Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
Nodal Officer
|
EDS
|
CF (Garhwal)
|
28/01/2021
|
The hard copy of the proposal containing original documents is not yet received in this office. The user agency may provide original hard copy of the proposal to this office including authenticated copy of Part I to Part iii as in online web portal.
|
|
2
|
CF (Garhwal)
|
EDS
|
DFO (Badrinath,Gopeshwar)
|
28/01/2021
|
The hard copy of the proposal containing original documents is not yet received in this office. The user agency may provide original hard copy of the proposal to this office including authenticated copy of Part I to Part iii as in online web portal.
|
|
3
|
DFO (Badrinath,Gopeshwar)
|
EDS
|
User Agency (pwdtharali@gmail.com)
|
28/01/2021
|
The hard copy of the proposal containing original documents is not yet received in this office. The user agency may provide original hard copy of the proposal to this office including authenticated copy of Part I to Part iii as in online web portal.
|
|
4
|
User Agency (pwdtharali@gmail.com)
|
REPLY
|
DFO (Badrinath,Gopeshwar)
|
06/02/2021
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Badrinath,Gopeshwar)
|
REPLY
|
CF (Garhwal)
|
11/02/2021
|
The correction have been made as per the instruction received
|
|
6
|
CF (Garhwal)
|
REPLY
|
Nodal Officer
|
12/02/2021
|
Sir Please received the information this proposal
|
|
7
|
Nodal Officer
|
EDS
|
CF (Garhwal)
|
18/02/2021
|
find the letter attached
|
|
8
|
CF (Garhwal)
|
EDS
|
DFO (Badrinath,Gopeshwar)
|
19/02/2021
|
Sir Please remove the objection
|
|
9
|
DFO (Badrinath,Gopeshwar)
|
REPLY
|
CF (Garhwal)
|
20/02/2021
|
The correction have been made as per the instruction received.
|
|
10
|
CF (Garhwal)
|
REPLY
|
Nodal Officer
|
20/02/2021
|
The correction have been made as per the instruction received.
|
|