| Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
|
1
|
DFO (Almora)
|
EDS
|
User Agency (eepdalmora@rediffmail.com)
|
16/02/2021
|
proposal is not prepared as per SOP. proper paging also required
|
|
|
2
|
User Agency (eepdalmora@rediffmail.com)
|
REPLY
|
DFO (Almora)
|
17/03/2021
|
The correction have been made as per the instruction received
|
|
|
3
|
DFO (Almora)
|
EDS
|
User Agency (eepdalmora@rediffmail.com)
|
07/08/2021
|
Please submit 4 additional hard copy of the proposal. Hard copy will be sent to CF Office and nodal Office from this office.
|
|
|
4
|
User Agency (eepdalmora@rediffmail.com)
|
REPLY
|
DFO (Almora)
|
17/08/2021
|
The correction have been made as per the instruction received
|
|
|
5
|
DFO (Almora)
|
EDS
|
User Agency (eepdalmora@rediffmail.com)
|
04/09/2021
|
Hard copy of the proposal or received copy of the letter send to nodal office yet not received in this office
|
|
|
6
|
User Agency (eepdalmora@rediffmail.com)
|
REPLY
|
DFO (Almora)
|
08/09/2021
|
The correction have been made as per the instruction received
|
|
|
7
|
DFO (Almora)
|
EDS
|
User Agency (eepdalmora@rediffmail.com)
|
09/09/2021
|
Please submit the 5 authenticated hard copy of online part I
|
|
|
8
|
User Agency (eepdalmora@rediffmail.com)
|
REPLY
|
DFO (Almora)
|
14/09/2021
|
The correction have been made as per the instruction received
|
|
|
9
|
DFO (Almora)
|
EDS
|
User Agency (eepdalmora@rediffmail.com)
|
15/09/2021
|
Please sibmit received copy of the letter by which hard copy has been sent to nodal office
|
|
|
10
|
User Agency (eepdalmora@rediffmail.com)
|
REPLY
|
DFO (Almora)
|
22/09/2021
|
The correction have been made as per the instruction received
|
|
|
11
|
CF (North Kumaun)
|
EDS
|
DFO (Almora)
|
09/11/2021
|
Send 4 more hard copies of the answer to the objection, so that the matter can be sent to the higher level & direct the user agency to collect the returning letter for the proposal with the recommendation of CF North Kumaon and submit the hard copy at the Nodal Office.
|
|
|
12
|
DFO (Almora)
|
EDS
|
User Agency (eepdalmora@rediffmail.com)
|
25/11/2021
|
Send 4 more hard copies of the answer to the objection, so that the matter can be sent to the higher level & direct the user agency to collect the returning letter for the proposal with the recommendation of CF North Kumaon and submit the hard copy at the Nodal Office.
|
|
|
13
|
User Agency (eepdalmora@rediffmail.com)
|
REPLY
|
DFO (Almora)
|
13/04/2022
|
The correction have been made as per the instruction received
|
|
|
14
|
DFO (Almora)
|
REPLY
|
CF (North Kumaun)
|
18/06/2022
|
Please fine the letter attached and hard copy has been send to you.
|
|
|
15
|
Regional Office
|
EDS
|
State secretary
|
02/08/2022
|
State Govt. may attend the following shortcomings as per the attachment here
|
|
|
16
|
State secretary
|
EDS
|
Nodal Officer
|
05/08/2022
|
State Govt. may attend the following shortcomings as per the attachment here
|
|
|
17
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
06/08/2022
|
State Govt. may attend the following shortcomings as per the attachment here
|
|
|
18
|
CF (North Kumaun)
|
EDS
|
DFO (Almora)
|
08/08/2022
|
Do needful action as per the EDS
|
|
|
19
|
DFO (Almora)
|
EDS
|
User Agency (eepdalmora@rediffmail.com)
|
10/08/2022
|
Please do needful as per letter attached.
|
|
|
20
|
User Agency (eepdalmora@rediffmail.com)
|
REPLY
|
DFO (Almora)
|
24/02/2023
|
The correction have been made as per the instruction received
|
|
|
21
|
DFO (Almora)
|
REPLY
|
CF (North Kumaun)
|
01/03/2023
|
correction has been made as per letter attached.
|
|
|
22
|
CF (North Kumaun)
|
EDS
|
DFO (Almora)
|
04/03/2023
|
Hard copy yet not received
|
|
|
23
|
DFO (Almora)
|
REPLY
|
CF (North Kumaun)
|
20/03/2023
|
Correction has been made as per letter attached.
|
|
|
24
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
27/03/2023
|
as per letter no 2659/12-1 dated 23-03-2023
|
|
|
25
|
Nodal Officer
|
REPLY
|
State secretary
|
17/04/2023
|
The correction have been made as per the instruction received
|
|
|
26
|
State secretary
|
REPLY
|
Regional Office
|
17/04/2023
|
The correction have been made as per the instruction received
|
|
|
27
|
Regional Office
|
EDS
|
State secretary
|
28/04/2023
|
State Govt. may attend the following shortcomings as per the attachment here
|
|
|
28
|
State secretary
|
EDS
|
Nodal Officer
|
01/05/2023
|
State Govt. may attend the following shortcomings as per the attachment here
|
|
|
29
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
01/05/2023
|
State Govt. may attend the following shortcomings as per the attachment here
|
|
|
30
|
CF (North Kumaun)
|
EDS
|
DFO (Almora)
|
02/05/2023
|
Do needful action as per EDS
|
|
|
31
|
DFO (Almora)
|
EDS
|
User Agency (eepdalmora@rediffmail.com)
|
09/05/2023
|
please find the letter attached.
|
|
|
32
|
User Agency (eepdalmora@rediffmail.com)
|
REPLY
|
DFO (Almora)
|
09/05/2023
|
The correction have been made as per the instruction received
|
|
|
33
|
DFO (Almora)
|
REPLY
|
CF (North Kumaun)
|
17/05/2023
|
The correction has been made as per letter attached.
|
|
|
34
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
20/06/2023
|
As per letter no 12-1 dated
|
|
|
35
|
Nodal Officer
|
REPLY
|
State secretary
|
26/06/2023
|
The correction have been made as per the instruction received
|
|
|
36
|
State secretary
|
REPLY
|
Regional Office
|
29/06/2023
|
The correction have been made as per the instruction received
|
|
|
37
|
Regional Office
|
EDS
|
State secretary
|
20/07/2023
|
State Govt. may attend the following shortcomings as per the attachment here
|
|
|
38
|
State secretary
|
EDS
|
Nodal Officer
|
21/07/2023
|
State Govt. may attend the following shortcomings as per the attachment here
|
|
|
39
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
04/08/2023
|
State Govt. may attend the following shortcomings as per the attachment here
|
|
|
40
|
CF (North Kumaun)
|
EDS
|
DFO (Almora)
|
18/08/2023
|
State Govt. may attend the following shortcomings as per the attachment here
|
|
|
41
|
DFO (Almora)
|
EDS
|
User Agency (eepdalmora@rediffmail.com)
|
24/08/2023
|
Please find the letter attached and do needful
|
|
|
42
|
User Agency (eepdalmora@rediffmail.com)
|
REPLY
|
DFO (Almora)
|
27/09/2023
|
The correction have been made as per the instruction received
|
|
|
43
|
DFO (Almora)
|
EDS
|
User Agency (eepdalmora@rediffmail.com)
|
03/10/2023
|
please submit eds reply letter with 4 copies in hard copy
|
|
|
44
|
User Agency (eepdalmora@rediffmail.com)
|
REPLY
|
DFO (Almora)
|
04/10/2023
|
The correction have been made as per the instruction received
|
|
|
45
|
DFO (Almora)
|
REPLY
|
CF (North Kumaun)
|
19/10/2023
|
Please find the letter attached and do needful
|
|
|
46
|
CF (North Kumaun)
|
EDS
|
DFO (Almora)
|
19/10/2023
|
send back
|
|
|
47
|
DFO (Almora)
|
REPLY
|
CF (North Kumaun)
|
19/10/2023
|
Please find the letter attached and do needful
|
|
|
48
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
22/11/2023
|
As per letter no 1140/12-1 dated 26-10-2023
|
|
|
49
|
Nodal Officer
|
REPLY
|
State secretary
|
13/12/2023
|
The correction have been made as per the instruction received
|
|
|
50
|
State secretary
|
REPLY
|
Regional Office
|
13/12/2023
|
The correction have been made as per the instruction received
|
|
|
51
|
Regional Office
|
EDS
|
State secretary
|
27/03/2024
|
State Government is requested to attend the shortcomings as per the document attached.
|
|
|
52
|
State secretary
|
EDS
|
Nodal Officer
|
02/04/2024
|
State Government is requested to attend the shortcomings as per the letter attached.
|
|
|
53
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
05/04/2024
|
State Government is requested to attend the shortcomings as per the letter attached.
|
|
|
54
|
CF (North Kumaun)
|
EDS
|
DFO (Almora)
|
06/04/2024
|
Attend the shortcomings as per the letter attached.
|
|
|
55
|
DFO (Almora)
|
EDS
|
User Agency (eepdalmora@rediffmail.com)
|
29/04/2024
|
Please find the letter attached and do needfull
|
|
|
56
|
User Agency (eepdalmora@rediffmail.com)
|
REPLY
|
DFO (Almora)
|
15/07/2025
|
The correction have been made as per the instruction received
|
|
|
57
|
DFO (Almora)
|
REPLY
|
CF (North Kumaun)
|
02/08/2025
|
Correction has been made as per the letter attached.
|
|
|
58
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
05/08/2025
|
As Per Letter No-297/12-1-2
Dated- 01-08-2024
|
|
|
59
|
Nodal Officer
|
REPLY
|
State secretary
|
27/08/2025
|
As per attachment
|
|
|
60
|
State secretary
|
EDS
|
Nodal Officer
|
12/09/2025
|
Kindly re-forward the concerned proposal As the option of sending GOI is not open
|
|
|
61
|
Nodal Officer
|
REPLY
|
State secretary
|
12/09/2025
|
As per attached file
|
|
|
62
|
State secretary
|
REPLY
|
Regional Office
|
23/09/2025
|
As per attachment
|
|