Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Forest Division Renukoot)
|
EDS
|
User Agency (avinash.rai@adityabirla.com)
|
30/03/2022
|
Submit Hardcopy of proposal.
|
|
2
|
User Agency (avinash.rai@adityabirla.com)
|
REPLY
|
DFO (Forest Division Renukoot)
|
23/04/2022
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Forest Division Renukoot)
|
EDS
|
User Agency (avinash.rai@adityabirla.com)
|
27/04/2022
|
The Correction have been required as per discussion.
|
|
4
|
User Agency (avinash.rai@adityabirla.com)
|
REPLY
|
DFO (Forest Division Renukoot)
|
03/06/2022
|
The correction have been made as per the instruction received
|
|
5
|
Nodal Officer
|
EDS
|
CF (Mirzapur Circle Mirzapur)
|
04/07/2022
|
EDS letter attached.
|
|
6
|
CF (Mirzapur Circle Mirzapur)
|
EDS
|
DFO (Forest Division Renukoot)
|
05/07/2022
|
Eds letter attached
|
|
7
|
DFO (Forest Division Renukoot)
|
REPLY
|
CF (Mirzapur Circle Mirzapur)
|
13/07/2022
|
The correction have been made as per the instruction received
|
|
8
|
CF (Mirzapur Circle Mirzapur)
|
EDS
|
DFO (Forest Division Renukoot)
|
25/07/2022
|
SoI Toposheet is incorrect.
|
|
9
|
DFO (Forest Division Renukoot)
|
REPLY
|
CF (Mirzapur Circle Mirzapur)
|
29/07/2022
|
Now SOI Toposheet is corrected.
|
|
10
|
CF (Mirzapur Circle Mirzapur)
|
REPLY
|
Nodal Officer
|
29/07/2022
|
Eds letter hasbeen remove
|
|
11
|
State secretary
|
EDS
|
Nodal Officer
|
07/09/2022
|
eds
|
|
12
|
Nodal Officer
|
EDS
|
CF (Mirzapur Circle Mirzapur)
|
08/09/2022
|
EDS letter attached.
|
|
13
|
CF (Mirzapur Circle Mirzapur)
|
EDS
|
DFO (Forest Division Renukoot)
|
09/09/2022
|
Eds letter attached
|
|
14
|
DFO (Forest Division Renukoot)
|
REPLY
|
CF (Mirzapur Circle Mirzapur)
|
28/09/2022
|
The correction have been made as per the instruction received
|
|
15
|
CF (Mirzapur Circle Mirzapur)
|
REPLY
|
Nodal Officer
|
03/10/2022
|
Eds letter attached
|
|
16
|
Nodal Officer
|
REPLY
|
State secretary
|
04/10/2022
|
EDS Removed.
|
|
17
|
State secretary
|
EDS
|
Nodal Officer
|
12/09/2023
|
eds
|
|
18
|
Nodal Officer
|
EDS
|
CF (Mirzapur Circle Mirzapur)
|
12/09/2023
|
EDS Letter attached.
|
|
19
|
CF (Mirzapur Circle Mirzapur)
|
EDS
|
DFO (Forest Division Renukoot)
|
13/09/2023
|
Eds letter attached
|
|
20
|
DFO (Forest Division Renukoot)
|
EDS
|
User Agency (gil-rnq.uhoffice@adityabirla.com)
|
16/09/2023
|
EDS Letter Attached
|
|
21
|
User Agency (gil-rnq.uhoffice@adityabirla.com)
|
REPLY
|
DFO (Forest Division Renukoot)
|
26/02/2024
|
The correction have been made as per the instruction received
|
|
22
|
DFO (Forest Division Renukoot)
|
REPLY
|
CF (Mirzapur Circle Mirzapur)
|
04/03/2024
|
EDS
|
|
23
|
CF (Mirzapur Circle Mirzapur)
|
REPLY
|
Nodal Officer
|
04/03/2024
|
Eds letter hasbeen remove
|
|
24
|
Nodal Officer
|
REPLY
|
State secretary
|
05/03/2024
|
EDS Removed.
|
|