A. General Details
  (i). Proposal No. : FP/UK/ROAD/46968/2020              (ii). Name of Project for which Forest Land is required : Narayanbagar-Kimoli Motor Road Km. 8 to Nani Malli, Musaudiyar-Boonga Motor Road.              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : For construction of Narayanbagar-Kimoli Motor Road Km. 8 to Nani Malli, Musaudiyar-Boonga Motor Road the proposed alignment is suitable for all means. No other alignment is suitable for above road. Therefore the proposed forest land is required.              (iv). State : Uttarakhand              (v). Category of the Project : Road              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 4.346
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/UK/ROAD/46968/202002/07/202008/07/2020   26/08/2020   02/09/2020   09/10/2020 Badrinath,Gopeshwar :12/10/2020Garhwal:
  16/04/2024 (Badrinath,Gopeshwar)

  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by Circle (Garhwal) on:30/04/2024  
Replied by DFO (Badrinath,Gopeshwar) on:01/07/2024  
Query raised by Circle (Garhwal) on:09/07/2024  
Replied by DFO () on:  
Query raised by DFO (Badrinath,Gopeshwar) on:23/10/2020  
Replied by UA on :18/01/2021  
Query raised by DFO (Badrinath,Gopeshwar) on:11/02/2021  
Replied by UA on :10/08/2021  
Query raised by DFO (Badrinath,Gopeshwar) on:26/08/2021  
Replied by UA on :17/11/2021  
Query raised by DFO (Badrinath,Gopeshwar) on:15/12/2021  
Replied by UA on :16/02/2022  
Query raised by DFO (Badrinath,Gopeshwar) on:25/04/2022  
Replied by UA on :29/09/2022  
Query raised by DFO (Badrinath,Gopeshwar) on:17/01/2023  
Replied by UA on :19/04/2023  
Query raised by DFO (Badrinath,Gopeshwar) on:25/05/2023  
Replied by UA on :08/12/2023  
Query raised by DFO (Badrinath,Gopeshwar) on:13/03/2024  
Replied by UA on :14/03/2024  
Query raised by DFO (Badrinath,Gopeshwar) on:22/07/2024  
Replied by UA on :27/07/2024  
NOTE:- Proposal is pending at DFO due to EDS raised by CF .