Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
15/04/2021
|
The hard copy of the proposal containing original documents is not yet received in this office. The user agency may provide original hard copy of the proposal to this office including authenticated copy of Part I to Part iii as in online web portal.
|
|
2
|
CF (North Kumaun)
|
EDS
|
DFO (Pithoragarh)
|
15/04/2021
|
The hard copy of the proposal containing original documents is not yet received in this office. The user agency may provide original hard copy of the proposal to this office including authenticated copy of Part I to Part iii as in online web portal.
|
|
3
|
DFO (Pithoragarh)
|
EDS
|
User Agency (eepwdaskote@gmail.com)
|
17/04/2021
|
The hard copy of the proposal containing original documents is not yet received in this office. The user agency may provide original hard copy of the proposal to this office including authenticated copy of Part I to Part iii as in online web portal.
|
|
4
|
User Agency (eepwdaskote@gmail.com)
|
REPLY
|
DFO (Pithoragarh)
|
20/04/2021
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Pithoragarh)
|
REPLY
|
CF (North Kumaun)
|
06/05/2021
|
The correction have been made as per the instruction received
|
|
6
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
13/05/2021
|
The On line objections raised by Reg. Office /Nodal officer on date 15-04-2021 has been clarified by DFO Pithoragarh letter no 4602/12-1 dated 06-05-2021.
|
|
7
|
Regional Office
|
EDS
|
State secretary
|
07/07/2021
|
State Government may attend to the shortcomings mentioned in the attached document.
|
|
8
|
State secretary
|
EDS
|
Nodal Officer
|
12/07/2021
|
State Government may attend to the shortcomings mentioned in the attached document.
|
|
9
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
12/07/2021
|
State Government may attend to the shortcomings mentioned in the attached document.
|
|
10
|
CF (North Kumaun)
|
EDS
|
DFO (Pithoragarh)
|
31/07/2021
|
The proposal is being reverted back through our official letter no. 415/12-1 Dated 28-07-2021 with the intent that it must be submitted back online to the office after complying with all the instructions given in the letter.
|
|
11
|
DFO (Pithoragarh)
|
EDS
|
User Agency (eepwdaskote@gmail.com)
|
02/08/2021
|
plz find enclosed and take necessary action accordingly
|
|
12
|
User Agency (eepwdaskote@gmail.com)
|
REPLY
|
DFO (Pithoragarh)
|
04/01/2022
|
The correction have been made as per the instruction received
|
|
13
|
DFO (Pithoragarh)
|
EDS
|
User Agency (eepwdaskote@gmail.com)
|
10/02/2022
|
Remove objection no. 1
|
|
14
|
User Agency (eepwdaskote@gmail.com)
|
REPLY
|
DFO (Pithoragarh)
|
31/03/2022
|
The correction have been made as per the instruction received
|
|
15
|
DFO (Pithoragarh)
|
REPLY
|
CF (North Kumaun)
|
18/04/2022
|
Objection removed
|
|
16
|
CF (North Kumaun)
|
EDS
|
DFO (Pithoragarh)
|
22/04/2022
|
find the letter attached
|
|
17
|
DFO (Pithoragarh)
|
REPLY
|
CF (North Kumaun)
|
02/05/2022
|
Objection removed.
|
|
18
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
05/05/2022
|
As per letter no 4881/12-1 dated 28-04-2022
|
|
19
|
Nodal Officer
|
REPLY
|
State secretary
|
17/05/2022
|
The correction have been made as per the instruction received
|
|
20
|
State secretary
|
REPLY
|
Regional Office
|
17/05/2022
|
The correction have been made as per the instruction received
|
|
21
|
Regional Office
|
EDS
|
State secretary
|
06/06/2022
|
state Govt. may attend the following shortcomings as per the attachment here
|
|
22
|
State secretary
|
EDS
|
Nodal Officer
|
07/06/2022
|
State Govt. may attend the following shortcomings as per the attachment here
|
|
23
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
08/06/2022
|
State Govt. may attend the following shortcomings as per the attachment here
|
|
24
|
CF (North Kumaun)
|
EDS
|
DFO (Pithoragarh)
|
14/06/2022
|
State Govt. may attend the following shortcomings as per the attachment here
|
|
25
|
DFO (Pithoragarh)
|
EDS
|
User Agency (eepwdaskote@gmail.com)
|
15/06/2022
|
Remove objection as per letter attached.
|
|
26
|
User Agency (eepwdaskote@gmail.com)
|
REPLY
|
DFO (Pithoragarh)
|
25/08/2023
|
The correction have been made as per the instruction received
|
|
27
|
DFO (Pithoragarh)
|
REPLY
|
CF (North Kumaun)
|
06/09/2023
|
objection removed.
|
|
28
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
10/10/2023
|
As per letter no 820/12-1 dated 20-09-2023
|
|
29
|
Nodal Officer
|
REPLY
|
State secretary
|
12/10/2023
|
The correction have been made as per the instruction received
|
|
30
|
State secretary
|
REPLY
|
Regional Office
|
12/10/2023
|
The correction have been made as per the instruction received
|
|
31
|
Regional Office
|
EDS
|
State secretary
|
25/10/2023
|
State Govt. may attend the following shortcomings as per the attachment here
|
|
32
|
State secretary
|
EDS
|
Nodal Officer
|
27/10/2023
|
State Govt. may attend the following shortcomings as per the attachment here
|
|
33
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
01/11/2023
|
State Govt. may attend the following shortcomings as per the attachment here
|
|
34
|
CF (North Kumaun)
|
EDS
|
DFO (Pithoragarh)
|
04/11/2023
|
May attend the following shortcomings as per the attachment here
|
|
35
|
DFO (Pithoragarh)
|
EDS
|
User Agency (eepwdaskote@gmail.com)
|
07/11/2023
|
Remove objection as per letter.
|
|
36
|
User Agency (eepwdaskote@gmail.com)
|
REPLY
|
DFO (Pithoragarh)
|
23/12/2023
|
The correction have been made as per the instruction received
|
|
37
|
DFO (Pithoragarh)
|
REPLY
|
CF (North Kumaun)
|
23/01/2024
|
Objection removed
|
|
38
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
20/02/2024
|
As per letter no 2007/12-1 dated 09-02-2024
|
|
39
|
Nodal Officer
|
REPLY
|
State secretary
|
27/02/2024
|
The correction have been made as per the instruction received
|
|
40
|
State secretary
|
REPLY
|
Regional Office
|
29/02/2024
|
The correction have been made as per the instruction received
|
|
41
|
Regional Office
|
EDS
|
State secretary
|
01/10/2024
|
State Government is requested to submit reply as per the Agenda Item No. 3 of MoM of FRCM attached herewith.
|
|
42
|
State secretary
|
EDS
|
Nodal Officer
|
08/10/2024
|
State Government is requested to submit reply as per the Agenda Item No. 3 of MoM of FRCM attached herewith.
|
|
43
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
04/12/2024
|
User Agency is requested to submit reply as per the Agenda Item No. 3 of MoM of FRCM attached herewith
|
|
44
|
CF (North Kumaun)
|
EDS
|
DFO (Pithoragarh)
|
13/12/2024
|
User Agency is requested to submit reply as per the Agenda Item No. 3 of MoM of FRCM attached herewith
|
|
45
|
DFO (Pithoragarh)
|
EDS
|
User Agency (eepwdaskote@gmail.com)
|
26/12/2024
|
do necessary action as per rec direction.
|
|