TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/UK/TRANS/154613/2022              (ii). Name of Project for which Forest Land is required : Dedicated 33 KV Transmission Line to Rail Vikas Nigam Limited from Gular Sub Station to Tunnel T2 in Shivpuri Tehri Garhwal District of Uttrakhand              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : The proposed 33 KV transmission line is required exclusively for operation of trains on 126 Km long new BG Rail Between Rishikesh - Karnaprayag (RVNL Project) in the state of Uttarakhand              (iv). State : Uttarakhand              (v). Category of the Project : Transmission Line              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 1.68
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/UK/TRANS/154613/202220/04/2022aa21/04/2022   27/04/2022 Narendranagar,Munikireti :27/04/2022Bhagirathi:
  04/05/2022 (Narendranagar,Munikireti)

Uttarakhand:
02/08/2022
Uttarakhand:
18/08/2022
Dehradun:
08/09/2022
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Dehradun) on:23/09/2022  
Replied by State Government(Uttarakhand) on:03/08/2023  
Query raised by Regional Office (Dehradun) on:29/08/2023  
Replied by State Government(Uttarakhand) on:24/09/2024  
Query raised by Regional Office (Dehradun) on:23/12/2024  
Query raised by State Government (Uttarakhand) on:23/09/2022  
Replied by Nodal Officer (Uttarakhand) on:03/08/2023  
Query raised by State Government (Uttarakhand) on:29/08/2023  
Replied by Nodal Officer (Uttarakhand) on:19/09/2024  
Query raised by State Government (Uttarakhand) on:23/12/2024  
Query raised by Nodal Officer (Uttarakhand) on:23/09/2022  
Replied by Circle(Bhagirathi) on:05/07/2023  
Query raised by Nodal Officer (Uttarakhand) on:29/08/2023  
Replied by Circle(Bhagirathi) on:05/08/2024  
Query raised by Circle (Bhagirathi) on:23/05/2022  
Replied by DFO (Narendranagar,Munikireti) on:13/07/2022  
Query raised by Circle (Bhagirathi) on:06/10/2022  
Replied by DFO (Narendranagar,Munikireti) on:24/06/2023  
Query raised by Circle (Bhagirathi) on:20/09/2023  
Replied by DFO (Narendranagar,Munikireti) on:05/08/2024  
Query raised by DFO (Narendranagar,Munikireti) on:23/05/2022  
Replied by UA on :04/07/2022  
Query raised by DFO (Narendranagar,Munikireti) on:11/10/2022  
Replied by UA on :30/12/2022  
Query raised by DFO (Narendranagar,Munikireti) on:24/05/2023  
Replied by UA on :18/06/2023  
Query raised by DFO (Narendranagar,Munikireti) on:20/09/2023  
Replied by UA on :12/07/2024  
NOTE:- Proposal is pending at Nodal Officer due to EDS raised by Regional Office .
Close(X)