Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Forest Division Renukoot)
|
EDS
|
User Agency (nodalofficerenvbina@gmail.com)
|
11/06/2020
|
Findout the attatchment.
|
|
2
|
User Agency (nodalofficerenvbina@gmail.com)
|
REPLY
|
DFO (Forest Division Renukoot)
|
31/12/2020
|
The correction have been made as per the instruction received
|
|
3
|
CF (Mirzapur Circle Mirzapur)
|
EDS
|
DFO (Forest Division Renukoot)
|
19/01/2021
|
No hard copy send
|
|
4
|
DFO (Forest Division Renukoot)
|
EDS
|
User Agency (nodalofficerenvbina@gmail.com)
|
01/02/2021
|
Hardcopy not completed according to instruction.
|
|
5
|
User Agency (nodalofficerenvbina@gmail.com)
|
REPLY
|
DFO (Forest Division Renukoot)
|
03/02/2021
|
The correction have been made as per the instruction received
|
|
6
|
DFO (Forest Division Renukoot)
|
REPLY
|
CF (Mirzapur Circle Mirzapur)
|
03/02/2021
|
Hard Copy Send
|
|
7
|
CF (Mirzapur Circle Mirzapur)
|
EDS
|
DFO (Forest Division Renukoot)
|
09/02/2021
|
Eds letter Attached
|
|
8
|
DFO (Forest Division Renukoot)
|
EDS
|
User Agency (nodalofficerenvbina@gmail.com)
|
16/02/2021
|
Eds letter Attached
|
|
9
|
User Agency (nodalofficerenvbina@gmail.com)
|
REPLY
|
DFO (Forest Division Renukoot)
|
18/03/2021
|
The correction have been made as per the instruction received
|
|
10
|
DFO (Forest Division Renukoot)
|
REPLY
|
CF (Mirzapur Circle Mirzapur)
|
23/03/2021
|
The correction have been made as per the instruction received
|
|
11
|
CF (Mirzapur Circle Mirzapur)
|
EDS
|
DFO (Forest Division Renukoot)
|
26/03/2021
|
Eds letter attached
|
|
12
|
DFO (Forest Division Renukoot)
|
EDS
|
User Agency (nodalofficerenvbina@gmail.com)
|
31/03/2021
|
Eds letter attached
|
|
13
|
User Agency (nodalofficerenvbina@gmail.com)
|
REPLY
|
DFO (Forest Division Renukoot)
|
08/04/2021
|
The correction have been made as per the instruction received
|
|
14
|
DFO (Forest Division Renukoot)
|
REPLY
|
CF (Mirzapur Circle Mirzapur)
|
12/04/2021
|
Correction have been made.
|
|
15
|
Nodal Officer
|
EDS
|
CF (Mirzapur Circle Mirzapur)
|
20/04/2021
|
EDS Letter attached.
|
|
16
|
CF (Mirzapur Circle Mirzapur)
|
EDS
|
DFO (Forest Division Renukoot)
|
20/04/2021
|
Eds letter attached
|
|
17
|
DFO (Forest Division Renukoot)
|
EDS
|
User Agency (nodalofficerenvbina@gmail.com)
|
27/04/2021
|
Eds letter attached
|
|
18
|
User Agency (nodalofficerenvbina@gmail.com)
|
REPLY
|
DFO (Forest Division Renukoot)
|
03/06/2021
|
The correction have been made as per the instruction received
|
|
19
|
DFO (Forest Division Renukoot)
|
REPLY
|
CF (Mirzapur Circle Mirzapur)
|
14/06/2021
|
The correction have been made
|
|
20
|
CF (Mirzapur Circle Mirzapur)
|
EDS
|
DFO (Forest Division Renukoot)
|
14/06/2021
|
No hard copy send
|
|
21
|
DFO (Forest Division Renukoot)
|
REPLY
|
CF (Mirzapur Circle Mirzapur)
|
16/06/2021
|
The correction have been made
|
|
22
|
CF (Mirzapur Circle Mirzapur)
|
REPLY
|
Nodal Officer
|
22/06/2021
|
Eds letter has been remove
|
|
23
|
State secretary
|
EDS
|
Nodal Officer
|
12/07/2021
|
Please provide the proper information
|
|
24
|
Nodal Officer
|
EDS
|
CF (Mirzapur Circle Mirzapur)
|
13/07/2021
|
EDS Letter attached.
|
|
25
|
CF (Mirzapur Circle Mirzapur)
|
EDS
|
DFO (Forest Division Renukoot)
|
14/07/2021
|
Eds letter attached
|
|
26
|
DFO (Forest Division Renukoot)
|
EDS
|
User Agency (nodalofficerenvbina@gmail.com)
|
17/07/2021
|
Eds letter attached
|
|
27
|
User Agency (nodalofficerenvbina@gmail.com)
|
REPLY
|
DFO (Forest Division Renukoot)
|
21/07/2021
|
The correction have been made as per the instruction received
|
|
28
|
DFO (Forest Division Renukoot)
|
REPLY
|
CF (Mirzapur Circle Mirzapur)
|
27/07/2021
|
The correction have been made
|
|
29
|
CF (Mirzapur Circle Mirzapur)
|
REPLY
|
Nodal Officer
|
02/08/2021
|
Eds letter has been remove
|
|
30
|
Nodal Officer
|
REPLY
|
State secretary
|
06/08/2021
|
EDS Removed.
|
|
31
|
State secretary
|
EDS
|
Nodal Officer
|
10/09/2021
|
Please provide the proper information
|
|
32
|
Nodal Officer
|
EDS
|
CF (Mirzapur Circle Mirzapur)
|
13/09/2021
|
EDS Letter attached.
|
|
33
|
CF (Mirzapur Circle Mirzapur)
|
EDS
|
DFO (Forest Division Renukoot)
|
16/09/2021
|
Eds letter attached
|
|
34
|
DFO (Forest Division Renukoot)
|
EDS
|
User Agency (nodalofficerenvbina@gmail.com)
|
23/09/2021
|
Eds letter attached
|
|
35
|
User Agency (nodalofficerenvbina@gmail.com)
|
REPLY
|
DFO (Forest Division Renukoot)
|
06/10/2021
|
The correction have been made as per the instruction received
|
|
36
|
DFO (Forest Division Renukoot)
|
REPLY
|
CF (Mirzapur Circle Mirzapur)
|
18/10/2021
|
Query Replied
|
|
37
|
CF (Mirzapur Circle Mirzapur)
|
REPLY
|
Nodal Officer
|
22/10/2021
|
Eds letter has been remove
|
|
38
|
Nodal Officer
|
REPLY
|
State secretary
|
25/10/2021
|
EDS Removed.
|
|
39
|
State secretary
|
EDS
|
Nodal Officer
|
27/01/2022
|
EDS
|
|
40
|
Nodal Officer
|
EDS
|
CF (Mirzapur Circle Mirzapur)
|
27/01/2022
|
EDS Letter attached.
|
|
41
|
CF (Mirzapur Circle Mirzapur)
|
EDS
|
DFO (Forest Division Renukoot)
|
31/01/2022
|
Eds letter attached
|
|
42
|
DFO (Forest Division Renukoot)
|
EDS
|
User Agency (nodalofficerenvbina@gmail.com)
|
01/02/2022
|
Information required as per issued Government Letter
|
|
43
|
User Agency (nodalofficerenvbina@gmail.com)
|
REPLY
|
DFO (Forest Division Renukoot)
|
07/02/2022
|
The correction have been made as per the instruction received
|
|
44
|
DFO (Forest Division Renukoot)
|
REPLY
|
CF (Mirzapur Circle Mirzapur)
|
07/02/2022
|
The correction have been made as per the instruction received
|
|
45
|
CF (Mirzapur Circle Mirzapur)
|
REPLY
|
Nodal Officer
|
09/02/2022
|
Eds letter hasbeen remove
|
|
46
|
Nodal Officer
|
REPLY
|
State secretary
|
14/02/2022
|
EDS Removed.
|
|
47
|
Regional Office
|
EDS
|
State secretary
|
12/04/2022
|
EDS
|
|
48
|
State secretary
|
EDS
|
Nodal Officer
|
13/04/2022
|
EDS
|
|
49
|
Nodal Officer
|
EDS
|
CF (Mirzapur Circle Mirzapur)
|
13/04/2022
|
EDS letter has been send by E-Mail.
|
|
50
|
CF (Mirzapur Circle Mirzapur)
|
EDS
|
DFO (Forest Division Renukoot)
|
19/04/2022
|
EDS letter has been send by E-Mail.
|
|
51
|
DFO (Forest Division Renukoot)
|
EDS
|
User Agency (nodalofficerenvbina@gmail.com)
|
22/04/2022
|
Eds letter attached
|
|
52
|
User Agency (nodalofficerenvbina@gmail.com)
|
REPLY
|
DFO (Forest Division Renukoot)
|
16/07/2022
|
The correction have been made as per the instruction received
|
|
53
|
DFO (Forest Division Renukoot)
|
EDS
|
User Agency (nodalofficerenvbina@gmail.com)
|
21/07/2022
|
Information required as per enclosed letter.
|
|
54
|
User Agency (nodalofficerenvbina@gmail.com)
|
REPLY
|
DFO (Forest Division Renukoot)
|
06/10/2022
|
The correction have been made as per the instruction received
|
|
55
|
DFO (Forest Division Renukoot)
|
EDS
|
User Agency (nodalofficerenvbina@gmail.com)
|
10/10/2022
|
Hardcopy submitted but some annexure required as per hardcopy.
|
|
56
|
User Agency (nodalofficerenvbina@gmail.com)
|
REPLY
|
DFO (Forest Division Renukoot)
|
18/10/2022
|
The correction have been made as per the instruction received
|
|
57
|
DFO (Forest Division Renukoot)
|
REPLY
|
CF (Mirzapur Circle Mirzapur)
|
03/11/2022
|
Hard copy submitted.
|
|
58
|
CF (Mirzapur Circle Mirzapur)
|
REPLY
|
Nodal Officer
|
09/11/2022
|
eds remove
|
|
59
|
Nodal Officer
|
EDS
|
CF (Mirzapur Circle Mirzapur)
|
14/11/2022
|
EDS Letter attached.
|
|
60
|
CF (Mirzapur Circle Mirzapur)
|
REPLY
|
Nodal Officer
|
17/11/2022
|
EDS Latter atached
|
|
61
|
Nodal Officer
|
EDS
|
CF (Mirzapur Circle Mirzapur)
|
17/11/2022
|
EDS Letter attached.
|
|
62
|
CF (Mirzapur Circle Mirzapur)
|
EDS
|
DFO (Forest Division Renukoot)
|
18/11/2022
|
Eds letter attached
|
|
63
|
DFO (Forest Division Renukoot)
|
EDS
|
User Agency (nodalofficerenvbina@gmail.com)
|
23/11/2022
|
Eds letter attached
|
|
64
|
User Agency (nodalofficerenvbina@gmail.com)
|
REPLY
|
DFO (Forest Division Renukoot)
|
26/12/2022
|
The correction have been made as per the instruction received
|
|
65
|
DFO (Forest Division Renukoot)
|
EDS
|
User Agency (nodalofficerenvbina@gmail.com)
|
30/12/2022
|
due to Hardcopy incomplete
|
|
66
|
User Agency (nodalofficerenvbina@gmail.com)
|
REPLY
|
DFO (Forest Division Renukoot)
|
31/12/2022
|
The correction have been made as per the instruction received
|
|
67
|
DFO (Forest Division Renukoot)
|
EDS
|
User Agency (nodalofficerenvbina@gmail.com)
|
18/01/2023
|
due to CA land KML file & other related document not received.
|
|
68
|
User Agency (nodalofficerenvbina@gmail.com)
|
REPLY
|
DFO (Forest Division Renukoot)
|
22/01/2023
|
The correction have been made as per the instruction received
|
|
69
|
DFO (Forest Division Renukoot)
|
REPLY
|
CF (Mirzapur Circle Mirzapur)
|
23/01/2023
|
The correction have been made as per the instruction received
|
|
70
|
CF (Mirzapur Circle Mirzapur)
|
REPLY
|
Nodal Officer
|
02/02/2023
|
EDS Remove file attach
|
|
71
|
Nodal Officer
|
REPLY
|
State secretary
|
09/02/2023
|
EDS Removed.
|
|
72
|
State secretary
|
REPLY
|
Regional Office
|
09/02/2023
|
EDS Removed.
|
|
73
|
Regional Office
|
EDS
|
State secretary
|
29/03/2023
|
EDS
|
|
74
|
State secretary
|
EDS
|
Nodal Officer
|
01/05/2023
|
eds
|
|
75
|
Nodal Officer
|
EDS
|
CF (Mirzapur Circle Mirzapur)
|
01/05/2023
|
EDS Letter attached.
|
|
76
|
CF (Mirzapur Circle Mirzapur)
|
EDS
|
DFO (Forest Division Renukoot)
|
08/05/2023
|
Eds letter attached
|
|
77
|
DFO (Forest Division Renukoot)
|
EDS
|
User Agency (nodalofficerenvbina@gmail.com)
|
17/05/2023
|
Infrmation requrid as per Dfo Letter 3833 date 17-05-23
|
|
78
|
User Agency (nodalofficerenvbina@gmail.com)
|
REPLY
|
DFO (Forest Division Renukoot)
|
19/09/2023
|
The correction have been made as per the instruction received
|
|
79
|
DFO (Forest Division Renukoot)
|
EDS
|
User Agency (nodalofficerenvbina@gmail.com)
|
21/09/2023
|
EDS Letter attached as per instruction
|
|
80
|
User Agency (nodalofficerenvbina@gmail.com)
|
REPLY
|
DFO (Forest Division Renukoot)
|
07/10/2024
|
The correction have been made as per the instruction received
|
|
81
|
DFO (Forest Division Renukoot)
|
EDS
|
User Agency (nodalofficerenvbina@gmail.com)
|
08/10/2024
|
EDS Letter attached as per instruction
|
|
82
|
User Agency (nodalofficerenvbina@gmail.com)
|
REPLY
|
DFO (Forest Division Renukoot)
|
05/01/2025
|
The correction have been made as per the instruction received
|
|
83
|
DFO (Forest Division Renukoot)
|
EDS
|
User Agency (nodalofficerenvbina@gmail.com)
|
21/01/2025
|
Hard copy reply not received
|
|
84
|
User Agency (nodalofficerenvbina@gmail.com)
|
REPLY
|
DFO (Forest Division Renukoot)
|
23/01/2025
|
The correction have been made as per the instruction received
|
|