  (i). Proposal No. : FP/UP/OFC/153034/2022              (ii). Name of Project for which Forest Land is required : OFC Laying in 15.873 KM. length along Agra-Jagner-Tantpur Road (SH-39) from Km. Ch. 205.000 to 220.873 on RHS by BSNL, Agra (under NOFN Project) in Distt. Agra (U.P.)              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Proposal to use 0.4762 Hac. PF Land for OFC Laying in 15.873 KM. length along Agra-Jagner-Tantpur Road (SH-39) from Km. Ch. 205.000 to 220.873 on RHS (To provide Hi-speed Internet connectivity to all Village panchayats of the country under NOFN Project) by BSNL, Agra in Distt. Agra (U.P.)              (iv). File no. : 2872              (v). State : Uttar Pradesh              (vi). Category of the Project : Optical Fibre Cable              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.4762
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentStage-I Approval onStage-II Approval on
FP/UP/OFC/153034/202209/03/202209/09/2022  30/05/2022  16/03/2022   13/09/2022  01/06/2022  26/05/2022   02/06/2022   09/09/2022 Social Forestry Division Agra :14/09/2022Agra Circle Agra:
  07/12/2022 (Social Forestry Division Agra)

Uttar Pradesh:
22/12/2022
Uttar Pradesh:
28/07/2023
29/07/2023
By :State Government
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by Nodal Officer (Uttar Pradesh) on:23/12/2022  
Replied by Circle(Agra Circle Agra) on:28/02/2023  
Query raised by Circle (Agra Circle Agra) on:09/12/2022  
Replied by DFO (Social Forestry Division Agra) on:14/12/2022  
Query raised by Circle (Agra Circle Agra) on:25/12/2022  
Replied by DFO (Social Forestry Division Agra) on:25/02/2023  
Query raised by DFO (Social Forestry Division Agra) on:24/09/2022  
Replied by UA on :02/11/2022  
Query raised by DFO (Social Forestry Division Agra) on:27/12/2022  
Replied by UA on :17/01/2023  
Query raised by DFO (Social Forestry Division Agra) on:20/01/2023  
Replied by UA on :27/01/2023  
Query raised by DFO (Social Forestry Division Agra) on:30/01/2023  
Replied by UA on :14/02/2023  
NOTE:- Stage-I Approval accorded by : State Government .