TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/UP/Others/17653/2016              (ii). Name of Project for which Forest Land is required : Proposed Laying of BSNL OFC Cable on NH-24(Lucknow-Sitapur)Road from CH.KM. 70.600-55.100              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Proposed Laying of BSNL OFC Cable on NH-24(Lucknow-Sitapur)Road from CH.KM. 70.600-55.100 in Forest Division:Awadh,District:Lucknow Required Forest Area is 0.6975Ha.              (iv). File no. : P-28/14-2-2017-800(24)/2017              (v). State : Uttar Pradesh              (vi). Category of the Project : Others              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.6975
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentStage-I Approval onStage-II Approval on
FP/UP/Others/17653/201624/05/201613/06/2016  30/05/2016   17/06/2016  02/06/2016   21/06/2016   07/09/2016 Awadh Forest Division Lucknow :14/09/2016Lucknow Circle Lucknow:
  15/02/2017 (Awadh Forest Division Lucknow)

Uttar Pradesh:
16/02/2017
Uttar Pradesh:
28/02/2017
17/05/2017
By :State Government
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by Nodal Officer (Uttar Pradesh) on:21/02/2017  
Replied by Circle(Lucknow Circle Lucknow) on:22/02/2017  
Query raised by Nodal Officer (Uttar Pradesh) on:27/02/2017  
Replied by Circle(Lucknow Circle Lucknow) on:28/02/2017  
Query raised by Circle (Lucknow Circle Lucknow) on:22/02/2017  
Replied by DFO (Awadh Forest Division Lucknow) on:22/02/2017  
Query raised by Circle (Lucknow Circle Lucknow) on:27/02/2017  
Replied by DFO (Awadh Forest Division Lucknow) on:28/02/2017  
Query raised by DFO (Awadh Forest Division Lucknow) on:03/10/2016  
Replied by UA on :18/01/2017  
NOTE:- Stage-I Approval accorded by : State Government .