TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/UK/WATER/47887/2020              (ii). Name of Project for which Forest Land is required : Bhatad Drinking Water Supply Scheme              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : This scheme will provide drinking water to vill-Bhatad, who are suffering from drinking water problem.              (iv). State : Uttarakhand              (v). Category of the Project : Drinking Water              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 0.067
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/UK/WATER/47887/202029/07/2020aa05/08/2020   07/09/2020 Chakrata :09/09/2020Yamuna:
  01/10/2020 (Chakrata)

Uttarakhand:
08/10/2020
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by Nodal Officer (Uttarakhand) on:28/10/2020  
Replied by Circle(Yamuna) on:19/05/2021  
Query raised by Nodal Officer (Uttarakhand) on:11/06/2021  
Replied by Circle(Yamuna) on:14/12/2021  
Query raised by Circle (Yamuna) on:29/10/2020  
Replied by DFO (Chakrata) on:18/05/2021  
Query raised by Circle (Yamuna) on:16/06/2021  
Replied by DFO (Chakrata) on:18/11/2021  
Query raised by Circle (Yamuna) on:24/11/2021  
Replied by DFO (Chakrata) on:09/12/2021  
Query raised by DFO (Chakrata) on:02/11/2020  
Replied by UA on :23/11/2020  
Query raised by DFO (Chakrata) on:23/11/2020  
Replied by UA on :16/02/2021  
Query raised by DFO (Chakrata) on:16/02/2021  
Replied by UA on :23/02/2021  
Query raised by DFO (Chakrata) on:25/02/2021  
Replied by UA on :06/03/2021  
Query raised by DFO (Chakrata) on:17/03/2021  
Replied by UA on :18/05/2021  
Query raised by DFO (Chakrata) on:21/06/2021  
Replied by UA on :18/11/2021  
NOTE:- Proposal is pending at DFO due to EDS raised by Nodal Officer .
Close(X)
Close(X)
Please wait ...