Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Pithoragarh)
|
EDS
|
User Agency (eepwdddt@rediffmail.com)
|
12/10/2020
|
Plz complete all documents in the file
|
|
2
|
User Agency (eepwdddt@rediffmail.com)
|
REPLY
|
DFO (Pithoragarh)
|
21/10/2020
|
The correction have been made as per the instruction received
|
|
3
|
CF (North Kumaun)
|
EDS
|
DFO (Pithoragarh)
|
13/01/2021
|
As per letter no 2731/12-1 dated 13-01-2021
|
|
4
|
DFO (Pithoragarh)
|
EDS
|
User Agency (eepwdddt@rediffmail.com)
|
14/01/2021
|
As per letter no 2731/12-1 dated 13-01-2021
|
|
5
|
User Agency (eepwdddt@rediffmail.com)
|
REPLY
|
DFO (Pithoragarh)
|
02/06/2021
|
The correction have been made as per the instruction received
|
|
6
|
DFO (Pithoragarh)
|
REPLY
|
CF (North Kumaun)
|
16/06/2021
|
Correction has been made as per letter.
|
|
7
|
CF (North Kumaun)
|
EDS
|
DFO (Pithoragarh)
|
08/07/2021
|
PLZ DFO forward own signature in letter
|
|
8
|
DFO (Pithoragarh)
|
REPLY
|
CF (North Kumaun)
|
20/07/2021
|
plz find enclosed necessary corrections have been done
|
|
9
|
CF (North Kumaun)
|
EDS
|
DFO (Pithoragarh)
|
31/07/2021
|
The proposal is being reverted back through our official letter no. 415/12-1 Dated 28-07-2021 with the intent that it must be submitted back online to the office after complying with all the instructions given in the letter.
|
|
10
|
DFO (Pithoragarh)
|
EDS
|
User Agency (eepwdddt@rediffmail.com)
|
02/08/2021
|
The proposal is being reverted back through our official letter no. 415/12-1 Dated 28-07-2021 with the intent that it must be submitted back online to the office after complying with all the instructions given in the letter.
|
|
11
|
User Agency (eepwdddt@rediffmail.com)
|
REPLY
|
DFO (Pithoragarh)
|
05/08/2021
|
The correction have been made as per the instruction received
|
|
12
|
DFO (Pithoragarh)
|
EDS
|
User Agency (eepwdddt@rediffmail.com)
|
06/08/2021
|
Please read enclosed letter. And follow the direction as mentioned in letter.
|
|
13
|
User Agency (eepwdddt@rediffmail.com)
|
REPLY
|
DFO (Pithoragarh)
|
24/09/2021
|
The correction have been made as per the instruction received
|
|
14
|
DFO (Pithoragarh)
|
REPLY
|
CF (North Kumaun)
|
11/10/2021
|
all attachment are being sent offline in 4 hard copies.
|
|
15
|
CF (North Kumaun)
|
EDS
|
DFO (Pithoragarh)
|
09/11/2021
|
Send 4 more hard copies of the answer to the objection, so that the matter can be sent to the higher level & direct the user agency to collect the returning letter for the proposal with the recommendation of CF North Kumaon and submit the hard copy at the Nodal Office.
|
|
16
|
DFO (Pithoragarh)
|
REPLY
|
CF (North Kumaun)
|
12/11/2021
|
all copies are already sent to the CF Office
|
|
17
|
CF (North Kumaun)
|
EDS
|
DFO (Pithoragarh)
|
26/11/2021
|
The proposal is being reverted back through our official letter no. 415/12-1 Dated 28-07-2021 with the intent that it must be submitted back online to the office after complying with all the instructions given in the letter.
|
|
18
|
DFO (Pithoragarh)
|
REPLY
|
CF (North Kumaun)
|
21/12/2021
|
objections have been removed
|
|
19
|
CF (North Kumaun)
|
EDS
|
DFO (Pithoragarh)
|
12/01/2022
|
The proposal is being reverted back through our official letter no. 415/12-1 Dated 28-07-2021 with the intent that it must be submitted back online to the office after complying with all the instructions given in the letter.
|
|
20
|
DFO (Pithoragarh)
|
REPLY
|
CF (North Kumaun)
|
23/02/2022
|
objection removed
|
|
21
|
CF (North Kumaun)
|
EDS
|
DFO (Pithoragarh)
|
22/03/2022
|
The proposal is being reverted back through our official letter no. 415/12-1 Dated 28-07-2021 with the intent that it must be submitted back online to the office after complying with all the instructions given in the letter.
|
|
22
|
DFO (Pithoragarh)
|
EDS
|
User Agency (eepwdddt@rediffmail.com)
|
25/03/2022
|
The proposal is being reverted back through our official letter no. 415/12-1 Dated 28-07-2021 with the intent that it must be submitted back online to the office after complying with all the instructions given in the letter.
|
|
23
|
User Agency (eepwdddt@rediffmail.com)
|
REPLY
|
DFO (Pithoragarh)
|
01/04/2022
|
The correction have been made as per the instruction received
|
|
24
|
DFO (Pithoragarh)
|
EDS
|
User Agency (eepwdddt@rediffmail.com)
|
12/04/2022
|
plz submit 4 hard copies of the Land transfer proposal to CF office.
|
|
25
|
User Agency (eepwdddt@rediffmail.com)
|
REPLY
|
DFO (Pithoragarh)
|
07/05/2022
|
The correction have been made as per the instruction received
|
|
26
|
DFO (Pithoragarh)
|
REPLY
|
CF (North Kumaun)
|
17/06/2022
|
Hard copies has been sent to
CF office.
|
|
27
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
20/08/2022
|
find the letter attached
|
|
28
|
CF (North Kumaun)
|
EDS
|
DFO (Pithoragarh)
|
22/08/2022
|
find the letter attached
|
|
29
|
DFO (Pithoragarh)
|
EDS
|
User Agency (eepwdddt@rediffmail.com)
|
25/08/2022
|
plz remove objection.
|
|
30
|
User Agency (eepwdddt@rediffmail.com)
|
REPLY
|
DFO (Pithoragarh)
|
02/05/2023
|
The correction have been made as per the instruction received
|
|
31
|
DFO (Pithoragarh)
|
EDS
|
User Agency (eepwdddt@rediffmail.com)
|
06/05/2023
|
plz send hard copies also after removing the objections.
|
|
32
|
User Agency (eepwdddt@rediffmail.com)
|
REPLY
|
DFO (Pithoragarh)
|
01/06/2023
|
The correction have been made as per the instruction received
|
|
33
|
DFO (Pithoragarh)
|
REPLY
|
CF (North Kumaun)
|
24/07/2023
|
objection removed.
|
|
34
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
07/05/2024
|
AS per letter no 2901/121 dated 04-05-2024
|
|
35
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
03/06/2024
|
find the letter attached
|
|
36
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
04/06/2024
|
plz attached encloser
|
|
37
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
21/08/2024
|
Plz upload the hard copy of the encloser
|
|
38
|
CF (North Kumaun)
|
EDS
|
DFO (Pithoragarh)
|
28/08/2024
|
As per letter no 530/12-1 dated 23-08-2024
|
|
39
|
DFO (Pithoragarh)
|
REPLY
|
CF (North Kumaun)
|
20/09/2024
|
Objection removed.
|
|
40
|
CF (North Kumaun)
|
EDS
|
DFO (Pithoragarh)
|
04/10/2024
|
as per Letter no-835/12-1-2
Dated - 27.09.2024
objection not removed
|
|
41
|
DFO (Pithoragarh)
|
EDS
|
User Agency (eepwdddt@rediffmail.com)
|
19/10/2024
|
remove objection
|
|
42
|
User Agency (eepwdddt@rediffmail.com)
|
REPLY
|
DFO (Pithoragarh)
|
08/11/2024
|
The correction have been made as per the instruction received
|
|
43
|
DFO (Pithoragarh)
|
REPLY
|
CF (North Kumaun)
|
19/11/2024
|
objection has been removed.
|
|
44
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
30/11/2024
|
As Per Letter No-1273/12-1(2)
Dated- 25/11/2024
|
|