Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
Nodal Officer
|
EDS
|
CF (Moradabad Circle Moradabad)
|
29/12/2015
|
Basic information viz. KML file, CA scheme, etc. have not been uploaded. Go through the form carefully and provide complete information as per the requirement of online portal.
|
|
2
|
CF (Moradabad Circle Moradabad)
|
EDS
|
DFO (Social Forestry Division Bijnor)
|
05/01/2016
|
It is to cetify that as per joint inspection report which is attachted
|
|
3
|
DFO (Social Forestry Division Bijnor)
|
REPLY
|
CF (Moradabad Circle Moradabad)
|
06/01/2016
|
It is to cetify that as per joint inspection report which is attachment-4. There is no density of vegetation (trees) in the forest land which has to be used by the user agency for the purpose of entry & exit. Therefor cutting and felling of trees (vegetation) is not required. In this view according to guidelines of form part-II at serial no.4 (II) compansatory afforestation is not required.
|
|
4
|
CF (Moradabad Circle Moradabad)
|
EDS
|
DFO (Social Forestry Division Bijnor)
|
10/03/2016
|
ccf/nodal officer lko has been raised EDS like provide CA scheme duly geo-map, topo sheet, kml, CA estimate and replied nodal letter no.81TC/Bijnor/15797/up-162/2015 date 07.01.2015
|
|
5
|
DFO (Social Forestry Division Bijnor)
|
REPLY
|
CF (Moradabad Circle Moradabad)
|
11/03/2016
|
Provide/Upload Geo mep, topo sheet kml file and site selection cer, and CA scheme
|
|
6
|
CF (Moradabad Circle Moradabad)
|
REPLY
|
Nodal Officer
|
23/03/2016
|
EDS letter no 81TC/BIJNOR/15797/UP-62/2016 DATED 07-01-2016 Removal of EDS by of your direction
|
|
7
|
State secretary
|
EDS
|
Nodal Officer
|
27/05/2016
|
please provide the required information
|
|
8
|
Nodal Officer
|
EDS
|
CF (Moradabad Circle Moradabad)
|
09/06/2016
|
EDS raised vide letter dated 31-05-2016 submit reply.
|
|
9
|
CF (Moradabad Circle Moradabad)
|
EDS
|
DFO (Social Forestry Division Bijnor)
|
25/06/2016
|
Plz under secretery forerst department of Sg letter date 27.5.2016 removed EDS.
|
|
10
|
DFO (Social Forestry Division Bijnor)
|
EDS
|
User Agency (gulshan.sethi@essar.com)
|
28/06/2016
|
Upload to all certificate
|
|
11
|
User Agency (gulshan.sethi@essar.com)
|
REPLY
|
DFO (Social Forestry Division Bijnor)
|
04/07/2016
|
The correction have been made as per the instruction received
|
|
12
|
DFO (Social Forestry Division Bijnor)
|
REPLY
|
CF (Moradabad Circle Moradabad)
|
04/07/2016
|
Remove all objection
|
|
13
|
CF (Moradabad Circle Moradabad)
|
REPLY
|
Nodal Officer
|
12/07/2016
|
All objection remove
|
|
14
|
Nodal Officer
|
REPLY
|
State secretary
|
28/07/2016
|
EDS replied dated 25.07.2016.
|
|
15
|
State secretary
|
EDS
|
Nodal Officer
|
10/08/2016
|
please provide the required information
|
|
16
|
Nodal Officer
|
EDS
|
CF (Moradabad Circle Moradabad)
|
26/08/2016
|
EDS raised dt. 12.08.2016
|
|
17
|
CF (Moradabad Circle Moradabad)
|
REPLY
|
Nodal Officer
|
06/09/2016
|
all objections has removed vide DFO Bijnore letter no. 27/14-1 dt. 04-07-2016
|
|
18
|
Nodal Officer
|
EDS
|
CF (Moradabad Circle Moradabad)
|
21/09/2016
|
Submit answer EDS letter dated 12-08-16 of this office.
|
|
19
|
CF (Moradabad Circle Moradabad)
|
EDS
|
DFO (Social Forestry Division Bijnor)
|
22/09/2016
|
EDS letter SG dated 10.08.2016 and Nodal officer lko.Removal of Eds As per Norms.
|
|
20
|
DFO (Social Forestry Division Bijnor)
|
REPLY
|
CF (Moradabad Circle Moradabad)
|
26/09/2016
|
remove objection
|
|
21
|
CF (Moradabad Circle Moradabad)
|
REPLY
|
Nodal Officer
|
27/09/2016
|
Answer of the Query of U.P Government send to Cf moradabad letter no 840/22-2, Dated 27-09-2016
|
|
22
|
Nodal Officer
|
REPLY
|
State secretary
|
30/09/2016
|
EDS replied dated 28-09-2016.
|
|
23
|
Regional Office
|
EDS
|
State secretary
|
07/12/2016
|
EDS
|
|
24
|
State secretary
|
EDS
|
Nodal Officer
|
20/12/2016
|
please provide the proper information
|
|
25
|
Nodal Officer
|
EDS
|
CF (Moradabad Circle Moradabad)
|
20/12/2016
|
EDS raised vide letter dated 09-12-2016 and submit reply.
|
|
26
|
CF (Moradabad Circle Moradabad)
|
EDS
|
DFO (Social Forestry Division Bijnor)
|
21/12/2016
|
Remove query raised by govt.of India dated 6/12/2016
|
|
27
|
DFO (Social Forestry Division Bijnor)
|
EDS
|
User Agency (gulshan.sethi@essar.com)
|
21/12/2016
|
Remove query raised by govt.of India dated 6/12/2016
|
|
28
|
User Agency (gulshan.sethi@essar.com)
|
REPLY
|
DFO (Social Forestry Division Bijnor)
|
23/12/2016
|
The correction have been made as per the instruction received
|
|
29
|
DFO (Social Forestry Division Bijnor)
|
REPLY
|
CF (Moradabad Circle Moradabad)
|
23/12/2016
|
All observation are removed
|
|
30
|
CF (Moradabad Circle Moradabad)
|
REPLY
|
Nodal Officer
|
26/12/2016
|
All objection has been remove
|
|
31
|
Nodal Officer
|
REPLY
|
State secretary
|
27/12/2016
|
EDS replied.
|
|
32
|
State secretary
|
REPLY
|
Regional Office
|
10/01/2017
|
EDS replied.
|
|