category of the Project : Others              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.2901
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentStage-I Approval onStage-II Approval on
FP/UP/Others/24318/201705/04/201706/04/2017   17/04/2017   18/04/2017   13/05/2017 Forest Division Obra :15/05/2017Mirzapur Circle Mirzapur:
  14/06/2017 (Forest Division Obra)

Uttar Pradesh:
04/08/2017
Uttar Pradesh:
23/11/2017
29/12/2020
By :State Government
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by State Government (Uttar Pradesh) on:23/04/2018  
Replied by Nodal Officer (Uttar Pradesh) on:23/07/2018  
Query raised by State Government (Uttar Pradesh) on:30/08/2018  
Replied by Nodal Officer (Uttar Pradesh) on:25/10/2018  
Query raised by State Government (Uttar Pradesh) on:31/08/2020  
Replied by Nodal Officer (Uttar Pradesh) on:12/11/2020  
Query raised by State Government (Uttar Pradesh) on:20/11/2020  
Replied by Nodal Officer (Uttar Pradesh) on:20/11/2020  
Query raised by Nodal Officer (Uttar Pradesh) on:14/08/2017  
Replied by Circle(Mirzapur Circle Mirzapur) on:31/10/2017  
Query raised by Nodal Officer (Uttar Pradesh) on:25/04/2018  
Replied by Circle(Mirzapur Circle Mirzapur) on:20/07/2018  
Query raised by Nodal Officer (Uttar Pradesh) on:31/08/2018  
Replied by Circle(Mirzapur Circle Mirzapur) on:17/10/2018  
Query raised by Nodal Officer (Uttar Pradesh) on:22/10/2018  
Replied by Circle(Mirzapur Circle Mirzapur) on:24/10/2018  
Query raised by Nodal Officer (Uttar Pradesh) on:01/09/2020  
Replied by Circle(Mirzapur Circle Mirzapur) on:12/11/2020  
Query raised by Circle (Mirzapur Circle Mirzapur) on:14/08/2017  
Replied by DFO (Forest Division Obra) on:28/09/2017  
Query raised by Circle (Mirzapur Circle Mirzapur) on:27/04/2018  
Replied by DFO (Forest Division Obra) on:20/07/2018  
Query raised by Circle (Mirzapur Circle Mirzapur) on:04/09/2018  
Replied by DFO (Forest Division Obra) on:28/09/2018  
Query raised by Circle (Mirzapur Circle Mirzapur) on:03/09/2020  
Replied by DFO (Forest Division Obra) on:09/11/2020  
Query raised by DFO (Forest Division Obra) on:05/09/2017  
Replied by UA on :07/09/2017  
Query raised by DFO (Forest Division Obra) on:07/05/2018  
Replied by UA on :15/05/2018  
Query raised by DFO (Forest Division Obra) on:31/05/2018  
Replied by UA on :09/07/2018  
Query raised by DFO (Forest Division Obra) on:21/09/2020  
Replied by UA on :30/09/2020  
NOTE:- Stage-I Approval accorded by : State Government .