TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/UP/Others/123011/2021              (ii). Name of Project for which Forest Land is required : Forest land Proposed to be diverted for laying of underground 33/11KV cable at Bareilly-Pilibhit Road Near Civil Enclave (Airport) in Distt Bareilly              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Forest land Proposed to be diverted for laying of underground 33/11KV cable at Bareilly-Pilibhit Road Near Civil Enclave (Airport) in Distt Bareilly              (iv). State : Uttar Pradesh              (v). Category of the Project : Others              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 0.0714
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/UP/Others/123011/202115/02/2021aa24/02/2021   27/02/2021 Social Forestry Division Bareilly :02/03/2021Bareilly Circle Bareilly:
  27/04/2021 (Social Forestry Division Bareilly)

Uttar Pradesh:
05/05/2021
Uttar Pradesh:
29/05/2021
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by State Government (Uttar Pradesh) on:12/06/2021  
Replied by Nodal Officer (Uttar Pradesh) on:14/07/2021  
Query raised by Nodal Officer (Uttar Pradesh) on:13/05/2021  
Replied by Circle(Bareilly Circle Bareilly) on:25/05/2021  
Query raised by Nodal Officer (Uttar Pradesh) on:15/06/2021  
Replied by Circle(Bareilly Circle Bareilly) on:06/07/2021  
Query raised by Circle (Bareilly Circle Bareilly) on:27/04/2021  
Replied by DFO (Social Forestry Division Bareilly) on:27/04/2021  
Query raised by Circle (Bareilly Circle Bareilly) on:30/06/2021  
Replied by DFO (Social Forestry Division Bareilly) on:02/07/2021  
NOTE:- Proposal is pending at State Government .
Close(X)