| Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
|
1
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
05/03/2021
|
The hard copy of the proposal containing original documents is not yet received in this office. The user agency may provide original hard copy of the proposal to this office including authenticated copy of Part I to Part iii as in online web portal.
|
|
|
2
|
CF (North Kumaun)
|
EDS
|
DFO (Almora)
|
06/03/2021
|
The hard copy of the proposal containing original documents is not yet received in this office. The user agency may provide original hard copy of the proposal to this office including authenticated copy of Part I to Part iii as in online web portal.
|
|
|
3
|
DFO (Almora)
|
EDS
|
User Agency (bishan.rautela.bgr@gmail.com)
|
08/03/2021
|
The hard copy of the proposal containing original documents is not yet received in Nodal office. The user agency may provide original hard copy of the proposal to this office including authenticated copy of Part I to Part iii as in online web portal.
|
|
|
4
|
User Agency (bishan.rautela.bgr@gmail.com)
|
REPLY
|
DFO (Almora)
|
10/06/2021
|
The correction have been made as per the instruction received
|
|
|
5
|
DFO (Almora)
|
EDS
|
User Agency (bishan.rautela.bgr@gmail.com)
|
23/06/2021
|
please submit the hard copy of authenticated copy of part I
|
|
|
6
|
User Agency (bishan.rautela.bgr@gmail.com)
|
REPLY
|
DFO (Almora)
|
07/07/2021
|
The correction have been made as per the instruction received
|
|
|
7
|
DFO (Almora)
|
REPLY
|
CF (North Kumaun)
|
20/07/2021
|
as per EDS, correction has been made and related Hard copy will be sent to you with attached letter.
|
|
|
8
|
CF (North Kumaun)
|
EDS
|
DFO (Almora)
|
23/07/2021
|
As per letter no 273/12-1 dated 23-07-2021
|
|
|
9
|
DFO (Almora)
|
EDS
|
User Agency (bishan.rautela.bgr@gmail.com)
|
02/08/2021
|
hard copy of the proposal not received in CF office. please submit hard of the proposal in CF office
|
|
|
10
|
User Agency (bishan.rautela.bgr@gmail.com)
|
REPLY
|
DFO (Almora)
|
04/02/2023
|
The correction have been made as per the instruction received
|
|
|
11
|
DFO (Almora)
|
REPLY
|
CF (North Kumaun)
|
17/02/2023
|
Please find the letter attached.
|
|
|
12
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
13/03/2023
|
As per letter no 2360/12-1 dated 27-02-2023
|
|
|
13
|
Regional Office
|
EDS
|
State secretary
|
28/04/2023
|
State Govt. may attend the following shortcomings as per the attachment here
|
|
|
14
|
State secretary
|
EDS
|
Nodal Officer
|
01/05/2023
|
State Govt. may attend the following shortcomings as per the attachment here
|
|
|
15
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
01/05/2023
|
State Govt. may attend the following shortcomings as per the attachment here
|
|
|
16
|
CF (North Kumaun)
|
EDS
|
DFO (Almora)
|
02/05/2023
|
May attend the following shortcomings as per the attachment here
|
|
|
17
|
DFO (Almora)
|
EDS
|
User Agency (bishan.rautela.bgr@gmail.com)
|
09/05/2023
|
Please find the letter attached.
|
|