TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/UP/Approach/153338/2022              (ii). Name of Project for which Forest Land is required : Proposed BPCL Retail Outlet on Deoria-Kasia Road (SH-79) In Km No. 11, (Ch. No. 100, RHS) At Gata No. – 418, Village: -Sirsia, Tehsil: - Deoria, District: - Deoria              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Proposed Protected forest land to be diverted for Entry/Exit approach to BPCL Retail Outlet on Deoria-Kasia Road (SH-79) In Km No. 11, (Ch. No. 100, RHS) At Gata No. – 418, Village: -Sirsia, Tehsil: - Deoria, District: - Deoria              (iv). State : Uttar Pradesh              (v). Category of the Project : Approach Access              (vi). Shape of forest land proposed to be diverted : Non Linear              (vii). Area of forest land proposed for diversion(in ha.): 0.075028
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/UP/Approach/153338/202210/03/2022aa16/03/2022   29/03/2022 Social Forestry Division Deoria :29/03/2022Gorakhpur Circle Gorakhpur:
  21/06/2022 (Social Forestry Division Deoria)

Uttar Pradesh:
23/08/2022
Uttar Pradesh:
05/04/2023
Lucknow:
24/05/2023
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Lucknow) on:26/06/2023  
Replied by State Government(Uttar Pradesh) on:09/01/2024  
Query raised by Regional Office (Lucknow) on:12/03/2024  
Replied by State Government(Uttar Pradesh) on:21/05/2024  
Query raised by Regional Office (Lucknow) on:01/08/2024  
Replied by State Government(Uttar Pradesh) on:03/09/2024  
Query raised by Regional Office (Lucknow) on:10/10/2024  
Query raised by State Government (Uttar Pradesh) on:27/06/2023  
Replied by Nodal Officer (Uttar Pradesh) on:09/01/2024  
Query raised by State Government (Uttar Pradesh) on:13/03/2024  
Replied by Nodal Officer (Uttar Pradesh) on:21/05/2024  
Query raised by State Government (Uttar Pradesh) on:02/08/2024  
Replied by Nodal Officer (Uttar Pradesh) on:03/09/2024  
Query raised by State Government (Uttar Pradesh) on:15/10/2024  
Query raised by Nodal Officer (Uttar Pradesh) on:26/08/2022  
Replied by Circle(Gorakhpur Circle Gorakhpur) on:20/02/2023  
Query raised by Nodal Officer (Uttar Pradesh) on:25/02/2023  
Replied by Circle(Gorakhpur Circle Gorakhpur) on:31/03/2023  
Query raised by Nodal Officer (Uttar Pradesh) on:03/04/2023  
Replied by Circle(Gorakhpur Circle Gorakhpur) on:05/04/2023  
Query raised by Nodal Officer (Uttar Pradesh) on:28/06/2023  
Replied by Circle(Gorakhpur Circle Gorakhpur) on:25/07/2023  
Query raised by Nodal Officer (Uttar Pradesh) on:25/07/2023  
Replied by Circle(Gorakhpur Circle Gorakhpur) on:31/07/2023  
Query raised by Nodal Officer (Uttar Pradesh) on:31/07/2023  
Replied by Circle(Gorakhpur Circle Gorakhpur) on:28/08/2023  
Query raised by Nodal Officer (Uttar Pradesh) on:04/09/2023  
Replied by Circle(Gorakhpur Circle Gorakhpur) on:08/01/2024  
Query raised by Nodal Officer (Uttar Pradesh) on:14/03/2024  
Replied by Circle(Gorakhpur Circle Gorakhpur) on:20/05/2024  
Query raised by Nodal Officer (Uttar Pradesh) on:05/08/2024  
Replied by Circle(Gorakhpur Circle Gorakhpur) on:02/09/2024  
Query raised by Nodal Officer (Uttar Pradesh) on:16/10/2024  
Replied by Circle() on:  
Query raised by Circle (Gorakhpur Circle Gorakhpur) on:28/06/2022  
Replied by DFO (Social Forestry Division Deoria) on:30/07/2022  
Query raised by Circle (Gorakhpur Circle Gorakhpur) on:06/09/2022  
Replied by DFO (Social Forestry Division Deoria) on:27/01/2023  
Query raised by Circle (Gorakhpur Circle Gorakhpur) on:28/02/2023  
Replied by DFO (Social Forestry Division Deoria) on:18/03/2023  
Query raised by Circle (Gorakhpur Circle Gorakhpur) on:05/04/2023  
Replied by DFO (Social Forestry Division Deoria) on:05/04/2023  
Query raised by Circle (Gorakhpur Circle Gorakhpur) on:28/06/2023  
Replied by DFO (Social Forestry Division Deoria) on:24/07/2023  
Query raised by Circle (Gorakhpur Circle Gorakhpur) on:01/08/2023  
Replied by DFO (Social Forestry Division Deoria) on:16/08/2023  
Query raised by Circle (Gorakhpur Circle Gorakhpur) on:21/09/2023  
Replied by DFO (Social Forestry Division Deoria) on:17/11/2023  
Query raised by Circle (Gorakhpur Circle Gorakhpur) on:14/12/2023  
Replied by DFO (Social Forestry Division Deoria) on:14/12/2023  
Query raised by Circle (Gorakhpur Circle Gorakhpur) on:04/04/2024  
Replied by DFO (Social Forestry Division Deoria) on:30/04/2024  
Query raised by Circle (Gorakhpur Circle Gorakhpur) on:12/08/2024  
Replied by DFO (Social Forestry Division Deoria) on:30/08/2024  
Query raised by Circle (Gorakhpur Circle Gorakhpur) on:23/10/2024  
Replied by DFO (Social Forestry Division Deoria) on:16/11/2024  
Query raised by Circle (Gorakhpur Circle Gorakhpur) on:20/11/2024  
Replied by DFO () on:  
Query raised by DFO (Social Forestry Division Deoria) on:14/07/2022  
Replied by UA on :19/07/2022  
Query raised by DFO (Social Forestry Division Deoria) on:15/09/2022  
Replied by UA on :23/01/2023  
NOTE:- Proposal is pending at DFO due to EDS raised by Regional Office .