| Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
|
1
|
DFO (Mussoorie)
|
EDS
|
User Agency (songdamdehradun19@gmail.com)
|
24/09/2019
|
Pl. objection remove as per mension this office letter N0. 3845/12-1 dated 17-5-2019 & Letter No. 1245/12-1 dated 24-9-2019
|
|
|
2
|
User Agency (songdamdehradun19@gmail.com)
|
REPLY
|
DFO (Mussoorie)
|
20/11/2019
|
The correction have been made as per the instruction received
|
|
|
3
|
DFO (Mussoorie)
|
EDS
|
User Agency (songdamdehradun19@gmail.com)
|
09/12/2019
|
Pl. objection remove as per mension this office letter N0. 3845/12-1 dated 17-5-2019 & Letter No. 1245/12-1 dated 24-9-2019 & letter no. 2228/12-1 dt. 09-12-2019
|
|
|
4
|
User Agency (songdamdehradun19@gmail.com)
|
REPLY
|
DFO (Mussoorie)
|
12/12/2019
|
The correction have been made as per the instruction received
|
|
|
5
|
DFO (Mussoorie)
|
EDS
|
User Agency (songdamdehradun19@gmail.com)
|
16/12/2019
|
Pl. objection remove as per mension this office letter N0. 3845/12-1 dated 17-5-2019 & Letter No. 1245/12-1 dated 24-9-2019 & letter no. 2228/12-1 dt. 09-12-2019. No any correction by User agency in online Part-I as per above EDS letter.
|
|
|
6
|
User Agency (songdamdehradun19@gmail.com)
|
REPLY
|
DFO (Mussoorie)
|
25/12/2019
|
The correction have been made as per the instruction received
|
|
|
7
|
DFO (Mussoorie)
|
EDS
|
User Agency (songdamdehradun19@gmail.com)
|
28/12/2019
|
Proposal retren request by UA for sum query of online proposal.
|
|
|
8
|
User Agency (songdamdehradun19@gmail.com)
|
REPLY
|
DFO (Mussoorie)
|
30/12/2019
|
The correction have been made as per the instruction received
|
|
|
9
|
Nodal Officer
|
EDS
|
CF (Shivalik)
|
03/02/2020
|
find the letter attached
|
|
|
10
|
Nodal Officer
|
EDS
|
CF (Yamuna)
|
03/02/2020
|
find the letter attached
|
|
|
11
|
CF (Yamuna)
|
EDS
|
DFO (Mussoorie)
|
03/02/2020
|
find the letter attached
|
|
|
12
|
DFO (Mussoorie)
|
EDS
|
User Agency (songdamdehradun19@gmail.com)
|
04/02/2020
|
Pl. Pointwise objection remove as per mension Nodal officer letter no. dated 03-02-2020.
|
|
|
13
|
User Agency (songdamdehradun19@gmail.com)
|
REPLY
|
DFO (Mussoorie)
|
04/02/2020
|
The correction have been made as per the instruction received
|
|
|
14
|
DFO (Mussoorie)
|
REPLY
|
CF (Yamuna)
|
11/02/2020
|
Sir. Pointwise objection remove as per Nodal office EDS dt. on 03-02-2020 mansion this office letter no 3323/12-1 dt.10-02-2020.
|
|
|
15
|
CF (Shivalik)
|
EDS
|
DFO (Dehradun)
|
12/02/2020
|
find the letter attached
|
|
|
16
|
DFO (Dehradun)
|
REPLY
|
CF (Shivalik)
|
17/02/2020
|
The asked queries have correct and uploaded to the appropriate place of part-I and Part-II for further action
|
|
|
17
|
CF (Shivalik)
|
REPLY
|
Nodal Officer
|
18/02/2020
|
The Correction have been made as per instructions received.
|
|
|
18
|
CF (Yamuna)
|
REPLY
|
Nodal Officer
|
19/02/2020
|
Reply provided by DFO is attached.
|
|
|
19
|
Nodal Officer
|
EDS
|
CF (Shivalik)
|
02/03/2020
|
find the letter attached
|
|
|
20
|
Nodal Officer
|
EDS
|
CF (Yamuna)
|
02/03/2020
|
find the letter attached
|
|
|
21
|
CF (Shivalik)
|
EDS
|
DFO (Dehradun)
|
02/03/2020
|
find the letter attached
|
|
|
22
|
CF (Yamuna)
|
EDS
|
DFO (Mussoorie)
|
03/03/2020
|
find the letter attached
|
|
|
23
|
DFO (Mussoorie)
|
EDS
|
User Agency (songdamdehradun19@gmail.com)
|
05/03/2020
|
Pl. Pointwise objection remove as per mension Nodal officer letter no. 2257/FU/UK/WATER/40701/2019 dated 05-03-2020 & This office letter No 3660/12-1 dated 5-3-2020.
|
|
|
24
|
User Agency (songdamdehradun19@gmail.com)
|
REPLY
|
DFO (Mussoorie)
|
03/07/2020
|
The correction have been made as per the instruction received
|
|
|
25
|
DFO (Dehradun)
|
EDS
|
User Agency (songdamdehradun19@gmail.com)
|
03/07/2020
|
Plze upload the expected documents required by nodel office and submit herewith for further action
|
|
|
26
|
User Agency (songdamdehradun19@gmail.com)
|
REPLY
|
DFO (Dehradun)
|
03/07/2020
|
The correction have been made as per the instruction received
|
|
|
27
|
DFO (Mussoorie)
|
EDS
|
User Agency (songdamdehradun19@gmail.com)
|
03/07/2020
|
Online proposal return on request by User Agency. Mr. Shani Assisstant Engneer.
|
|
|
28
|
User Agency (songdamdehradun19@gmail.com)
|
REPLY
|
DFO (Mussoorie)
|
03/07/2020
|
The correction have been made as per the instruction received
|
|
|
29
|
DFO (Dehradun)
|
REPLY
|
CF (Shivalik)
|
13/07/2020
|
Sir,
The raised queries have been rectified and accordingly updated online for further action
|
|
|
30
|
DFO (Mussoorie)
|
EDS
|
User Agency (songdamdehradun19@gmail.com)
|
15/07/2020
|
Please reupload the EDS reply of the proposal.
|
|
|
31
|
User Agency (songdamdehradun19@gmail.com)
|
REPLY
|
DFO (Mussoorie)
|
15/07/2020
|
The correction have been made as per the instruction received
|
|
|
32
|
DFO (Mussoorie)
|
REPLY
|
CF (Yamuna)
|
17/07/2020
|
The correction have been made as per the letter attached herewith.
|
|
|
33
|
CF (Yamuna)
|
REPLY
|
Nodal Officer
|
20/07/2020
|
Reply provided by DFO is attached.
|
|
|
34
|
CF (Shivalik)
|
REPLY
|
Nodal Officer
|
23/07/2020
|
The Correction have been made as per instructions received.
|
|
|
35
|
Head Office
|
EDS
|
State secretary
|
09/09/2020
|
EDS
|
|
|
36
|
State secretary
|
EDS
|
Nodal Officer
|
10/09/2020
|
EDS
|
|
|
37
|
Nodal Officer
|
EDS
|
CF (Shivalik)
|
10/09/2020
|
state govt. may attend the following shortcomings as per the attachment here
|
|
|
38
|
Nodal Officer
|
EDS
|
CF (Yamuna)
|
10/09/2020
|
state govt. may attend the following shortcomings as per the attachment here
|
|
|
39
|
CF (Yamuna)
|
EDS
|
DFO (Mussoorie)
|
11/09/2020
|
state govt. may attend the following shortcomings as per the attachment here
|
|
|
40
|
DFO (Mussoorie)
|
EDS
|
User Agency (songdamdehradun19@gmail.com)
|
11/09/2020
|
Attend the shortcomings as per the attachement here.
|
|
|
41
|
User Agency (songdamdehradun19@gmail.com)
|
REPLY
|
DFO (Mussoorie)
|
15/10/2020
|
The correction have been made as per the instruction received
|
|
|
42
|
DFO (Mussoorie)
|
REPLY
|
CF (Yamuna)
|
27/10/2020
|
kindly refer to the letter attached.
|
|
|
43
|
CF (Yamuna)
|
EDS
|
DFO (Mussoorie)
|
27/10/2020
|
kindly review the reply.
|
|
|
44
|
DFO (Mussoorie)
|
REPLY
|
CF (Yamuna)
|
29/10/2020
|
please find the letter attched.
|
|
|
45
|
CF (Yamuna)
|
REPLY
|
Nodal Officer
|
29/10/2020
|
Reply of DFO is attached.
|
|
|
46
|
CF (Shivalik)
|
EDS
|
DFO (Dehradun)
|
30/10/2020
|
state govt. may attend the following shortcomings as per the attachment here
|
|
|
47
|
DFO (Dehradun)
|
REPLY
|
CF (Shivalik)
|
02/11/2020
|
Sir,
The queries have been removed and accordingly uploaded online in part-I and II for futher action
|
|
|
48
|
CF (Shivalik)
|
REPLY
|
Nodal Officer
|
03/11/2020
|
The Correction have been made as per instructions received.
|
|
|
49
|
Nodal Officer
|
REPLY
|
State secretary
|
05/11/2020
|
The Correction have been made as per instructions received.
|
|
|
50
|
State secretary
|
REPLY
|
Head Office
|
05/11/2020
|
The Correction have been made as per instructions received.
|
|