| Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
|
1
|
DFO (Social Forestry Division Hardoi)
|
EDS
|
User Agency (iocl.divlko@gmail.com)
|
31/08/2016
|
village name correction need
|
|
|
2
|
User Agency (iocl.divlko@gmail.com)
|
REPLY
|
DFO (Social Forestry Division Hardoi)
|
01/09/2016
|
The correction have been made as per the instruction received
|
|
|
3
|
Nodal Officer
|
EDS
|
CF (Lucknow Circle Lucknow)
|
28/09/2016
|
EDS raised vide letter dated 15-09-2016 and submit reply.
|
|
|
4
|
CF (Lucknow Circle Lucknow)
|
EDS
|
DFO (Social Forestry Division Hardoi)
|
26/10/2016
|
Please remove EDS raised by Nodal Officer.
|
|
|
5
|
DFO (Social Forestry Division Hardoi)
|
REPLY
|
CF (Lucknow Circle Lucknow)
|
27/10/2016
|
EDS has been completed
|
|
|
6
|
CF (Lucknow Circle Lucknow)
|
REPLY
|
Nodal Officer
|
02/11/2016
|
EDS removed by DFO.
|
|
|
7
|
State secretary
|
EDS
|
Nodal Officer
|
20/12/2016
|
please provide the proper information
|
|
|
8
|
Nodal Officer
|
EDS
|
CF (Lucknow Circle Lucknow)
|
22/12/2016
|
EDS raised vide letter dated 22-12-2016 and submit reply.
|
|
|
9
|
CF (Lucknow Circle Lucknow)
|
EDS
|
DFO (Social Forestry Division Hardoi)
|
02/01/2017
|
Please remove EDS raised by Nodal Officer.
|
|
|
10
|
DFO (Social Forestry Division Hardoi)
|
REPLY
|
CF (Lucknow Circle Lucknow)
|
06/07/2017
|
EDS Has been completed
|
|
|
11
|
CF (Lucknow Circle Lucknow)
|
REPLY
|
Nodal Officer
|
10/07/2017
|
EDS completed by DFO
|
|
|
12
|
Nodal Officer
|
REPLY
|
State secretary
|
18/07/2017
|
This proposal sanction by GoUP on 05.07.2017. Upload the sanction on portal.
|
|