  (i). Proposal No. : FP/UP/Approach/49598/2020              (ii). Name of Project for which Forest Land is required : Forest Land Proposed to be diverted for Approach Access to Sikka Hotel developed by Real Virtual Works Pvt. Ltd at Bareilly-Rampur Road, KM-242, Ch 241.650, Plot No. CP3, Vill-C.B. Ganj, Tehsil Sadar, Distt Bareilly              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Forest Land Proposed to be diverted for Approach Access to Sikka Hotel developed by Real Virtual Works Pvt. Ltd at Bareilly-Rampur Road, KM-242, Ch 241.650, Plot No. CP3, Vill-C.B. Ganj, Tehsil Sadar, Distt Bareilly              (iv). State : Uttar Pradesh              (v). Category of the Project : Approach Access              (vi). Shape of forest land proposed to be diverted : Non Linear              (vii). Area of forest land proposed for diversion(in ha.): 0.0922187
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/UP/Approach/49598/202010/09/202016/09/2020  14/09/2020   21/09/2020  14/09/2020   22/09/2020   02/10/2020 Social Forestry Division Bareilly :03/10/2020Bareilly Circle Bareilly:
  14/10/2021 (Social Forestry Division Bareilly)

Uttar Pradesh:
31/07/2024
Uttar Pradesh:
03/08/2024
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by State Government (Uttar Pradesh) on:19/09/2024  
Replied by Nodal Officer (Uttar Pradesh) on:18/12/2024  
Query raised by State Government (Uttar Pradesh) on:24/02/2025  
Query raised by Nodal Officer (Uttar Pradesh) on:19/09/2024  
Replied by Circle(Bareilly Circle Bareilly) on:02/12/2024  
Query raised by Nodal Officer (Uttar Pradesh) on:04/12/2024  
Replied by Circle(Bareilly Circle Bareilly) on:13/12/2024  
Query raised by Nodal Officer (Uttar Pradesh) on:03/03/2025  
Replied by Circle() on:  
Query raised by Circle (Bareilly Circle Bareilly) on:22/10/2021  
Replied by DFO (Social Forestry Division Bareilly) on:28/12/2021  
Query raised by Circle (Bareilly Circle Bareilly) on:11/01/2022  
Replied by DFO (Social Forestry Division Bareilly) on:18/01/2022  
Query raised by Circle (Bareilly Circle Bareilly) on:23/01/2022  
Replied by DFO (Social Forestry Division Bareilly) on:05/06/2024  
Query raised by Circle (Bareilly Circle Bareilly) on:02/07/2024  
Replied by DFO (Social Forestry Division Bareilly) on:24/07/2024  
Query raised by Circle (Bareilly Circle Bareilly) on:26/09/2024  
Replied by DFO (Social Forestry Division Bareilly) on:29/11/2024  
Query raised by Circle (Bareilly Circle Bareilly) on:10/03/2025  
Replied by DFO () on:  
Query raised by DFO (Social Forestry Division Bareilly) on:12/10/2020  
Replied by UA on :07/10/2021  
Query raised by DFO (Social Forestry Division Bareilly) on:17/11/2021  
Replied by UA on :28/12/2021  
Query raised by DFO (Social Forestry Division Bareilly) on:29/01/2022  
Replied by UA on :30/05/2024  
Query raised by DFO (Social Forestry Division Bareilly) on:06/07/2024  
Replied by UA on :15/07/2024  
Query raised by DFO (Social Forestry Division Bareilly) on:17/07/2024  
Replied by UA on :18/07/2024  
Query raised by DFO (Social Forestry Division Bareilly) on:01/10/2024  
Replied by UA on :29/11/2024  
NOTE:- Proposal is pending at DFO due to EDS raised by State Government .